You are on page 1of 50

LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

LECTURE 2
INTRODUCTION TO GROUND
IMPROVEMENT
PROF. Ir. DR. HJ. RAMLI NAZIR
TROPICAL GEOENGINEERING CENTRE,
UNIVERSITI TEKNOLOGI MALAYSIA

INSPIRING CREATIVE AND INNOVATIVE MINDS

INTRODUCTION

• What is Ground Rehabilitation and its purpose ?

• A technique that improves the engineering properties of the treated soil


mass.

• Why do we need Ground Rehabilitation ?


• Due to rapid infrastructure development, there is going to be scarcity of
useful land. The general practice of contractors is to take up construction
work only on normal useful lands.

1
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Never Get Mix Up !!!

 Ground Improvement

 Where poor ground conditions make traditional forms of construction expensive, it may be
economically viable to attempt to improve the engineering properties of the ground before
building on it. This can be done by reducing the pore water pressure, by reducing the volume
of voids in the soil, or by adding stronger materials.

 Ground Treatment

 Ground Treatment is an operation that consists in mixing naturally occurring soil with other
materials. By improving its characteristics it allows use of a soil that was unsuitable in its
natural state. In addition, this technique helps protect the environment: by using on-site
materials, rare natural resources are safeguarded (massive rock formations) and sources of
harm and stress are reduced.

 Ground Reinforcement

 Soil reinforcement is the act of improving soil strength to enable it support or carry more load.
Two common examples are:

1) Mixing a soil amendment such as lime or Cement or gravel into weak clayey soil
and recompacting (to form column) to improve soil bearing capacity (often done
under the road base in highway construction)

2) Installing plastic or composite webbing layers (called geogrid material) alternating


with compacted soil or putting reinforcement such as anchor, nails etc. to produce
a stronger sloped soil structure (often done on steep roadway embankments to
improve strength and stability).

2
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Principle of ground Improvement

• Every technique should lead to an increase of soil shear strength,


a reduction of soil compressibility and a reduction of soil
permeability.

• The choice of ground improvement technique depends on


geological formation of the soil, soil characteristics, cost,
availability of backfill material and experience in the past.

• According to Bergado et al. (1996) they can be divided broadly into two categories.

• The first category includes techniques which require foreign materials and utilisation of
reinforcements.

• They are based on stiffening columns either by the use of a granular fill (stone columns),
by piling elements which are not reaching a still soil stratum (creep piles) or by in situ
mixing of the soil with chemical agents (deep stabilisation).

• The second category includes methods which are strengthening the soil by dewatering,
i.e. preloading techniques often combined with vertical drains.

3
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Type of Ground rehabilitation

WHY NEED GROUND


IMPROVEMENT?

4
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

CHICKEN AND EGG


PROBLEM

Dilemma in GROUND IMPROVEMENT

2. Well, do you want 1. Doc, can you


me to open up guarantee I have
everything, big or 100% fix of all my
small one, to check problems?
for fixing.

3. Doc, his credit


card limit is up to
RM50,000 only.

10

5
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Why need ground improvement?

• To fulfill settlement criteria


Double track - Settlement < 25mm over 6 months after CPC,
Highway - Settlement < 400mm for the first 7 years of service

Double track - 10mm differential settlement over 10m chord


Highway - 20mm differential settlement over 10m chord near structure for the first 7
years of service

• To enhance stability of embankment and prevent collapse

• Normally at soft ground area

Differential Settlement

6
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

7
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Consolidation

• Additional load (fill)


• Fine grain soil
• Low permeability
• Consolidation settlement

Fill Dh
Fill
Clay Layer Clay Layer
V1 V2
V1 > V 2

8
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Piston

Terzaghi’s Theory of Consolidation


Spring Water
(a) (b) (c)

(a) (b) (c)

Consolidation Mechanism

dh

9
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

CHOICES OF GROUND
IMPROVEMENT

10
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Ground improvement methods


