Professional Documents
Culture Documents
17
17
17
2023 REVISED RULES FOR THE ISSUANCE OF
CERTIFICATES OF COMPLIANCE FOR GENERATION
FACILITIES (2023 REVISED COC RULES)
ARTICLE I
GENERAL PROVISIONS
(qqq) “Republic Act No. 9136 (R.A. No. 9136)” refers to the
Electric Power Industry Reform Act of 2001 otherwise
known as “An Act Ordaining Reforms in the Electric Power
Industry, Amending for the Purpose Certain Laws and for
Other Purposes”.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 11 of 59
(ttt) “Small Grid Owner (SGO)” refers to the party that owns the
backbone transmission or sub-transmission or
Distribution System, and responsible for planning,
operations and maintaining adequate capacity.
(gggg) “WESM Rules” refer to the detailed rules that govern the
administration and operation of the WESM.
5Providing for the Amendments to Rule 29 Part (A) of the Implementing Rules and Regulations of
Republic Act No. 9136.
17 Series of 2023
Resolution No. _____,
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 13 of 59
3.1 General
3.1.2. The application for a COC or PAO shall be in the name of the
person(s) or entity(ies) owning and operating the Generation
Facilities used in the Generation of Electricity. For purposes of
this Section, the person or entity owning the Generation Facility
is understood to be the person or entity having legal title to the
same. In such case, such person or entity shall apply for the COC
or PAO, and the COC or PAO shall be issued, subject to the
provisions below:
3.1.3. A COC or PAO shall be secured from the ERC before the
Commercial Operation of the Generation Facility/Generating
Unit(s).
6Supplementing Department Circular No. DC2021-06-0013 on the Framework Governing the Test
and Commissioning of Generation Facilities for Ensuring Readiness to Deliver Energy to the Grid
or Distribution Network.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 15 of 59
3.1.4. The COC or PAO shall stipulate all the obligations of the
grantee(s) consistent with the standards and operating
guidelines established herein and which the ERC may require
from time to time.
(a) The terms and conditions of the COC or PAO and the
technical specification of the Generation Facilities,
including, but not limited to, the Rated Capacity (MW),
Dependable Capacity (MW), Maximum Load (Pmax in
MW), Minimum Stable Loading (Pmin in MW), Ramp Up
Rate (MW/min), Ramp Down Rate (MW/min), shall be
contained in a document which is made an integral part of
the issued COC or PAO.
3.1.5. The COC or PAO for GenCos shall be issued in accordance with
the “Standard Grid Interconnection Variants” under ERC
Resolution No. 23, Series of 2016 otherwise known as “A
Resolution Adopting Amended Rules on the Definition and
Boundaries of Connection Assets for Customers of
Transmission Providers,” and any amendments thereto.
3.2 QE
3.3 DER
ARTICLE II
QUALIFICATIONS OF COC APPLICANTS
(c) This limitation shall not also apply to MGSPs, Entities with
SGF, QE, and Entities with DER.
ARTICLE III
REQUIREMENTS AND PROCEDURES
Section 7. In General.
7.3 The ERC shall act on the application within sixty (60) calendar
days from receipt of the complete application, which includes the
submission of all documentary requirements and the conduct of
the technical inspection.
8.1 GenCos and MGSPs shall submit the COC or PAO pre-filing
requirements at least thirty (30) calendar days before the date of
Test and Commissioning. A certification for pre-filing shall be
issued by the ERC upon complete submission of the listed pre-
filing requirements under Section 9.1 hereof.
8.2 The application for new COC or PAO of GenCos and MGSPs must
be filed no later than thirty (30) calendar days from the last day of
the Test and Commissioning and must be accompanied by the
requirements under Sections 9.2 or 10 hereof, for COC
applications or PAO applications, respectively.
8.3 The application for COC for SGF and DER shall be filed no later
than thirty (30) calendar days from the last day of the Test and
Commissioning period.
