You are on page 1of 41

(Original PDF) Reinforced Concrete

Design (9th Edition)


Visit to download the full and correct content document:
https://ebooksecure.com/download/original-pdf-reinforced-concrete-design-9th-edition
/
C ON T EN T S

Chapter
1 2-5 Flexural Strength of Rectangular
Beams 24
MATERIALS AND MECHANICS
OF BENDING, AND CONCRETE SLAB 2-6 Equivalent Stress Distribution 25
SYSTEMS 1
2-7 Balanced, Brittle, and Ductile Failure
1-1 Concrete 1 Modes 27

1-2 The ACI Building Code 1 2-8 Ductility Requirements 28

1-3 Cement and Water 1 2-9 Strength Requirements 30

1-4 Aggregates 1 2-10 Rectangular Beam Analysis for Moment


(Tension Reinforcement Only) 31
1-5 Concrete Mixes 2
2-11 Summary of Procedure for
1-6 Concrete in Compression 3
Rectangular Beam Analysis for FMn
1-7 Concrete in Tension 5 (Tension Reinforcement Only) 34

1-8 Reinforcing Steel 5 2-12 Slabs: Introduction 34

1-9 Concrete Cover 8 2-13 One-Way Slabs: Analysis for


Moment 34
1-10 Beams: Mechanics of Bending Review 8
2-14 Rectangular Beam Design for
1-11 Concrete Slab Systems 13
Moment (Tension Reinforcement
1-12 Gravity Load Distribution in Concrete Only) 37
Slab Systems 14
2-15 Summary Of Procedure for Rectangu-
References 16 lar Reinforced Concrete Beam Design
for Moment (Tension Reinforcement
Problems 17 Only) 41

2-16 Design of One-Way Slabs for Moment


Chapter
2 (Tension Reinforcement Only) 41
RECTANGULAR REINFORCED
2-17 Summary of Procedure for Design of
CONCRETE BEAMS AND SLABS:
One-Way Slabs for Moment (To Satisfy
TENSION STEEL ONLY 21
ACI Minimum Thickness, h) 43
2-1 Introduction 21
2-18 Slabs-On-Grade 43
2-2 Analysis and Design Method 21
References 46
2-3 Behavior Under Load 22
Problems 46
2-4 Strength Design Method
Assumptions 23
viii Contents

Chapter
3 Chapter
5
REINFORCED CONCRETE BEAMS: DEVELOPMENT, SPLICES, AND
T-BEAMS, L-BEAMS, AND DOUBLY SIMPLE-SPAN BAR CUTOFFS 104
REINFORCED BEAMS 51
5-1 Bond Stress and Development Length:
3-1 T-Beams and L-Beams: Introduction 51 Introduction 104

3-2 T-Beam and L-Beam Analysis 53 5-2 Development Length: Tension Bars 106

3-3 Analysis of Beams Having 5-3 Development Length: Compression


Irregular Cross Sections 56 Bars 111

3-4 T-Beam and L-Beam Design (for 5-4 Development Length: Standard
Moment) 57 Hooks in Tension 112

3-5 Summary of Procedure for Analysis of 5-5 Development of Web


T-Beams and L-Beams (for Moment) 60 Reinforcement 115

3-6 Summary of Procedure for Design of 5-6 Splices 117


T-Beams and L-Beams (for Moment) 61
5-7 Tension Splices 117
3-7 Doubly Reinforced Beams:
5-8 Compression Splices 117
Introduction 62
5-9 Simple-Span Bar Cutoffs and Bends 118
3-8 Doubly Reinforced Beam Analysis for
Moment (Condition I) 62 5-10 Code Requirements for Development
of Positive Moment Steel at Simple
3-9 Doubly Reinforced Beam Analysis for
Supports 122
Moment (Condition II) 65
5-11 Structural Integrity Reinforcement–
3-10 Summary of Procedure for Analysis
Beams 125
of Doubly Reinforced Beams (for
Moment) 67 References 126

3-11 Doubly Reinforced Beam Design for Problems 126


Moment 68

3-12 Summary of Procedure for Design


of Doubly Reinforced Beams
Chapter
6
CONTINUOUS ONE-WAY AND TWO-WAY
(for Moment) 69 FLOOR SYSTEMS 130

3-13 Additional Code Requirements for 6-1 Introduction 130


Doubly Reinforced Beams 70
6-2 Continuous-Span Bar Cutoffs 132
Problems 71
6-3 Design of Continuous One-Way Floor
Systems 133

Chapter
4 6-4 Analysis and Design of Continuous
Two-Way Slabs 145
SHEAR AND TORSION 75
References 180
4-1 Introduction 75
Problems 180
4-2 Shear Reinforcement Design
Requirements 76

4-3 Shear Analysis Procedure 78


Chapter
7
SERVICEABILITY 183
4-4 Stirrup Design Procedure 79
7-1 Introduction 183
4-5 Torsion of Reinforced Concrete
Members 86 7-2 Deflections 183

4-6 Corbels and Brackets 94 7-3 Calculation of Icr 184

References 99 7-4 Immediate Deflection 186

Problems 99 7-5 Long-Term Deflection 186


Contents ix

7-6 Procedure for Calculating the 9-6 Summary of Procedure for Analysis
Deflection of Simply Supported and Design of Short Columns with
and Continuous Beams and Slabs 189 Small Eccentricities 241

7-7 Procedure for Calculating the 9-7 The Load-Moment Relationship 241
Deflection of Continuous Girders 190
9-8 Columns Subjected to Axial Load at
7-8 Deflection Control Measures in Large Eccentricity 242
Reinforced Concrete Structures 193
9-9 F Factor Considerations 242
7-9 Crack Control 194
9-10 Analysis of Short Columns: Large
7-10 Floor Vibrations 195 Eccentricity 243

7-11 Gross and Cracked Section Properties 9-11 Biaxial Bending 250
of Concrete Sections 197
9-12 The Slender Column 252
References 198
9-13 Concrete Column Schedule 256
Problems 198
References 257

Problems 257
Chapter
8
WALLS 200
Chapter
10
FOUNDATIONS 260
8-1 Introduction 200
10-1 Introduction 260
8-2 Lateral Forces on Retaining
Walls 201 10-2 The Geotechnical Report 261

8-3 Design of Reinforced Concrete 10-3 Wall Footings 262


Cantilever Retaining Walls 204
10-4 Wall Footings Under Light Loads 267
8-4 Design Considerations for Bearing
10-5 Individual Reinforced Concrete
Walls 219
Footings for Columns 267
8-5 Design Considerations for Basement
10-6 Square Reinforced Concrete Footings 270
Walls 221
10-7 Rectangular Reinforced Concrete
8-6 Lateral Load Resisting Systems
Footings 273
in Concrete Buildings 221
10-8 Eccentrically Loaded Footings 277
8-7 Concrete Moment Frames 222
10-9 Combined Footings 282
8-8 Shear Walls 223

References 231 10-10 Cantilever or Strap Footings 284

10-11 Analysis and Design of Mat


Problems 231
Foundations 286

10-12 Deep Foundations–Piles, Drilled Shaft


Chapter
9 (Caissons), and Pile Caps 287

10-13 Strut-and-Tie Models for Pile Caps


COLUMNS 234
and Deep Beams 292
9-1 Introduction 234
References 300
9-2 Strength of Reinforced Concrete
Columns: Small Eccentricity 235 Problems 301

9-3 Code Requirements Concerning


Chapter
11
Column Details 236 PRESTRESSED CONCRETE
FUNDAMENTALS 303
9-4 Analysis of Short Columns: Small
Eccentricity 238 11-1 Introduction 303

9-5 Design of Short Columns: Small 11-2 Design Approach and Basic
Eccentricity 239 Concepts 303
x Contents

11-3 Stress Patterns in Prestressed


Concrete Beams 305
Chapter
14
PRACTICAL CONSIDERATIONS IN
11-4 Prestressed Concrete Materials 306 THE DESIGN OF REINFORCED CONCRETE
BUILDINGS 360
11-5 Analysis of Rectangular Prestressed
Concrete Beams 307 14-1 Introduction 360

11-6 Alternative Methods of Elastic 14-2 Rules of Thumb and Practical


Analysis: Load Balancing Method 310 Considerations for Reinforced
Concrete Design 360
11-7 Flexural Strength Analysis 313
14-3 Approximate Moments and Shears
11-8 Notes on Prestressed Concrete
in Continuous Girders 362
Design 315

References 315 14-4 Strengthening and Rehabilitation


of Existing Reinforced Concrete
Problems 315 Structures 364

14-5 Diaphragms, Drag Struts,


Chapter
12 and Chords 369

CONCRETE FORMWORK 317 14-6 One-Way Slabs Subjected to


Concentrated Loads 371
12-1 Introduction 317
14-7 Load Testing of Structures 373
12-2 Formwork Requirements 317
14-8 Closure or Pour Strips in Reinforced
12-3 Formwork Materials and
Concrete Floors 375
Accessories 318
14-9 Fire Resistance of Concrete Structural
12-4 Loads and Pressures on Forms 319
Elements 376
12-5 The Design Approach 321
14-10 Analysis and Design of Edge-Supported
12-6 Design of Formwork for Slabs 326 Two-Way Slabs on Stiff Supports 377