• Temporary surcharge
• Prefabricated vertical drains
• Excavate and replacement
• Counterweight berm
• Basal reinforcement
• Piled embankments
• Stone column

Temporary surcharge

11
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Temporary Surcharge

Finish Surcharge
Level
Embankment
Embankment

Soft Soil

EMBANKMENT

Construction Surcharge Service Life of


Duration Embankment
Vertical Pressure from
Embankment Loading

Surcharge

Permanent
Loading

Log
Time

Log
Time

Permanent
Loading Only
Settlement

Service
Life
Primary Secondary Settlement
Consolidation Consolidation without
Permanent & Surcharge
Surcharge
Loading

12
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Prefabricated Vertical Drains


(PVD)

13
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Prefabricated Vertical Drains


(PVD)

• Commonly used to accelerate the rate of


consolidation and is use in conjunction with
surcharging

• Successfully used worldwide

• Cost effective (RM1.10 to 1.30 per m)

• PVD will not improve the subsoil shear strength at


time of installation

Drainage Path for Consolidation

2 HD 1m 10m
t  HD
HD 100
t 1
100
times
faster!

14
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

15
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

PREFABRICATED VERTICAL DRAINS

16
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

SMEAR
EFFECT

17
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

PVD can not


penetrate material
with SPTN value of 7
to 10 (depending on
machine capacity)

18
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Vacuum preloading with PVD

19
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Excavate and Replace

Excavate and Replacement

• To remove unsuitable and backfill with approved suitable/granular


material

- Organics
- High plasticity clays
• To reduce settlement

• To increase subsoil shear strength

20
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Excavate and Replace

Soil Replacement

Proper Way for Excavation

EGL Excavation
Backfill for
Depth = D D construction
access or
working
platform

**The required excavation depth shall not be measured from


backfill for construction access or working platform
EGL
Backfill for
construction
access or
D working
platform

**The required excavation depth shall be measured from EGL.

21
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Typical Cross Section

Temporary Sheet Pile


(Precaution measure)

Existing live
tracks

Effect of E&R on Subsoil Settlement

For a soft clay of 15m


thick under 2m high
embankment.

The subsoil settlement is reduced by 27% to 60%

22
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Counterweight Berm
(for Stability of Embankment)

Counterweight Berm

• To improve the stability of the embankment

• Additional fill is required

• Additional space (land area) required

23
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Counterweight Berm…

FOS b > FOS a


Counterweight
Berm Embankment

Soft
Layer FOS a = Not Sufficient =
can Fail
Firm FOS b = Better
Strata

WRONG SEQUENCE OF CONSTRUCTION

Surcharge level

2
3 1

WRONG = DANGEROUS = WILL FAIL

24
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Construction of Counterweight Berm

Surcharge level

2
1 1

CORRECT !!!! = SAFE


Together with Embankment to height of BERM

Geotextile
BASAL REINFORCEMENT

25
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Basal Reinforcement

• To enhance embankment stability against failure

• Strength will deteriorate when exposed to sunlight

• The primary direction (MD) shall be perpendicular to


the proposed track

• Geotextile WHOLE LENGTH across the


embankment SHALL BE ONE PIECE (DO NOT
ALLOW JOINTS)

• Design strength = 0.5 x ultimate strength

26
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Basal Reinforcement

Basal Reinforcement
(One continuous
piece with no joint)

Basal Reinforcement

Primary Direction (in


Roll Directiron)

Pulling Pulling

Higher strength
Difficult to Pull Open

27
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Basal Reinforcement

Primary Direction
Pulling
Pulling

Displacement of geotextile
-low strength  EASY to
SEPARATE by Pulling

Step 1 – Lay basal reinforcement

28
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Step 1 – Lay basal reinforcement

Lay
geotextile
in primary
direction

Step 1 – Lay basal reinforcement

Lay
geotextile
in primary
direction

29
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Step 1 – Lay basal reinforcement