8.4 In the case of a COC application for QEs, the procedure under the
Amended Net Metering Rules shall be followed.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 22 of 59
8In cases where the submitted document is issued to a different entity, other than the GenCo or
MGSP, a written explanation must be submitted explaining the relationship of that entity to the
GenCo or MGSP, accompanied with supporting documents that would substantiate the
explanation.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 23 of 59
9 Must be any form of application through online, duly acknowledged by the concerned agency or
walk in stamped received by the concerned agency.
10 The DU and the MGSP shall come to an agreement on the use of existing facilities and distribution
system in the area awarded to the MGSP, either by way of sale, lease, or usufruct or any other
manner, during the term of the MGSP without jeopardizing the affordability of electricity rates in
the said area.
11 Submission of first page of Application with Docket No. Applicable for GenCos who develop, own
of public offering being considered, the succeeding steps to be undertaken and the tentative
timeline for such steps.
16 Must be consistent with the capacity of the generator nameplate rating.
17 In accordance with the Memorandum Circular 005, July 2014, otherwise known as “Revised
Guidelines for Coverage Screening and Standardized Requirements under the Philippine EIS
System,” and any amendments thereto (MC 005-2014).
18 In accordance with Section 1, Rule XIX, Part VI of the Implementing Rules, and Regulations
(IRR) for R.A. No. 8749, otherwise known as “The Philippine Clean Air Act of 1999,” and any
amendments thereto (R.A. No. 8749-IRR); Applicable for Oil-Based, Coal, Biomass, Geothermal,
and Natural Gas Generation Facilities except for Standby stationary/portable/mobile/multi-
purpose Generator set engines (1-15kW) used in small scale operation (e.g., tower light, air
compressors, pumps etc.).
19 Required only for generation facilities that utilizes water for power generation, commercial and
industrial purposes.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 26 of 59
Indigenous Peoples Rights Act of 1997” (IPRA), which reads “Certification Precondition. - all
department and other governmental agencies shall henceforth be strictly enjoined from issuing,
renewing, or granting any concession, license or lease, or entering into any production-sharing
agreement, without prior certification from the NCIP that the area affected does not overlap with
any ancestral domain. Such certificate shall only be issued after a field based investigation is
conducted by the Ancestral Domain concession, license, lease, or production sharing agreement
while there is pending application CADT: Provided, finally, That the ICCs/IPs shall have the right
to stop or suspend, in accordance with this Act, any project that has not satisfied the requirement
of this consultation process”. A Certificate of Non-Overlap (CNO) issued by NCIP must be
submitted if the area of the Generation Facility is patently outside and will not affect any ancestral
domain.
23 In cases where the submitted document is issued to a different entity, other than the GenCo or
MGSP, a written explanation must be submitted explaining the relationship of that entity to the
GenCo or MGSP, accompanied with supporting documents that would substantiate the
explanation.
24Updated COC Form No. 1 including the GUCT Results and actual date of Test and Commissioning.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 27 of 59
DOE
25 The DU shall ensure that under Section 4.3.3.7 of the PDC 2017 Edition and the DOE DC 2021-
06-0013 are complied with prior to issuance of FCATC.
26 Not applicable for Generation Facilities operating in the Off-Grid Area and Embedded
Generators below the regional threshold per DOE DC No. DC2019-002-003, and any amendments
thereto.
27 Applicable for GenCos who developed, owned and/or operate dedicated point-to-point limited
(ii) PTO;30
NWRB
(iv) WP.32
29 The proof of establishment of TA by the GenCo for electrification fund (EF), development and
livelihood fund (DLF) and reforestation, watershed management, health and/or environmental
enhancement fund (RWMHEEF) shall be submitted together with the MOA (e.g. Bank Certification
on the establishment of said Trust Accounts or Bank Statement). The applicability of execution or
non-execution of MOA with ICCs/ IPs shall be made in accordance and observance of R.A. No. 8371
otherwise known as IPRA and/or related rules as well as related issuance(s) of NCIP.