12-7 Design of Formwork for Beams 331 14-11 Cast-In Place Concrete
Specifications 379
12-8 Wall Form Design 335
14-12 Student Design Projects 381
12-9 Forms for Columns 339

References 342 References 385

Problems 342
APPENDIX A TABLES AND DIAGRAMS 386

APPENDIX B SUPPLEMENTARY AIDS


Chapter
13 AND GUIDELINES 403
DETAILING REINFORCED CONCRETE B-1 ACCURACY FOR
STRUCTURES 344 COMPUTATIONS FOR
13-1 Introduction 344 REINFORCED CONCRETE 403

B-2 FLOW DIAGRAMS 403


13-2 Placing or Shop Drawings 345

13-3 Marking Systems and Bar Marks 345 APPENDIX C METRICATION 408

13-4 Schedules 352 C-1 THE INTERNATIONAL SYSTEM


OF UNITS (SI) 408
13-5 Fabricating Standards 352
C-2 SI STYLE AND USAGE 410
13-6 Bar Lists 353
C-3 CONVERSION FACTORS 411
13-7 Extras 354
REFERENCES 416
13-8 Bar Supports and Bar Placement 355
APPENDIX D ANSWERS TO SELECTED
13-9 Computer Detailing 356 PROBLEMS 417

References 359 INDEX 419


CHAPTER ONE

MATERIALS AND MECHANICS OF BENDING,


AND CONCRETE SLAB SYSTEMS

1-1 Concrete 1-6 Concrete in 1-10 Beams: Mechanics of


Compression Bending Review
1-2 The ACI Building Code
1-7 Concrete in Tension 1-11 Concrete Slab Systems
1-3 Cement and Water
1-8 Reinforcing Steel 1-12 Gravity Load Distribution
1-4 Aggregates
in Concrete Slab Systems
1-9 Concrete Cover
1-5 Concrete Mixes

1-1 CONCRETE so incorporated, it has official sanction, becomes a legal


document, and is part of the law controlling reinforced
Concrete, the most commonly used construction mate- concrete design and construction in a particular area.
rial worldwide, is a composite material that consists
primarily of a mixture of cement and fine and coarse
aggregates (sand, gravel, crushed rock, and/or other 1-3 CEMENT AND WATER
materials) to which water has been added as a neces- Structural concrete uses, almost exclusively, hydrau-
sary ingredient for the chemical reaction during the lic cement. With this cement, water is necessary for
curing process. The bulk of the mixture consists of the chemical reaction of hydration. In the process of
the fine and coarse aggregates. The resulting concrete hydration, the cement sets and bonds the fresh con-
strength and durability are a function of the propor- crete into one mass. Portland cement, which originated
tions of the mix as well as other factors, such as the in England, is undoubtedly the most common form
concrete placing, finishing, and curing history. of cement. Portland cement consists chiefly of cal-
The compressive strength of concrete is relatively cium and aluminum silicates. The raw materials are
high. Yet, it is a relatively brittle material, the tensile limestones, which provide calcium oxide (CaO), and
strength of which is small compared with its compres- clays or shales, which furnish silicon dioxide (SiO2)
sive strength. Hence steel reinforcing rods (which have and aluminum oxide (Al2O3). Following processing,
high tensile and compressive strength) are used in cement is marketed in bulk or in 94-lb (1-ft3) bags.
combination with the concrete; the steel will resist the In fresh concrete, the ratio of the amount of water
tension and the concrete the compression. Reinforced to the amount of cement, by weight, is termed the
concrete is the result of this combination of steel and water-cementitious material ratio. This ratio can also
concrete. In many instances, steel and concrete are posi- be expressed in terms of gallons of water per bag of
tioned in members so that they both resist compression. cement. For complete hydration of the cement in a
mix, a water-cementitious material ratio of 0.35 to
0.40 (4 to 4 1>2 gal of water/bag of cement) is required.
1-2 THE ACI BUILDING CODE To increase the workability of the concrete (the ease
The design and construction of reinforced concrete with which it can be mixed, handled, and placed),
buildings is controlled by the Building Code Requirements higher water-cementitious material ratios are nor-
for Structural Concrete (ACI 318-14) of the American mally used or superplasticizers are added to the mix.
Concrete Institute (ACI) [1]. The use of the term code in
this text refers to the ACI Code unless otherwise stipu-
lated. The code is revised, updated, and currently cur-
1-4 AGGREGATES
rently reissued on a 3-year cycle. It has been incorporated In ordinary structural concretes, the aggregates occupy
into the building codes of almost all states and munici- approximately 70% to 75% of the volume of the hard-
palities throughout the United States, however. When ened mass. Gradation of aggregate size to produce
1
2 CHApTER ONE

close packing is desirable because, in general, the more defined as the compressive strength of the concrete at 28
densely the aggregate can be packed, the better are the days after placement, but there are other factors to con-
strength and durability because of the inter-locking of sider in order to satisfy the concrete durability require-
the aggregates. ments of the ACI Code. For each group of structural
Aggregates are typically classified as fine or coarse. members, the exposure classes must first be assigned
Fine aggregate is generally sand and may be categorized based on ACI 318–14, Table 19.3.1.1 depending on the
as consisting of particles that will pass a No. 4 sieve degree of exposure of the concrete to freeze/thaw (F),
(four openings per linear inch). Coarse aggregate consists sulfate (S), water (W), and corrosion (C). Once the expo-
of particles that would be retained on a No. 4 sieve. The sure classes are known, ACI 318–14, Table 19.3.2.1 is
maximum size of coarse aggregate in reinforced con- used to determine the minimum design strength and
crete is governed by various ACI Code requirements. water-cementitious material ratio. This table is also used
These requirements are established primarily to ensure to determine whether or not air entrainment is needed.
that the concrete can be placed with ease into the forms If air entrainment is needed, then ACI 318–14, Table
without any danger of jam-up between adjacent bars 19.3.3.1 is used. The amount of air entrainment needed
or between bars and the sides of the forms. Section is a function of the exposure class and the aggregate
26.4.2.1 of ACI 318 states that maximum size of coarse size. Air entraining typically ranges between 4.5% and
aggregate should not exceed the least of the following: 7%. The design data for a sample mix is shown below:

(i) one-fifth the narrowest dimension between Sample Mix Design Data
sides of forms Mix Design Number: 4001-A (this number is spe-
(ii) one-third the depth of slabs cific to the concrete supplier)
(iii) three-fourths the minimum specified clear Minimum compressive strength at 28 days
spacing between individual reinforcing bars or f′c = 4000 psi
wires, bundles of bars, prestressed reinforcement, Used for: Footings, piers, and foundation walls
individual tendons, bundled tendons, or ducts Slump: 4 in.; 8 in. with HRWR1
Air content: 6.0, +>- 1.5,
Note that smaller aggregate sizes have a relatively water-to-cementitious material ratio: 0.40
larger total surface area and thus require more cement
paste to coat the surfaces of the aggregate which Weight per Cubic
results in higher drying shrinkage. In typical building Materials Yard
construction, the nominal maximum coarse aggregate Cement, Type I/II, ASTM C150 540 lbs
size of 3>4″ is commonly specified, though maximum
Fly Ash, ASTM C618 95 lbs
aggregate size of up to 1 1>2″ is also sometimes specified
Natural Sand, ASTM C33 1230 lbs
to achieve reduced shrinkage.
#1 and #2 crushed stone, ASTM C33 1780 lbs
Potable Water, ASTM C1602 255 lbs
1-5 CONCRETE MIXES Air Entrainment, ASTM C260 1.5 oz./cwt
Water Reducer, ASTM C494 Type A 3.0 oz./cwt
There are numerous factors to consider when determin-
ing all of the components of a concrete mix. The most High-Range Water Reducer, ASTM C494 7 oz. to 10 oz./cwt
Type F*
basic mix consists of water, cement, coarse aggregate,
Non-Chloride Accelerator, ASTM C494* 0 oz. to 26 oz./cwt
and fine aggregate (sand). Beyond these basic compo-
nents, one or more chemical admixtures can be used *Added at the site upon request
depending on the required performance of the concrete. The most common admixtures are outlined as follows:
Since the admixtures are a proprietary product, the dos-
age is based on the manufacturer’s recommendations. Air Entrainment
Admixtures are often dosed in units of fluid ounces per
100 pounds of cementitious material (cwt). The strength Air entrainment provides small air bubbles in the con-
of the concrete could be adversely impacted by certain crete to act as a buffer against volumetric changes during
admixtures, and there could also be compatibility issues freeze/thaw cycles and thus makes the concrete more
with multiple admixtures. To control these issues and durable. It also makes the concrete more workable. A rule
to also ensure the performance of the concrete, concrete of thumb is that the compressive strength of concrete will
suppliers will typically go through the process of creat- decrease by 5% for every 1% increase in entrained air.
ing batches of concrete and testing them. Once a certain
mix is validated, it can then be used in the future using
Water Reducers
the same components and proportions. A sample mix When it is desired to make the concrete more work-
design is shown in the below table. able, a common cost-effective solution is to simply
The most critical parameter in the design and selec- add water, but this will have a negative impact on
tion of a concrete mix is the design strength f′c, which is 1
High range water reducer (HRWR)
Materials and Mechanics of Bending, and Concrete Slab Systems 3