Lay
geotextile
in primary
direction

Step 1 – Lay basal reinforcement

Lay
geotextile
in primary
direction

30
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Step 1 – Lay basal reinforcement

Lay
geotextile
in primary
direction

Step 1 – Finished lay basal reinforcement

31
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Step 2 –Fill with appropriate material and


proper compaction

Step 2 –Fill with appropriate material and


proper compaction

32
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Step 2 –Fill with appropriate material and


proper compaction

Fill up to
surcharge level

WRONG !!!!
Basal reinforcement
SHALL NOT be connected
by stitching in Primary
Direction. Primary
direction

33
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Primary
direction

WRONG !!!!
Basal reinforcement SHALL
NOT be connected by
stitching in Primary
Direction.

WRONG !!!!
Bad Handling of Basal
reinforcement  BREAK
in Primary Direction

34
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Good Practice (proper cover)

 GOOD !
 Proper storage of basal reinforcement –
covered with plastic sheet

BAD Practice (No proper cover)

 BAD !!!
 Improper storage of basal reinforcement
and the basal reinforcement also exposed
to sunlight prior to installation
 Cause loss of Strength (BAD)

35
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Piled Embankment

Piled Embankment

• Design philosophy
- Design as a type of ground improvement works

• Design criteria
The FOS for pile is 1.5

• Embankment filling can be fast.

36
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Piled Embankment

Embankment

Compressible
Layer

Firm
Strata

37
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Must do proper curing 


ALWAYS WET (with WATER)

38
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Final Profile

Abutment
Long Term
Profile
O.G.L.

Pile

Final Profile

Abutment
Long Term
Profile

O.G.L.

Pile Approach
Slab

Transition Embankment
Piles

39
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Stone Column

Stone columns

• To model as composite soil

• Not suitable for undrained shear strength less than 10kPa

• Adequate fill height is required to prevent “mushroom” effect =


large differential settlement  more than 2.5m high

• Availability of aggregate

• Filling speed must be controlled


to prevent Failure

40
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

MECHANISM OF STONE
COLUMN

Sand platform

Sand
Soft clay platform
2 – 3D
Soft clay

Stone
column Stone
D column
D

Firm strata Firm strata

41
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Bulging & General


Shear

Soil Arching
Large pile spacing Inadequate fill
thickness
Unsuitable fill materials

42
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Mushroom Effect

Fig. 7. ‘Mushrooms’ and undulating surface on expressway.

MAIN

Mushrooms

43
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Schematic of wet top feed method

Soft clay

Very soft clay

Soft clay

Schematic of dry bottom feed method

44
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

STONE COLUMNS

Top feed / Wet Method Bottom feed / Dry Method

LOOSE SAND – NEED


IMPROVEMENT?

45
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

46
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Ground improvement for Culvert

Culvert – Shall sit on piles???

47
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

EXPENSIVE SOLUTIONS!!!!

Piled Culvert

How to solve this problem???

• Ground improvement at culvert area shall follow ground improvement


at adjacent area
• Complete ground improvement first, then construct culvert
• Temporary culvert required
• Oversize culvert

48
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

Main Considerations for Ground


improvement

• Technical Suitability

• Practicality and Availability of material

• Cost effectiveness

• Time effectiveness – shorter construction time

• Soil and groundwater conditions

Ranking of improvement Method


Method Cost Time Priority
Modification of Embankment v.low v.short 1
Geometry
Soft Soil Replacement v.low long 2
Surcharging low v.long 4
Staged Construction low v.long 3
Surcharge + Vertical Drains medium medium 5
Geosynthetics Reinforcement medium short 6

Piled Embankment high medium 7


Lightweight Fills high v.short 9
Vacuum Preloading v.high short 8
Stone Column v.high long 10
Jet Grouting v.high long 11

49
LECTURE 2 INTRODUCTION TO GROUND IMPROVEMENT

END OF LECTURE 2

50

You might also like