30 In accordance with Section 1, Rule XIX, Part VI of the R.A. No. 8749-IRR. Applicable for oil-
based, coal, biomass, geothermal, and natural gas Generation Facilities except for standby
stationary/portable/mobile/multi-purpose generator set engines (1-15kW) used in small scale
operation (e.g., tower light, air compressors, pumps etc.).
31 Required only for generation facilities that utilizes water for power generation, commercial and
industrial purposes.
32 For power generation, commercial and industrial purposes.
33 In cases where the submitted document is issued to a different entity, a written explanation must
be submitted explaining the relationship of that entity to the entity with SGF, accompanied with
supporting documents that would substantiate the explanation.
34 In accordance with Section 1, Rule XIX, Part VI of the R.A. No. 8749-IRR; Applicable for oil-
based, coal, biomass, geothermal, and natural gas Generation Facilities except for standby
stationary/portable/mobile/multi-purpose generator set engines (1-15kW) used in small scale
operation (e.g., tower light, air compressors, pumps etc.).
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 29 of 59
(iii) SEC issued COR with AOI/AOP and By-Laws, and all
subsequent amendments thereto, or Business Name
Registration Certificate (for Single Proprietorship),
whichever is applicable;
37 In accordance with Section 1, Rule XIX, Part VI of the R.A. No. 8749-IRR; Applicable for oil-
based, coal, biomass, geothermal, and natural gas Generation Facilities except for standby
stationary/portable/mobile/multi-purpose Generator set engines (1-15kW) used in small scale
operation (e.g. tower light, air compressors, pumps etc.).
38 In accordance with MC 005-2014.
39 In accordance with Section 1, Rule XIX, Part VI of the R.A. No. 8749-IRR. Applicable for oil-
based, coal, biomass, geothermal, and natural gas Generation Facilities except for standby
stationary/portable/mobile/multi-purpose generator set engines (1-15kW) used in small scale
operation (e.g., tower light, air compressors, pumps etc.).
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 31 of 59
(h) POR;45
(i) Renewed BP for issued by the LGU for its Principal Office
and/or BP issued by the LGU where the Generation Facility
is located;
below the regional threshold per DOE DC No. DC2019-002-003, and any amendments thereto.
43 Applicable for GenCos who developed, owned and/or operate dedicated point-to-point limited
Based, Coal, Biomass, Geothermal, and Natural Gas Generation Facilities except for Standby
stationary/portable/mobile/multi-purpose Generator set engines (1-15kW) used in small scale
operation (e.g., tower light, air compressors, pumps etc.).
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 32 of 59
48 Required only for generation facilities that utilizes water for power, generation, Commercial and
industrial purposes.
49 For power generation, commercial and industrial purposes.
50 For existing Grid-connected generation facilities that were not issued with FCATC nor PCATC,
at least the Compliance Plan for the issuance of Certificate of PGC and OATS Rules Compliance
stamped received by TNP must be submitted. The Certificate of PGC and OATS Rules Compliance
is the alternative document for FCATC issued by the TNP.
51 Applicable for Generation Facilities which are AS provider.
52 Not applicable for Generation Facilities operating in the Off-Grid Area and Embedded Generators
below the regional threshold per DOE DC No. DC2019-002-003, and any amendments thereto.
53 Applicable for GenCos who developed, owned and/or operate dedicated point-to-point limited
financial benchmark.
55 Applicable for GenCos which has other business segment.
17 Series of 2023
Resolution No. _____,
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 33 of 59
For new generation facilities applying for new PAOs, the GenCo and
MGSP shall also submit the pre-filing requirements listed under
Section 9.1 hereof, as well as the requirements stated under Section 9.2
56 The establishment of Trust Accounts shall be in accordance with DOE Circular 2018-08-0021,
including Section 7.4 thereof. Further, the applicability of execution or non-execution of MOA with
ICCs/IPs shall be made in accordance and observance of R.A. No. 8371 or IPRA and/or related rules
as well as related issuance(s) of NCIP.