the strength of the concrete. Water-reducing admix- information on the temperature requirements for con-
tures will increase the slump and thus the workability crete can be found in ACI 305 - Guide to Hot Weather
of concrete while not adversely impacting the water- Concreting and ACI 306 - Guide to Cold Weather
cementitious material ratio. Concreting. Special mix considerations also apply to
When a much higher degree of workability is mass concrete pours, such as thick mat foundations,
needed, a superplasticizer (high-range water reducer) where the high temperatures generated from the
can be used which will yield slumps around 8 in. hydration process, if not adequately controlled, can
and higher. There are also products available that are lead to cracking of the concrete.
called mid-range water reducers that provide a more
moderate amount of slump increase.
1-6 CONCRETE IN
Accelerators and Retarders COMPRESSION
It is sometimes desired to decrease or increase the The theory and techniques relative to the design and
setting time of the concrete, and so an accelerator or proportioning of concrete mixes, as well as the placing,
retarder product could be used. Accelerators can finishing, and curing of concrete, are outside the scope
be used to increase the rate at which the concrete of this book and are adequately discussed in many
reaches its design strength. This may be desired due other publications [2–5]. Field testing, quality control,
to weather conditions or to meet a certain construction and inspection are also adequately covered elsewhere.
schedule. Calcium chloride is a common accelerator This is not to imply that these are of less importance in
component, but it cannot be used in reinforced con- overall concrete construction technology but only to
crete since the chloride will promote corrosion in the reiterate that the objective of this book is to deal with
steel reinforcement. the design and analysis of reinforced concrete members.
Set retarders are used to delay the chemical reac- We are concerned primarily with how a reinforced
tion with the cement that allows the concrete to set. concrete member behaves when subjected to load. It
This might be used to offset the effect of high tempera- is generally accepted that the behavior of a reinforced
tures since high temperatures can produce a faster concrete member under load depends on the stress–
setting time. They might also be used, for example, strain relationship of the materials, as well as the type
during a paving operation to allow more time between of stress to which it is subjected. With concrete used
concrete batches and reduce the possibility of a cold principally in compression, the compressive stress–
joint in the pavement. strain curve is of primary interest.
The compressive strength of concrete is denoted
as f′c and is assigned the unit of pounds per square inch
Corrosion-Inhibitor (psi). This is the unit for f′c used in the ACI Code equa-
Corrosion-inhibiting admixtures are used to deter corro- tions. For calculations, f′c is frequently used with the
sion of reinforcing steel in concrete that is exposed to unit kips per square inch (ksi).
water or salt. This will increase the durability and life A test that has been standardized by the American
span of the concrete structure. Society for Testing and Materials (ASTM C39) [6] is
Other chemical admixtures include shrinkage used to determine the compressive strength ( f′c) of
compensating and permeability reducing admix- concrete. The test involves compression loading to
tures. For more information on chemical admixtures, failure of a specimen cylinder of concrete. The com-
the reader should refer to ACI 212.3R-16-Report on pressive strength so determined is the highest com-
Chemical Admixtures for Concrete. pressive stress to which the specimen is subjected.
Concrete that is placed between 50° F and 85° F do Note in Figure 1-1 that f′c is not the stress that exists
not require any special mix design or temperature con- in the specimen at failure but that which occurs at a
siderations. When concrete is placed during extreme strain of about 0.002 (though the concrete strain at f′c
weather temperatures outside of these range, spe- may vary between approximately 0.0015 and 0.0025).
cial considerations for cold and hot weather concrete Currently, 28-day concrete strengths (f′c) range from
must be accounted for [13, 14]. 2500 to upwards of 10,000 psi, with 3000 to 4000 psi
When concrete is poured in cold temperatures being common for reinforced concrete structures
without any precautionary measures taken, the con- and 5000 to 6000 psi being common for prestressed
crete will freeze and thus destory the bond between concrete members, and higher strengths used for
the concrete and the rebar. Pouring concrete at exces- columns in high-rise buildings. High strength con-
sively high temperatures causes the concrete to set crete with 12,000 psi compressive strength was used
faster than anticipated, leading to the formation of recently for the columns, shear walls, and drilled
cold joints. High temperatures also lead to uncon- caissons for a project at the Hudson Yards in New
trolled and signigicant cracking of the concrete which York City. For normal weight concrete, the compres-
negatively impacts strength and durability. Detailed sive strength at 28 days is specified in the ACI Code
4 CHApTER ONE

f 9c = 6000 psi
6

f 9c = 5000 psi
5
Stress (psi 3 1000)
f 9c = 4000 psi
4

f 9c = 3000 psi
3

0
0 0.001 0.002 0.003 0.004 FIGURE 1-1 Typical stress–strain
Strain (in./in.) curves for concrete.

as the design strength. However, for higher strength where


concrete, the compressive strength at 56 or 90 days is Ec = modulus of elasticity of concrete in comp-
commonly used [15]. The curves shown in Figure 1-1 ression (psi)
represent the result of compression tests on 28-day wc = unit weight of concrete (lb/ft3)
standard cylinders for varying design mixes. The
f′c = compressive strength of concrete (psi)
strain at rupture of concrete varies as indicated by
the plots in Figure 1-1, but in developing the ACI This expression is valid for concretes having wc
Code equations for flexure, a limiting crushing strain between 90 and 160 lb/ft3. For normal-weight con-
of 0.003 is assumed (ACI 318-14, Section 22.2.2.1). crete, the unit weight wc will vary with the mix propor-
A review of the stress–strain curves for different- tions and with the character and size of the aggregates.
strength concretes reveals that the maximum com- If the unit weight is taken as 144 lb/ft3, the resulting
pressive strength is generally achieved at a unit strain expression for modulus of elasticity is
of approximately 0.002 in./in. Stress then decreases,
accompanied by additional strain. Higher-strength Ec = 57,0001f′c (see Table A-6 for values of Ec)
concretes are more brittle and will fracture at a lower
maximum strain than will the lower-strength con- It should also be noted that the stress–strain curve
cretes. The initial slope of the curve varies, unlike for the same-strength concrete may be of different
that of steel, and only approximates a straight line. shapes if the condition of loading varies appreciably.
For steel, where stresses are below the yield point With different rates of strain (loading), we will have dif-
and the material behaves elastically, the stress–strain ferent-shape curves. Generally, the maximum strength
plot will be a straight line. The slope of the straight of a given concrete is smaller at slower rates of strain.
line is the modulus of elasticity. For concrete, how-
ever, we observe that the straight-line portion of the
plot is very short, if it exists at all. Therefore, there
exists no constant value of modulus of elasticity for 5000
a given concrete because the stress–strain ratio is
Compressive strength, f 9c (psi)

5 years
not constant. It may also be observed that the slope 4000 6 months
of the initial portion of the curve (if it approximates
a straight line) varies with concretes of different
3000 28 days
strengths. Even if we assume a straight-line portion,
the modulus of elasticity is different for concretes
of different strengths. At low and moderate stresses 2000
(up to about 0.5f′c), concrete is commonly assumed to
behave elastically. 1000
The ACI Code, Section 19.2.2, provides the
accepted empirical expression for modulus of elasticity: 0
Time
Ec = w 1.5
c 33 1f′c FIGURE 1-2 Strength–time relationship for concrete.
Materials and Mechanics of Bending, and Concrete Slab Systems 5