57 In accordance with MC 005-2014.
58 In accordance with Section 1, Rule XIX, Part VI of the R.A. No. 8749-IRR. Applicable for oil-based,
coal, biomass, geothermal, and natural gas Generation Facilities except for standby/stationary
/portable/ mobile/ multi-purpose generator set engines (1-15kW) used in small scale operation
(e.g., tower light, air compressors, pumps etc.).
59 Required only for generation facilities that utilizes water for power, generation, Commercial and
industrial purposes.
60 For power generation, commercial and industrial purposes.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 34 of 59
The PAO shall be issued in the form of a letter to the applicant and shall
be valid for a period of one (1) year from issuance thereof.
11.1 If the GenCo or MGSP cannot yet comply with the requirements
and conditions of the issued PAO, it shall file an application for
extension of PAO not later than sixty (6o) calendar days prior to
the expiration of the existing PAO, with a written verified
explanation as to the efforts undertaken to comply with the
requirements, and the reasons for their continued failure to
comply with all the requirements for COC issuance. The substitute
requirements stated Section 10 hereof shall be submitted by
GenCo and MGSP applicants for the requirements and conditions
that remain unavailable as of submission of the application for
PAO extension.
11.2 For application for extension of PAO filed in accordance with the
60-day period provided in these Rules, the extended PAO shall be
deemed to have been issued on the day immediately following the
expiration of the previously issued PAO, and the extended one (1)
year term shall be reckoned from such date.
11.3 If the application for extension of PAO was filed beyond the 60-
day period provided under these Rules, a new PAO shall be issued
by the ERC valid for a period of one (1) year effective from the date
of approval. As such, the subject facility shall be deemed to have
operated without a PAO from the date the same is deemed to have
expired, until prior to the issuance of the subject PAO extension.
Appropriate sanctions shall be imposed according to the rules of
the ERC for late filing and operating without a valid COC for the
period that is not covered by the new PAO.
11.4 The grant of PAO shall be limited to five (5) consecutive issuances,
which shall commence on the grant of PAO in accordance with
these 2023 Revised COC Rules.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 35 of 59
(i) PGC, PDC, PSGG, PEC, and WESM Rules and Manual
Requirements:
61 The DU shall ensure that under Section 4.3.3.7 of the PDC 2017 Edition and the DOE DC 2021-
06-0013 are complied with prior to issuance of FCATC.
62 Applicable if the amendment includes the change in the Pmax, Pmin and Ramp Rates.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 36 of 59
DOE
63 Must be consistent with the capacity of the generator nameplate rating and is applicable if there
is variance between the nameplate capacity and the capacity reflected in the previous issued COE.
64 Applicable for Partial Generating Unit Mothballing or Decommissioning.
65 Applicable if the capacity in the existing capacity is lower than the new capacity.
66 Applicable if there is variance between the nameplate capacity and the capacity reflected in the
previous issued PTO. Applicable for oil-based, coal, biomass, geothermal, and natural gas
Generation Facilities except for standby stationary/portable/mobile/multi-purpose generator set
engines (1-15kW) used in small scale operation (e.g., tower light, air compressors, pumps etc.).
67 In accordance with Section 1, Rule XIX, Part VI of the R.A. No. 8749-IRR; Applicable for oil-
based, coal, biomass, geothermal, and natural gas Generation Facilities except for standby
stationary/portable/mobile/multi-purpose generator set engines (1-15kW) used in small scale
operation (e.g., tower light, air compressors, pumps etc.).
17 Series of 2023
Resolution No. _____,
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 37 of 59
based, coal, biomass, geothermal, and natural gas Generation Facilities except for standby
stationary/portable/mobile/multi-purpose Generator set engines (1-15kW) used in small scale
operation (e.g. tower light, air compressors, pumps etc.).
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 38 of 59
71Applicable if the capacity in the existing capacity is lower than the new capacity.
72Applicable if there is variance between the nameplate capacity and the capacity reflected in the
previous issued PTO. Applicable for oil-based, coal, biomass, geothermal, and natural gas
Generation Facilities except for standby stationary/portable/mobile/multi-purpose generator set
engines (1-15kW) used in small scale operation (e.g. tower light, air compressors, pumps etc.).
73 A Letter from the TNP, DU and SGO indicating that there is no need to amend the issued FCATC
74 The DU shall ensure that under Section 4.3.3.7 of the PDC 2017 Edition and the DOE DC 2021-
06-0013 are complied with prior to issuance of FCATC.
75 Not applicable for Generation Facilities operating in the Off-Grid Area and Embedded Generators
below the regional threshold per DOE DC No. DC2019-002-003, and any amendments thereto.
76 The Chief Financial Officer shall certify the true copies.
77 Or proof of online submission if sent electronically to BIR and SEC.
78 Applicable for Generation Company which has other business segment.
17 Series of 2023
Resolution No. _____,
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 40 of 59
(i) SEC issued COR with AOI or AOP and By-Laws, and
all subsequent amendments thereto, or Business
Name Registration Certificate (for Single
Proprietorship);
(iv) Latest GIS of the new owner and its stockholders duly
stamped received by the SEC;
DOE
NWRB
(vi) FSA for main fuel84 and/or Fuel Sustainability Plan for
Biomass Generation Facility.
(b) SEC issued COR with AOI or AOP and By-Laws, and
all subsequent amendments thereto, or Business
81 In accordance with Section 1, Rule XIX, Part VI of the R.A. No. 8749-IRR. Applicable for oil-
based, coal, biomass, geothermal, and natural gas Generation Facilities except for standby
stationary/portable/mobile/multi-purpose generator set engines (1-15kW) used in small scale
operation (e.g., tower light, air compressors, pumps etc.).
82 Required only for generation facilities that utilizes water for power generation, commercial and
industrial purposes.
83 For power generation, commercial and industrial purposes.
84Applicable for oil-based, coal, biomass, geothermal, and natural gas Generation Facilities.
85 In cases where the submitted document is issued to a different entity, a written explanation must
be submitted explaining the relationship of that entity to the entity with SGF, accompanied with
supporting documents that would substantiate the explanation.
86 In accordance with Section 1, Rule XIX, Part VI of the R.A. No. 8749-IRR; Applicable for oil-
based, coal, biomass, geothermal, and natural gas Generation Facilities except for standby
stationary/portable/mobile/multi-purpose generator set engines (1-15kW) used in small scale
operation (e.g., tower light, air compressors, pumps etc.).
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 42 of 59
based, coal, biomass, geothermal, and natural gas Generation Facilities except for standby
stationary/portable/mobile/multi-purpose Generator set engines (1-15kW) used in small scale
operation (e.g. tower light, air compressors, pumps etc.).
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 43 of 59
Within ninety (90) calendar days from the effectivity94 of the transfer,
the new owner shall file for an amendment of COC to transfer the COC
or PAO in its name.
Upon the effectivity of the transfer of ownership, the new owner shall
comply with all the obligations imposed on a GenCo, MGSP, QE,
Entities with SGF and DER including the submission of reportorial
requirements under Section 28 hereof.
90 A Letter from the DU indicating that there is no need to amend the previously-issued DU
certification may be submitted in lieu of an amended DU certification.
91 Applicable if the capacity in the existing capacity is lower than the new capacity.
92 Applicable if there is variance between the nameplate capacity and the capacity reflected in the
previous issued PTO. Applicable for oil-based, coal, biomass, geothermal, and natural gas
Generation Facilities except for standby stationary/portable/mobile/multi-purpose generator set
engines (1-15kW) used in small scale operation (e.g., tower light, air compressors, pumps etc.).
93 Date of notary.
94 Ibid.
95 Ibid.
17 Series of 2023
Resolution No. _____,
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 44 of 59
A GenCo which intends to convert its COC or PAO to SGF or DER shall
file an application for COC-SGF or DER, which shall be deemed as a
new application and shall comply with all the pertinent requirements
for such COC. The COC or PAO of the GenCo shall be deemed
automatically revoked once the COC-SGF or DER has been issued.