Concrete strength varies with time, and the speci- bending stress in a plain concrete test beam at fail-
fied concrete strength is usually that strength that ure), as a measure of tensile strength (ASTM C78) [6].
occurs 28 days after the placing of concrete. A typical The moment that produces a tensile stress just equal to
strength–time curve for normal stone concrete is shown the modulus of rupture is termed the cracking moment,
in Figure 1-2. Generally, concrete attains approximately Mcr, and may be calculated using methods discussed
70% of its 28-day strength in 7 days and approximately in Section 1-9. The ACI Code recommends that the
85% to 90% in 14 days. modulus of rupture fr be taken as 7.5l 1f′c, where f′c
Concrete, under load, exhibits a phenomenon is in psi (ACI 318 Equation 19.2.3.1). Greek lowercase
termed creep. This is the property by which concrete lambda (l) is a modification factor reflecting the lower
continues to deform (or strain) over long periods of tensile strength of lightweight concrete relative to
time while under constant load. Creep occurs at a normal-weight concrete. The values for l are as follows:
decreasing rate over a period of time and may cease
Normal-weight concrete—1.0
after several years. Generally, high-strength concretes
exhibit less creep than do lower-strength concretes. Sand-lightweight concrete—0.85
The magnitude of the creep deformations is propor- All-lightweight concrete—0.75
tional to the magnitude of the applied load as well as Interpolation between these values is permitted.
to the length of time of load application. See ACI Code Table 19.2.4.2 for details. If the aver-
age splitting tensile strength fct is specified, then
l = f ct >(6.71f cm) … 1.0, where f cm is the average mea-
1-7 CONCRETE IN TENSION sured compressive strength, in psi.
The tensile and compressive strengths of concrete
are not proportional, and an increase in compressive
strength is accompanied by an appreciably smaller 1-8 REINFORCING STEEL
percentage increase in tensile strength. According to
Concrete cannot withstand very much tensile stress
the ACI Code Commentary, the tensile strength of
without cracking; therefore, tensile reinforcement must
normal-weight concrete in flexure is about 10% to 15%
be embedded in the concrete to overcome this defi-
of the compressive strength.
ciency. In the United States, this reinforcement is in the
The true tensile strength of concrete is difficult to
form of steel reinforcing bars or welded wire reinforc-
determine. The split-cylinder test (ASTM C496) [6] has
ing composed of steel wire. In addition, reinforcing in
been used to determine the tensile strength of light-
the form of structural steel shapes, steel pipe, steel tub-
weight aggregate concrete and is generally accepted as
ing, and high-strength steel tendons is permitted by the
a good measure of the true tensile strength. The split-
ACI Code. Many other approaches have been taken in
cylinder test uses a standard 6-in.-diameter, 12-in.-
the search for an economical reinforcement for concrete.
long cylinder placed on its side in a testing machine. A
Principal among these are the fiber-reinforced concretes,
compressive line load is applied uniformly along the
where the reinforcement is obtained through the use of
length of the cylinder, with support furnished along
short fibers of steel or other materials, such as fiberglass.
the full length of the bottom of the cylinder. The com-
For the purpose of this book, our discussion will primar-
pressive load produces a transverse tensile stress, and
ily include steel reinforcing bars and welded wire rein-
the cylinder will split in half along a diameter when its
forcing. High-strength steel tendons are used mainly in
tensile strength is reached.
prestressed concrete construction (see Chapter 11).
The tensile stress at which splitting occurs is
The specifications for steel reinforcement pub-
referred to as the splitting tensile strength, fct, and may
lished by the ASTM are generally accepted for the steel
be calculated by the following expression derived
used in reinforced concrete construction in the United
from the theory of elasticity:
States and are identified in ACI 318 Section 20.2.
2P The ACI Code states that reinforcing bars should
f ct = be secure and in place prior to the placement of con-
pLD
crete, thus the practice of wet-setting of rebar is not
where permitted. While it is not uncommon in practice to see
f ct = splitting tensile strength of lightweight aggre- some contractors wanting to place rebar in wet con-
gate concrete (psi) crete, this should not be permitted because the rebar
P = applied load at splitting (lb) displaces the aggregates, and proper bond between
L = length of cylinder (in.) the concrete and rebar cannot easily be assured.
The steel bars used for reinforcing are, almost
D = diameter of cylinder (in.)
exclusively, round deformed bars with some form of
Another common approach has been to use the patterned ribbed projections rolled onto their surfaces.
modulus of rupture, fr (which is the maximum tensile The patterns vary depending on the producer, but
6 CHApTER ONE

Letter designation for mill, a number indicating the size of the bar, a symbol
producing mill or letter indicating the type of steel from which the bar
Bar size (#7 shown)
was rolled, and for grade 60 bars, either the number 60
or a single continuous longitudinal line (called a grade
Steel type: line) through at least five deformation spaces. The grade
S: Carbon steel (A615) indicates the minimum specified yield stress in ksi. For
W: Low alloy steel (A706) instance, a grade 60 steel bar has a minimum specified
SS: Stainless steel (A955)
yield stress of 60 ksi. No symbol indicating grade is rolled
B

Grade (60ksi shown) onto grade 40 or 50 steel bars (see Figure 1-3). Grade 75
bars can have either two grade lines through at least five
7

deformation spaces or the grade mark 75. Reference [7]


S

is an excellent resource covering the various aspects of


bar identification.
60

Reinforcing bars are usually made from newly


manufactured steel (billet steel). Steel types and ASTM
specification numbers for bars are tabulated in Table
Main ribs
A-1. Note that ASTM A615, which is billet steel, is
available in grades 40, 60, 75, and 80. Grade 80 steel
is allowed for non-seismic applications per ASTM 615
FIGURE 1-3 Rebar marks and designation.
and ASTM 706 [8]. (The full range of bar sizes is not
available in grades 40, 75, and 80, however.) Grade
all patterns should conform to ASTM specifications. 75 steel is approximately 20% stronger than grade
Steel reinforcing bars are readily available in straight 60 steel, requiring a corresponding reduction in the
lengths of 60 ft. Smaller sizes are also available in coil required area of reinforcement, though the installed
stock for use in automatic bending machines. The bars cost of grade 75 steel reinforcement is slightly higher
vary in designation from No. 3 through No. 11, with than the cost for grade 60 steel. ASTM A706, low-alloy
two additional bars, No. 14 and No. 18. See Figure 1-3 steel, which was developed to satisfy the requirement
for a sample rebar designation. for reinforcing bars with controlled tensile properties
For bars No. 3 through No. 8, the designation repre- and controlled chemical composition for weldability,
sents the bar diameter in eighths of an inch. The No. 9, is available in only one grade. Tables A-2 and A-3 con-
No. 10, and No. 11 bars have diameters that provide tain useful information on cross-sectional areas of bars.
areas equal to 1-in.-square bars, 1 1>8 @in.@square bars, and The most useful physical properties of reinforc-
11>4 @in.@square bars, respectively. The No. 14 and No. 18 ing steel for reinforced concrete design calculations
bars correspond to or have the same cross-sectional areas are yield stress (fy) and modulus of elasticity. A typi-
as 11>2@in.@square bars and 2-in.-square bars, respec- cal stress–strain diagram for reinforcing steel is shown
tively, and are commonly available only by special order. in Figure 1-4a. The idealized stress–strain diagram of
Round, plain reinforcing bars are permitted for spirals Figure 1-4b is discussed in Chapter 2.
(lateral reinforcing) in concrete compression members. The yield stress (or yield point) of steel is deter-
ASTM specifications require that identification mined through procedures governed by ASTM
marks be rolled onto the bar to provide the following standards. For practical purposes, the yield stress
information: a letter or symbol indicating the producer’s may be thought of as that stress at which the steel

Elastic Elastic
region region

fy fy
Stress

Stress

ey ey
Strain Strain
As determined by tensile test Idealized
(a) (b)
FIGURE 1-4 Stress–strain diagram for reinforcing steel.
Materials and Mechanics of Bending, and Concrete Slab Systems 7

exhibits increasing strain with no increase in stress. wire size. WWR with wire diameters larger than about
For reinforcement without a sharply defined yield ¼ in. is usually available only in sheets.
point, ACI 318-14, similar to the ASTM standards, Both plain and deformed WWR products are avail-
defines the yield strength as the 0.2% proof stress (that able. According to ACI 318 Section 20.2.1.7, deformed
is, the offset stress at a 0.2% strain). The yield stress of wire, plain wire, welded deformed wire reinforcement,
the steel will usually be one of the known (or given) and welded plain wire reinforcement shall conform
quantities in a reinforced concrete design or analysis to ASTM A 1064 for carbon steel and ASTM A 1022
problem. See Table A-1 for the range of fy. for stainless steel. Depending on the application, both
The modulus of elasticity of carbon reinforcing materials have the maximum fy permitted for design
steel (the slope of the stress–strain curve in the elastic that varies from 60,000 psi to 100,000 psi (see ACI 318
region) varies over a very small range and has been Tables 20.2.2.4a and 20.2.2.4b). The deformed wire is usu-
adopted as 29,000,000 psi (ACI Code Section 20.2.2.2). ally more expensive, but it can be expected to have an
Unhindered corrosion of reinforcing steel will lead improved bond with the concrete.
to cracking and spalling of the concrete in which it is A rational method of designating wire sizes to
embedded. Quality concrete, under normal conditions, replace the formerly used gauge system has been
provides good protection against corrosion for steel adopted by the wire industry. Plain wires are described
embedded in the concrete with adequate cover (mini- by the letter W followed by a number equal to 100
mum requirements are discussed in Chapter 2). This times the cross-sectional area of the wire in square
protection is attributed to, among other factors, the inches. Deformed wire sizes are similarly described,
high alkalinity of the concrete. Where reinforced con- but the letter D is used. Thus a W9 wire has an area of
crete structures (or parts of structures) are subjected to 0.090 in.2 and a D8 wire has an area of 0.080 in.2 A W8
corrosive conditions, however, some type of corrosion wire has the same cross-sectional area as the D8 but is
protection system should be used to prevent deterio- plain rather than deformed. Sizes between full num-
ration. Examples of such structures are bridge decks, bers are given by decimals, such as W9.5.
parking garage decks, wastewater treatment plants, Generally, the material is indicated by the sym-
and industrial and chemical processing facilities. bol WWR, followed by spacings first of longitudi-
One method used to minimize the corrosion of the nal wires, then of transverse wires, and last by the
reinforcing steel is to coat the bars with a suitable pro- sizes of longitudinal and transverse wires. Thus
tective coating. The protective coating can be a nonme- WWR6 * 12 @ W16 * W8 indicates a plain WWR with
tallic material such as epoxy or a metallic material such 6-in. longitudinal spacing, 12-in. transverse spacing,
as zinc (galvanizing). The ACI Code requires epoxy- and a cross-sectional area equal to 0.16 in.2 for the lon-
coated reinforcing bars to comply with ASTM A775 gitudinal wires and 0.08 in.2 for the transverse wires.
or ASTM A934 and galvanized (zinc-coated) bars to Additional information about WWR, as well
comply with ASTM A767 (ACI 318 Section 20.6.2). The as tables relating size number with wire diameter,
bars to be epoxy-coated or zinc-coated (galvanized) area, and weight, may be obtained through the Wire
must meet the code requirements for uncoated bars as Reinforcement Institute [9] or the Concrete Reinforcing
tabulated in Table A-1. Steel Institute [9 and 10]. Table 1-1 contains common
Welded wire reinforcing (WWR) (commonly called WWR sizes with the area of steel in in.2/ft width.
mesh) is another type of reinforcement. It consists of Most concrete is reinforced in some way to resist
cold-drawn wire in orthogonal patterns, square or tensile forces (Figure 1-5). Some structural elements,
rectangular, resistance welded at all intersections. It particularly footings, are sometimes made of plain con-
may be supplied in either rolls or sheets, depending on crete, however. Plain concrete is defined as structural

TABLE 1-1 Welded Wire Reinforcement (Meets ASTM A185, fy = 60 ksi)

Area of steel in.2/ft


Wire gauge W-number (each direction) Wire diameter (in.)

6 * 6@10 * 10 6 : 6@W1.4 : W1.4 0.029 0.135 (10ga)


6 * 6@8 * 8 6 : 6@W2.0 : W2.0 0.041 0.162 (8ga)
6 * 6@6 * 6 6 : 6@W2.9 : W2.9 0.058 0.192 (6ga)
6 * 6@4 * 4 6 : 6@W4.0 : W4.0 0.080 0.225 (4ga)
4 * 4@10 * 10 4 : 4@W1.4 : W1.4 0.043 0.135 (10ga)
4 * 4@8 * 8 4 : 4@W2.0 : W2.0 0.062 0.162 (8ga)
4 * 4@6 * 6 4 : 4@W2.9 : W2.9 0.087 0.192 (6ga)
4 * 4@4 * 4 4 : 4@W4.0 : W4.0 0.120 0.225 (4ga)
8 CHApTER ONE

FIGURE 1-5 Concrete


construction in progress.
Note formwork, reinforcing
bars, and pumping of
concrete.
(George Limbrunner)

concrete with no reinforcement or with less reinforce- foundation and basement walls), the specified con-
ment than the minimum amount specified for rein- crete cover is 30. These members are typically placed
forced concrete. Plain concrete is discussed further in without the use of forms. For concrete elements
Chapter 10. not cast against soil or ground, but exposed to the
weather or in contact with ground, the specified con-
crete cover is 20 for No. 6 through No. 18 bars, and
1-9 CONCRETE COVER 1.50 for No. 5 and smaller bars. The surfaces of these
The clear distance between the concrete surface and the members would typically be formed. The presence of
face of the rebar is called the cover. The reinforcement forms allows for greater accuracy in establishing the
in concrete needs to have this cover for several reasons: proper clear cover distance.
The fire protection requirements of the Code may
• To protect the reinforcement against corrosion sometimes necessitate a higher concrete cover than
• To provide adequate surface area for bond between the above-specified concrete covers, depending on the
the concrete and the reinforcement required fire rating. See Chapter 14 for discussions
• To protect the reinforcement against loss of on concrete cover requirements as a function of the
strength in a fire fire ratings.

For protection against corrosion and to ensure


adequate bond between the reinforcement and the 1-10 BEAMS: MECHANICS
surrounding concrete, ACI 318-14 Table 20.6.1.3.1
specifies the concrete cover requirements for cast-
OF BENDING REVIEW
in-place reinforced concrete members. For slabs and The concept of bending stresses in homogeneous elas-
walls not exposed to weather or in contact with the tic beams is generally discussed at great length in all
ground, the minimum clear cover to the outermost strength of materials textbooks and courses. Beams
reinforcement surface is 3>4 ″ for No. 11 and smaller composed of material such as steel or timber are cat-
bars, and 1.50 for No. 14 and larger bars. For beams egorized as homogeneous, with each exhibiting elas-
and columns not exposed to weather or in contact tic behavior up to some limiting point. Within the
with the ground, the minimum clear cover to the out- limits of elastic behavior, the internal bending stress
ermost reinforcement surface is 1.50. For all structural distribution developed at any cross section is linear
elements cast against and permanently in contact with (straight line), varying from zero at the neutral axis to
soil or ground (e.g., footings, caissons, grade beams, a maximum at the outer fibers.
Materials and Mechanics of Bending, and Concrete Slab Systems 9

The accepted expression for the maximum bend- homogeneous or nonhomogeneous beams having
ing stress in a beam is termed the flexure formula, linear (straight-line) or nonlinear stress distributions.
For reinforced concrete beams, it has the advantage of
Mc using the basic resistance pattern found in the beam.
fb =
I The following three analysis examples dealing
with plain (unreinforced) concrete beams provide
where an introduction to the internal couple method. Note
f b = calculated bending stress at the outer fiber of that the unreinforced beams are considered homo-
the cross section geneous and elastic. This is valid if the moment is
small and tensile bending stresses in the concrete
M = the applied moment
are low (less than the tensile bending strength of the
c = distance from the neutral axis to the outside
concrete) with no cracking of the concrete develop-
tension or compression fiber of the beam ing. For this condition, the entire beam cross section
I = moment of inertia of the cross section about carries bending stresses. Therefore, the analysis for
the neutral axis bending stresses in the uncracked beam can be based
The flexure formula represents the relationship on the properties of the gross cross-sectional area
between bending stress, bending moment, and the using the elastic-based flexure formula. The use of
geometric properties of the beam cross section. By rear- the flexure formula is valid as long as the maximum
ranging the flexure formula, the maximum moment tensile stress in the concrete does not exceed the
that may be applied to the beam cross section, called modulus of rupture fr. If a moment is applied that
the resisting moment, MR, may be found: causes the maximum tensile stress just to reach the
modulus of rupture, the cross section will be on the
FbI verge of cracking. This moment is called the cracking
MR = moment, Mcr.
c
These examples use both the internal couple
where Fb = the allowable bending stress. approach and the flexure formula approach so that the
This procedure is straightforward for a beam of results may be compared.
known cross section for which the moment of inertia
can easily be found. For a reinforced concrete beam, Example 1-1
however, the use of the flexure formula presents some A normal-weight plain concrete beam is 6 in. * 12 in. in
complications, because the beam is not homogeneous cross section, as shown in Figure 1-6. The beam is simply
and concrete does not behave elastically over its full supported on a span of 4 ft and is subjected to a midspan
range of strength. As a result, a somewhat different concentrated load of 4500 lb. Assume f′c = 3000 psi.
approach that uses the beam’s internal bending stress
distribution is recommended. This approach is termed a. Calculate the maximum concrete tensile stress using
the internal couple method. the internal couple method.
Recall from strength of materials that a couple b. Repeat part (a) using the flexure formula approach.
is a pure moment composed of two equal, opposite, c. Compare the maximum concrete tensile stress
and parallel forces separated by a distance called with the value for modulus of rupture fr using the
the moment arm, which is commonly denoted Z. In ACI-recommended value based on f′c.
the internal couple method, the couple represents
an internal resisting moment and is composed of a Solution:
compressive force C above the neutral axis (assum- Calculate the weight of the beam (weight per unit length):
ing a single-span, simply supported beam that
develops compressive stress above the neutral axis) weight of beam = volume per unit length * unit weight
and a parallel internal tensile force T below the 6 in.112 in.2
= (150 lb>ft3)
neutral axis. 144 in.2 >ft2
As with all couples, and because the forces acting
= 75 lb>ft
on any cross section of the beam must be in equilib-
rium, C must equal T. The internal couple must be Calculate the maximum applied moment:
equal and opposite to the bending moment at the same
PL wL 2
location, which is computed from the external loads. It Mmax = +
4 8
represents a couple developed by the bending action
4500 lb14 ft2 75 lb>ft14 ft22
of the beam. = +
The internal couple method of determining beam 4 8
strength is more general and may be applied to = 4650 ft @ lb
10 CHApTER ONE

4500 lb
2'-0 A 6"