GenCo, MGSP, Entities with SGF and DER which intend to amend any
information on the technical specifications of its Generation Facilities
contained on the face of the COC or PAO and its annexes shall file an
application for the amendment of the COC or PAO in accordance with
Section 12 hereof.
For Entities with SGF having an aggregate Rated Capacity greater than
or equal to 1.000 MW, no COC shall be issued to such Generation
Facility without the conduct of a technical inspection.
The conduct of the technical inspections under this Section may also
be done through videoconferencing, which may still be subject to
further physical technical inspection, if necessary.
ARTICLE IV
FEES AND CHARGES
Section 17. Entities with SGF, QE, and Entities with DER. The
COC application fee for SGF shall be based on item VI-B of Resolution
No. 21, Series of 2007, and any amendments thereto. For purposes of
these 2023 Revised COC Rules, the COC application fee for SGF shall
also be applicable for COC application fee of QE and Entities with DER.
ARTICLE V
ISSUANCE AND TERM OF THE CERTIFICATE OF
COMPLIANCE
The term of the COC issued, with respect to Renewable DER that is for
End-User’s consumption and exporting, shall commence from the date
of approval of the ERC and is co-terminus with the Renewable DER
Agreement of the End-User with the DU.
The term of the QE-COC shall commence from the date of approval of
the ERC and is co-terminus with the Net-Metering Agreement of the
QE with the DU.
ARTICLE VI
OBLIGATIONS OF GENCO, MGSP, ENTITIES WITH SGF,
QE, AND ENTITIES WITH DER
Section 27. Material Change. Within seven (7) calendar days from
the happening of an event which results in a Material Change
concerning or affecting the company’s ownership, management,
operations, financial condition and performance, excluding outage
events, the GenCo, MGSP, and Entities with SGF and DER shall
submit a Material Change notice to the ERC of such fact or event and
its impact on the company.
A GenCo and MGSP shall inform the ERC, in writing, within seven (7)
calendar days of any changes in the individual Generating Unit’s
registered Pmax, Pmin, Ramp Up Rate and Ramp Down Rate which
should be supported by Generating Unit Capability Test Certificate and
corresponding results. Thereafter, the GenCo and MGSP shall file for
an amendment of the technical specifications (COC or PAO Annex B)
of its Generation Facilities in accordance with Section 12 hereof.
28.1.1. On or before the 30th day of January of each year, the GenCo
and MGSP shall submit to the ERC a Generation Company
Management Report (GCMR) which shall contain the following:
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 49 of 59
28.1.2. On or before the 30th day of January of each year, the GenCo
and MGSP shall submit to the ERC a Generation Company
Information Sheet (GCIS) in accordance with Section 1, Article
III of the ERC Resolution No. 26, Series of 2005, and any
amendments thereto.
28.1.3. On or before the 30th day of January of each year, the GenCo
and MGSP shall submit to the ERC the updated COC Form No.
4 (Generation Facility Description).
28.1.4. Within thirty (30) calendar days from public offering, the
GenCo shall submit reports on the extent of its compliance,
together with proofs showing the numbers of shares of stock
listed, registered or offered for sale, names of the
shareholders/purchasers presently owning said shares of stock
and other relevant information for monitoring and verification
purposes.
17 Series of 2023
Resolution No. _____,
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 50 of 59
28.1.5. Within one hundred fifty (150) days from the end of its calendar
or fiscal year, the GenCo shall submit a certified true copy of a
complete set of its AFS (i.e. statement of financial position,
statement of comprehensive income, statement of cash flows,
statement of changes in shareholders’ equity, notes to financial
statements) including the audit opinion and the statement of
management’s responsibility on the financial statements, duly
stamped received by the BIR. The statement of comprehensive
income should include a detailed schedule of operating
expenses for the period. The submitted financial statements
should clearly show the financial positions, results of operation,
and cash flows pertaining to the generation business. Together
with its AFS, the GenCo shall also submit the following:
(b) Five (5) year financial plan with the following details:
28.1.6. A GenCo or MGSP shall apply for the renewal of its expiring
permits indicated under Section 9.1 and Section 9.2 hereof,
based on the existing guidelines of the agencies concerned. In
line with this, GenCo or MGSP shall submit to the ERC copy/ies
of the renewed permits within thirty (30) days from the receipt
from the agencies concerned.