6"
N.A.
x x 12"
A
RA RB
4'- 0
Load Diagram Section A–A
(a) (b)

FIGURE 1-6 Loading diagram and section for Example 1-1.

a. Internal couple method 4. C = average stress * area of beam on which


1. Because the beam is homogeneous, elastic, and stress acts
symmetrical with respect to both the X–X and Y–Y C = 1 1
2 ftop1ytop21b2 = 2 ftop16 in.216 in.2 = 6975 lb
axes, the neutral axis (N.A.) is at midheight. Stresses
and strains vary linearly from zero at the neutral axis
Solving for ftop yields
(which is also the centroidal axis) to a maximum at
the outer fiber. As the member is subjected to posi- ftop = 388 psi = fbott
tive moment, the area above the N.A. is stressed in
compression and the area below the N.A. is stressed The modulus of elasticity of the concrete,
in tension. These stresses result from the bending
behavior of the member and are shown in Figure 1-7. Ec = 57,0001f′c = 57,00013000 psi
2. C represents the resultant compressive force above = 3,122,019 psi
the N.A. T represents the resultant tensile force be-
low the N.A. C and T each act at the centroid of their The concrete strain at the top of the beam is
respective triangles of stress distribution. Therefore,
ftop 388 psi
Z = 8 in. C and T must be equal (since ΣHF = 0). etop = = = 0.000124 in. > in.
The two forces act together to form the internal couple Ec 3,122,019 psi
(or internal resisting moment) of magnitude CZ or TZ.
3. The internal resisting moment must equal the bend- b. Flexure formula approach
ing moment due to external loads at any section.
Therefore, 6(123)
bh3
M = CZ = TZ I = = = 864 in.4
12 12
4650 ft @ lb (12 in.>ft) = C (8 in.)
Mc 46501122162
from which ftop = fbott = = = 388 psi
I 864
C = 6975 lb = T

Midspan
ftop

2"
C
6"

Z = 8"

6"
T
2"

fbott
RA 2'-0
Free Body Stress Internal Couple
(a) (b) (c)

FIGURE 1-7 Stress and internal couple diagram for Example 1-1.
Materials and Mechanics of Bending, and Concrete Slab Systems 11

c. The ACI-recommended value for the modulus of rupture a. Using the internal couple method
(based on f′c) is
Z = 14 - 212.332 = 9.34 in.
fr = 7.5l 1f′c = 7.511.02 13000 C = T = 12 10.4742182172 = 13.27 kips
fr = 411 psi 13.2719.342
Mcr = CZ = TZ = = 10.33 ft. @kips
12
The calculated tensile stress (fbott) of 388 psi is about
6% below the modulus of rupture, the stress at which flex-
b. Check using the flexure formula
ural cracking would be expected.
Mc
Example 1-1 is based on elastic theory and f =
I
assumes the following: (1) a plane section before fr I
bending remains a plane section after bending (the MR = Mcr =
c
variation in strain throughout the depth of the mem- 811423
bh3
ber is linear from zero at the neutral axis), and (2) the I = = = 1829 in.4
12 12
modulus of elasticity is constant; therefore, stress
fr I 0.474118292
is proportional to strain and the stress distribution Mcr = = = 10.32 ft. @ kips
c 71122
throughout the depth of the beam is also linear from
zero at the neutral axis to a maximum at the outer
The internal couple method may also be used to
fibers.
analyze irregularly shaped cross sections, although for
The internal couple approach may also be used to
homogeneous beams it is more cumbersome than the
find the moment strength (resisting moment) of a beam.
use of the flexure formula.

Example 1-2
Example 1-3
Calculate the cracking moment Mcr for the plain concrete
Calculate the cracking moment (resisting moment) for the
beam shown in Figure 1-8. Assume normal-weight concrete
T-shaped unreinforced concrete beam shown in Figure 1-9.
and f′c = 4000 psi.
Use f′c = 4000 psi. Assume positive moment (compression
a. Use the internal couple method. in the top). Use the internal couple method and check using
b. Check using the flexure formula. the flexure formula.

Solution: Solution:

The moment that produces a tensile stress just equal to the The neutral axis must be located so that the strain and stress
modulus of rupture fr is called the cracking moment, Mcr. diagrams may be defined. The location of the neutral axis
The modulus of rupture for normal-weight concrete is calcu- with respect to the noted reference axis is calculated from
lated from ACI Equation 19.2.3.1:
Σ(Ay)
y =
fr = 7.51f′c = 7.514000 = 474 psi ΣA
412021222 + 512021102
=
For convenience, we will use force units of kips (1 kip = 41202 + 51202
1000 lb). Therefore, fr = 0.474 ksi. = 15.33 in.

8" 474 psi

2.33"
C
7"

N.A.
14" Z

T
2.33"

474 psi
Beam Bending Stress Internal
Cross Section at Max. M Couple
(a) (b) (c) FIGURE 1-8 Sketch for Example 1-2.
12 CHApTER ONE

20" ftop

4" +
C
6.67" 8.67"
4.67"
N.A.

5.33" Z
20" + 10.22"
y = 15.33"
T

R.A.
5" fbott
Beam Bending Stress Internal
Cross Section at Max. M Couple FIGURE 1-9 Sketch for
(a) (b) (c) Example 1-3.

The bottom of the cross section is stressed in tension. The total tensile force can be evaluated as follows:
Note that the stress at the bottom will be numerically larger T = average stress * area
than at the top because of the relative distances from the
= 12 10.4742115.332152 = 18.17 kips
N.A. The stress at the bottom of the cross section will be set
equal to the modulus of rupture (l = 1.0 for normal-weight and its location below the N.A. is calculated from
2
concrete): 3 115.332 = 10.22 in. 1below the N.A.2

f bott = fr = 7.5l1f′c = 7.511.02 14000 = 474 psi = 0.474 ksi The compressive force will be broken up into compo-
nents because of the irregular area, as shown in Figure 1-10.
Using similar triangles in Figure 1-9b, the stress at the Referring to both Figures 1-9 and 1-10, the component
top of the flange is internal compressive forces, component internal couples, and
MR may now be evaluated. The component forces are first
8.67
ftop = 10.4742 = 0.268 ksi calculated:
15.33
C1 = 0.14441202142 = 11.55 kips
The modulus of elasticity of the concrete, C2 = 1
10.123621202142 = 4.94 kips
2
1
Ec = 57,0001fc′ = 57,00014000 psi = 3,605,000 psi C3 = 2 10.1444215214.672 = 1.686 kips
total C = C1 + C2 + C3 = 18.18 kips
The concrete strain at the top of the beam is
C ≈ T 1O.K.2
ftop 268 psi
etop = = = 0.000074 in.>in. Next we calculate the moment arm distance from each
Ec 3,605,000 psi component compressive force to the tensile force T:
1
Similarly, the stress at the bottom of the flange is Z1 = 10.22 + 4.67 + 2 14.002 = 16.89 in.
2
4.67 Z2 = 10.22 + 4.67 + 3 14.002 = 17.56 in.
fbott of flange = 10.4742 = 0.1444 ksi 2
15.33 Z3 = 10.22 + 3 14.672 = 13.33 in.

C3 C1

C2

N.A.

0.1444 ksi
0.1444 ksi

0.1236 ksi
FIGURE 1-10 Component compression forces for Example 1-3.
Materials and Mechanics of Bending, and Concrete Slab Systems 13

The magnitudes of the component internal couples are 1 2


then calculated from force × moment arm as follows: 30'-0"

18"
MR1 = 11.55116.892 = 195.1 in. @ kips
A
MR2 = 4.94117.562 = 86.7 in. @ kips
MR3 = 1.686113.332 = 22.5 in. @ kips

l1 = 33'-0"
Mcr = MR = MR1 + MR2 + MR3 = 304 in. @ kips

36'-0"
Check using the flexure formula. The moment of inertia
is calculated using the transfer formula for moment of inertia
from statics: B
I = Σ Io + Σ Ad 2

18"
18" l2 = 13'-6" 18"
1 1
I = (20)(43) + 12 (5)(203) + 4(20)(6.672) + 5(20)(5.332)
12
= 9840 in.4 FIGURE 1-11 Load distribution in one-way slab
systems.
fr I 0.474198402
Mcr = MR = = = 304 in. @ kips
c 15.33
1Checks O.K.2 Two-Way Slab Systems
As mentioned previously, the three examples are Two-way concrete slab systems are supported on col-
for plain, unreinforced, and uncracked concrete beams umns and span in two orthogonal directions, or the
that are considered homogeneous and elastic within slab is supported on all four sides by beams or walls
the bending stress limit of the modulus of rupture. The and the curvature of the slab, and the load transfer
internal couple method is also applicable to nonho- occurs in both orthogonal directions (see Figure 1-12).
mogeneous beams with nonlinear stress distributions A two-way slab system occurs when the clear span
of any shape, however. Because reinforced concrete of the longer side of the rectangular slab panel (/1)
beams are nonhomogeneous, the flexure formula is is less than twice the clear span of the shorter side
not directly applicable. Therefore, the basic approach of the slab panel (/2); that is, /1 >/2 6 2. Examples of
used for reinforced concrete beams is the internal cou- two-way slabs include flat plates, flat slabs, flat slabs
ple method (see Chapters 2 and 3). with beams, and slabs supported on stiff beams or
walls on all four sides of a rectangular slab panel.
Note that /1 is the larger dimension of the rectangu-
1-11 CONCRETE SLAB lar slab panel bounded on all four sides by columns
SYSTEMS or beams or walls and /2 is the smaller dimension of
the rectangular slab panel. Further treatment of two-
The two types of floor systems used in reinforced and way slab systems is covered in Chapter 6.
prestressed concrete structures are one way and two-
way slab systems.
1 2
One-Way Slab Systems 30'-0"
18"

One-way concrete floor systems are usually


supported by stiff beams or walls and the slab A
spans or bends predominantly in one direc-
tion (usually in the shorter direction of the rect-
angular slab panel) and the load transfer to the
l1 = 33'-0"

members supporting the slab occurs predomi-


36'-0"

nantly in the shorter direction (see Figure 1-11).


This is the case when the clear span of the longer
side of the rectangular slab panel (/1) is greater than
or equal to twice the clear span of the shorter side of
the slab (/2); that is, /1 >/2 Ú 2. In a reinforced or pre- B
18"

stressed concrete one-way slab system, the curva- l2 = 28'-6"


18" 18"
ture of the slab is predominantly in the shorter direc-
tion (i.e., parallel to the /2 dimension). The design of
one-way reinforced concrete slab systems is covered FIGURE 1-12 Load distribution in two-way slab
in Chapter 2. systems.
14 CHApTER ONE

1-12 GRAVITY LOAD • Glazing


DISTRIBUTION IN • Cladding
CONCRETE SLAB The weights of common building materials are
SYSTEMS given in Section C3 of ASCE 7-16. The density of
unreinforced concrete is approximately 145 lb/ft3
Reinforced concrete structures are subjected to a vari-
and the density of reinforced concrete is approxi-
ety of loads which includes dead loads, floor live
mately 150 lb/ft3.
loads, roof live loads, snow loads, hydrostatic pres-
sures, lateral soil pressures, wind loads, and seismic A sample dead load calculation for a building is as
or earthquake loads. In this section, we introduce the follows:
reader to the distribution of gravity loads in concrete
slab systems. Components of Roof Dead Load in a Reinforced
Gravity loads that act on structures include dead Concrete Building:
loads, floor live loads, snow loads, and roof live loads.
In concrete floor and roof systems, the pertinent load 5 ply + gravel = 6.5 psf
combinations that usually govern for ultimate strength Insulation and membrane = 3.5 psf
design are as follows: 4″ concrete slab ≅ 50 psf
Floor Slab: (slab weight = 4″>12 * 150 lb>ft 3 = 50 psf)
1.4D Mechanical/Electrical (M & E) ≅ 10 psf (20 psf for
1.2D + 1.6L industrial buildings)

Roof Slab: Suspended ceiling ≅ 2 psf


Total roof dead load, D ≅ 72 psf (unfactored)
1.4D
1.2D + 1.6 (Lr or S or R) + 0.5W
1.2D + 1.0W + 0.5(Lr or S or R) Components of Floor Dead Load in a Reinforced
Concrete Building:
where,
60 concrete slab1 = 75 psf
D = dead load
Floor finishes ≅ 8 psf (estimate weight of actual
L = floor live load
finishes specified by the architect)
Lr = roof live load
M & E ≅ 10 psf (20 psf for industrial building)
S = snow load
Suspended ceiling ≅ 2 psf
R = rain load
Partitions2, 3 ≅ 15 psf
W = wind load
Total floor dead load, D = 115 psf (unfactored)
When designing for serviceability limit state (e.g.,
deflections and vibrations), all the load factors in the
above load combinations (i.e., the “1.2” and “1.6”)
Tributary Width and Areas
default to 1.0 since serviceability is checked at work- In this section, we introduce the concept of tribu-
ing or service loads. For a detailed treatment of the tary area and tributary width. Beams in reinforced
different structural loads and the load combinations concrete floor or roof systems share the uniformly
prescribed in the Code, the reader should refer to distributed loads in proportion to their distance
References [11] and [12]. from adjacent parallel beams. The tributary width
(TW) of a beam is a measure of the total width of
floor or roof supported by the beam. The tributary
Dead Loads area (AT) is the area of the floor supported by a
The dead load is the weight of anything permanently structural element. For a beam, it is the product of
attached to the structure, including the self-weight of
the structure. Dead loads include the weight of the
following: 1
Weight of 6″ slab = 6″>12 * 150 lb>ft 3 = 75 psf
• Floor finishes 2
The minimum value per ASCE 7-16, Section 4.3.2, is 15 psf. Actual
weight of partitions may be higher.
• Partitions 3
The Code allows partition loads to be neglected whenever the floor
• Mechanical and electrical equipment and live load, L, is greater than or equal to 80 psf (ASCE 7-16, Section 4.3.2)
conduits (M & E)
Another random document with
no related content on Scribd:
„Hoekom die baas hy vra vir Swartbooi? Die baas hy het hom mos
opgepas. En al is hy weg, die baas hy het mos baja sjeld, hy kan
mos maklik betaal,” sê die skepsel met so ’n sataniese glimlaggie
van hartlike voldoening, dat ek somar lus voel om ’n handvol gruis by
sy keelgat af te druk.
Ek het gelukkig my £150 behou, want Swartbooi was eerlik
genoeg om die diamant aan sy baas terug te besorg, maar hierdie
voorvalletjie het vir my geleer hoe onmoontlik dit vir die delwer is om
sy werksvolk op te pas, en dat hy feitlik aan hulle genade oorgegee
is. Het hy eerlike kaffers, dan is dit ook nie nodig om hul op te pas
nie, maar het hy oneerlike volk, nou ja, dan moet hy maar self ’n plan
uitdink. Ek het nie raad vir hom nie.
Hoe Swartbooi daardie kosbare steentjie so vlak voor my oë kon
verduistermaan, weet ek tot vandag toe nog nie, maar die feit bly
daar dat hy dit wel gedoen het.
Nou, leser, sal jy miskien beter verstaan waarom die owerheid die
trepstelsel op die delwerye ingevoer het. Was dit nie in swang nie,
dan sou die onwettige diamanthandel welig op die diekens gefloreer
het, en sou die eerlike delwer maar baie min vrug op sy arbeid
gesien het. Selfs onder bestaande omstandighede gaan dit maar
moeilik en vind daar nog baie oneerlikheid plaas.
Maar ongelukkig is hierdie trepstelsel ’n uiters gevaarlike wapen in
die hande van die minder eerlike speurder, en kan dit alte maklik
gebeur dat die onskuldige persoon in die val gelei en gevang word.