On or before the 3oth day of January of each year, Entities with SGF
shall submit to the ERC Annual SGF Report which shall contain the
electricity generated (kWh), hours of operation (hr), and fuel
consumption (Liter).
28.4.3. The DU shall also submit the weekly Test and Commissioning
report and FCATC as provided under 4.3.1.7 and 4.4.4, Section
4 of the DOE DC on T and C, and any amendments there.
28.5.3. The TNP shall also submit the weekly Test and Commissioning
report and FCATC as provided under 4.3.1.7 and 4.4.4, Section
4 of the DOE DC2021-06-0013.96
ARTICLE VII
WITHDRAWAL / DENIAL OF THE CERTIFICATE OF
COMPLIANCE OR PROVISIONAL AUTHORITY TO
OPERATE, AND IMPOSITION OF PENALTIES
Section 31. Denial. The ERC may, upon due evaluation of all the
requirements and conduct of technical inspection, deny with finality
an application for the issuance of COC or PAO, without prejudice to the
refiling thereof upon full compliance with all the requirements for the
issuance of a COC or PAO.
ARTICLE VIII
MONITORING
Section 33. The ERC shall monitor the compliance of GenCo, MGSP,
Entities with SGF, QEs, and Entities with DER with the terms and
conditions of their COCs or PAOs, the provisions of these 2023 Revised
Rules and all other applicable Rules and Regulations.
Section 34. GenCo, MGSP, and other entities issued COCs, as may be
allowed under these Rules, shall be subject to an annual regulatory fee
to be imposed by the ERC in accordance with rules it shall adopt for
this purpose.
ARTICLE IX
TRANSITORY PROVISION
COC or PAO application without the need to repay the application fee.
Non-commencement of the re-filing process within six (6) months
from the effectivity of the 2023 Revised COC Rules shall mean that the
COC application is deemed withdrawn.
For existing Generation Facilities with issued PAO, the validity period
of such PAO is extended until 2024, and the date of which shall be the
day and month of its original expiry. After which, the GenCo and MGSP
shall apply for issuance of COC or PAO not later than sixty (6o)
calendar days prior to the expiration of the extended validity period.
For existing Generation Facilities with issued COC, the GenCo and
MGSP shall apply for issuance of COC or PAO not later than sixty (6o)
calendar days prior to the expiration of such COC.
Section 36. Transitory Provision for SGF, QE and DER. All COC
applications, including renewal thereof, filed before the promulgation
of these 2023 Revised COC Rules shall be processed in accordance with
ERC Resolution No. 16, Series of 2014.
ARTICLE X
EXCEPTION CLAUSE
Section 37. Where good cause appears, the ERC may allow an
exception from any provision of these 2023 Revised COC Rules, if such
exception is found to be for the interest of the public and is not contrary
to law or any other related rules and regulations.
17
Resolution No. _____, Series of 2023
“A RESOLUTION ADOPTING THE 2023 REVISED RULES FOR THE
ISSUANCE OF CERTIFICATES OF COMPLIANCE (COCs) FOR
GENERATION FACILITIES”
Page 58 of 59
ARTICLE XI
SEPARABILITY CLAUSE
ARTICLE XII
APPLICABILITY AND REPEALING CLAUSE
ARTICLE XIII
MISCELLANEOUS PROVISIONS
(a) in writing;
Section 43. Effectivity. These 2023 Revised COC Rules shall take
effect fifteen (15) calendar days following its complete publication in a
newspaper of general circulation or in the Official Gazette.