II.
Koos Blikkies was ’n interessante persoonlikheid. Nie juis rysig
van gestalte nie, was hy die besitter van ’n paar krom bene en
besonder lang arms. As ’n mens hom op ’n afstand sien aankom,
dan dink jy onwillekeurig aan Darwin se ewolusieteorie. Beskou jy
hom egter van naderby en kyk jy hom reg in die oë, dan vergeet jy
heeltemal sy krom bene en sy abnormale arms. So ’n ope en eerlike
gesig sien jy nie aldag nie, en al is dit miskien ’n bietjie vuil van die
stof, dan nog trek dit dadelik die aandag van elkeen wat hom vir die
eerste keer ontmoet.
Die naam Blikkies, verstaan ek, het hy met die driejarige oorlog
verwerf. Hy was eintlik die groot man gewees om vyandelike forte op
te blaas. En vir hierdie doel het hy kondensmelkblikkies gebruik wat
hy met dinamiet gelaai het. Koos self het die bynaam as ’n eretietel
beskou en was selfs trots daarop.
„Ek hou baie van boerdery, maar die boerdery hou niks van my
nie,” het hy eendag geantwoord op my vraag wat of hom dan
delwerye-toe gedrywe het. Maar ek het later uitgevind dat Koos
Blikkies se bure en sogenaamde vriende so van sy goedhartigheid
en vrygewigheid misbruik gemaak het dat hulle hom totaal
gerinneweer het. Met ’n wa, ’n span osse, ’n tent, ’n vrou en ses
kinders, ’n paar pikke en grawe en £100 kontant het hy uit die
boerdery gestap en op Kreepoort geland.
Die eerste jaar het die Geluksgodin haar gesigskant vir hom
getoon en het hy goed geld gemaak. Maar hier het dit ook maar nes
voorheen op sy plaas gegaan. Sy bure wat minder gelukkig was as
hy, het so dikwels van hom geleen en so selde weer die geleende
terugbetaal, dat Koos Blikkies aan die end van die jaar ryk aan
vriende maar arm aan geld was.
„Ek kan tog nie die arme mense rondom my van ellende sien
vergaan nie, en hulle sal my weer op ’n ander keer help as ek in
verleentheid is,” het hy aan sy vrou gesê toe sy hom vir die
duisendste keer gesmeek het om tog minder rojaal geld en goed uit
te leen.
Koos Blikkies is een van die weinige mense op aarde wie se
vertroue in sy medemens nie maklik kan geskok word nie. Self so
eerlik, opreg, eenvoudig en goedhartig, kon hy nooit iemand anders
van verkeerde of oneerlike motiewe verdink nie. Maar aan die ander
kant het hy nie geskroom om ’n man in sy gesig te sê wat hy van
hom dink as hy hom op ’n skelmstuk betrap het nie. En by so ’n
geleentheid kon hy hom nogal van besonder keurige taal bedien.
Speurder Midas was g’n vriend van die delwers nie, en hy het
onomwonde verklaar dat in sy opienie al die delwers ’n klomp skurke
was. Die leser sal derhalwe maklik kan begryp waarom hy en die
delwers mekaar nie juis uit liefde omhels het nie. Op die delwerye
het die gerug weleens die rondte gedoen dat Midas self nie bo
verdenking was nie. En die een delwer het in sy buurman se oor
gefluister dat die oneerlike skurk minder kans staan om getrep te
word as die eerlike man. Ja, dat Midas self ’n aandeel had in die
I.D.B.
„Het oom Koos gehoor dat die arme Jan Emmer vanmôre vroeg
getrep is?” sê Gert Struis aan sy buurman.
„Jy wil tog nie vir my kom vertel dat daardie arme sukkelaar
gevang is nie? Ek sal nooit glo dat Jan Emmer skuldig is nie!” sê
Koos Blikkies, en sy oë blits van verontwaardiging.
„Ja, Oom, ek het so flussies gesien dat Midas hom dorp-toe vat.
Hy loop tussen twee kafferpolies, en een van hulle het my vertel dat
Jan Emmer vir I.D.B. gevang is,” gaan Gert voort.
„En wat moet nou van sy siek vrou en babetjie word?” vra Koos
Blikkies weer.
„Die Here alleen weet, Oom. Dis juis deur hulle wat hy getrep is.”
„Hoe kan dit deur hulle wees, man? Jy praat nou somar nonsens,”
sê Koos, en ’n mens kon sien dat hy hom vererg.
„Nee, tog nie, Oom. Gister was die dokter by Jan Emmer se tent
en hy het die vrou en die babetjie see-toe georder. As hulle nie gaan
nie, het hy gesê, dan sou hul nog uiters ’n ses maande kan lewe.
Oom weet seker hoe hardop die arme Jan is en hoe lank Midas al
probeer om vir hom te trep. Dis hierdie soort game wat Midas speel
wat my bloed laat kook. Hy wis dat Jan byna enigiets sou waag om
geld in die hande te kry, sodat hy sy vrou en kind kan see-toe stuur
volgens die dokter se orders, en nou maak Midas van Jan se ellende
gebruik om die arme sukkelaar te trep en...”
Hier raak Gert se verontwaardiging vir hom meester en kon hy nie
voortgaan nie.
„Skandelik!” roep Koos Blikkies, „skandelik! En dan is die vent
nogal kamtig iemand wat moet toesien dat die wet uitgevoer en die
orde gehandhaaf word. Maar kan ons dan niks doen om die arme
Jan uit die tronk te hou nie?”
„Ek vrees ons kan niks daaraan doen nie, Oom, want Jan is
werklik getrep. Verlede nag om drie-uur het ’n kaffertrep hom ’n tien-
carat aangebied vir £10 en Jan het in die strik geloop. Die gedagte
aan sy vrou en babetjie se toestand het natuurlik die deurslag
gegee. Maar is dit nou regverdig om iemand in Jan se toestand so in
die versoeking te bring? Is dit nou reg om ’n man wat nog altyd eerlik
en ordentlik was, in ’n skelm te herskep? Waarom probeer hy nie
liewer daardie Moor Seal vang nie? So wragtag, Oom, as hul
daardie duiwel van Kreepoort nie wegneem nie, dan word hy nog
gelynch!”
Hierdie laaste sin het Gert op so ’n toon geuit dat Koos Blikkies jou
werklik-waar moes skrik.
„As ek in Jan Emmer se plek was, dan sou ek dieselfde gedoen
het,” sê Koos Blikkies, „en die persoon wat vir so iemand ’n trep stel,
is absoluut uit die bose en verdien om gestraf te word honderd maal
meer as die arme slagoffer wat deur sy duiwelse lis gevang is.”
In ’n armoedige hut op Kreepoort lê ’n arme vrou en haar kindjie
op hulle uiterste; maar wat het die wet daarmee te maak? Jan
Emmer is skuldig en moet gestraf word!

III.
Die treppery van Jan Emmer het ’n groot opskudding verwek op
Kreepoort. Die volgende dag kon ’n mens orals tussen die kleims
groepies delwers druk in gesprek met mekaar opmerk. Dit het alles
oor die een onderwerp gegaan, en die gemoedere was net warm.
Het Koos Blikkies nie die delwers tot gematigdheid aangespoor nie,
dan weet die liewe Vader alleen wat sou plaasgevind het.
„Nie met geweld nie,” het hy gesê, „maar met uitoorlê sal ons vir
Midas die les leer. Moet net nie oorhaastig te werk gaan nie.” En
hierop het die delwers na hulle kleims toe gegaan en die verder
verloop van sake in Koos se hande gelaat.
Vir Gert Struis en Piet Visasie het hy sy planne meegedeel. „Dit
sal nooit gaan om teveel konfidante te hê nie, want dan is ons
geheim netnou op die vlakte,” het hy aan hulle gesê.
„Maar wat is dan Oom se planne?” vra Gert.
„Kyk, neef, ek het vanmôre weer ’n mooi vyftiencarat-klippie gekry;
Swartbooi het dit so ’n uur of wat gelede vir my gebring. Hy het dit
somar in die kleim uitgekap.”
„Maar hoor, Oom is darem gelukkig,” val Gert hom in die rede.
Sonder om notiesie te neem van Gert se interrupsie gaan Koos
Blikkies voort: „Ek kan vir Swartbooi vertrou, want jy weet seker dat
ek eenmaal sy lewe gered het—maar dis nou tot daar-en-toe—en ek
gaan hom as trep gebruik om daardie Moor Seal te vang. Want as ek
vir Seal gevang het, dan het ek vir Midas ook in die hande.”
„En is Oom nie bang om die diamant te verloor nie?” vra Gert.
„Glad nie, neef, glad nie; ou Swartbooi sal my nooit bedrieg nie, en
hy is vir Seal te slim. Maar ek het jou en Piet Visasie se hulp nodig.
Ek weet Piet is ’n kêrel wat sy mond kan hou en wat nie maklik skrik
nie.”
„En hoe sal Oom vir Midas vang deur vir Seal te trep?” vra Gert
weer.
„Dis te lank om vir jou nou al die redes vir my gevolgtrekkings hier
uiteen te sit. Oefen maar geduld; jou nuuskierigheid sal oor ’n dag of
wat bevredig word. Seal ag homself so veilig met sy onwettige
handel dat hy baie maklik gaan gevang word.”
„Nou goed, Oom kan op my reken. Laat hoor nou Oom se planne.”
„Kyk,” begin oom Koos, „Swartbooi vertel aan my dat hy Seal se
rolplek ken. En hy weet te sê dat Midas altyd sorg dra dat daar nooit
’n kafferpolies in die nabyheid kan kom nie. Nou het Swartbooi al vir
Seal gepols, en hy sê die Moor is baie gretig om besigheid te doen.
Ons weet ook dat Midas op Smartendal se groot dans is. Môre-
oggend om drie-uur gaan Swartbooi my vyftiencarat-diamant aan
Seal verkoop, en jy, Piet Visasie en ek, sowel as twee
kafferkonstabels gaan die Moor vang. Verstaan jy nou?”
„Ja, Oom, en as ons daardeur somar vir Jan Emmer ook kan
loskry, dan sal ek meer as beloon vir die moeite voel.”
„Wie weet, neef, wie weet? Miskien het alles vir die beste gebeur!”
En met hierdie woorde stap Koos Blikkies na sy tent toe.
Daardie nag is die net nog ’n slaggie uitgesprei, maar hierdie keer
om ’n regte roofvoël te vang, en dit was nie tevergeefs nie. Seal is
op heterdaad betrap, en daar was vyf ooggetuies!

IV.
Belangstelling sowel as nuuskierigheid het my hof-toe gedrywe op
die gedenkwaardige dag van 9 Junie, 192..., toe Jan Emmer en Seal
voor die regter moes verskyn.
Dit was op ’n Vrydag, en daar die meeste delwers tog op daardie
dag na Smartendal moes kom om hulle diamante te laat registreer
alvorens hulle dié mag verkoop, was die hofsaal ver te klein om die
skare van delwers te bevat en moes etlike honderde teleurgesteld
omdraai.
Daar is ’n doodse stilte in die hof toe die regter sy plek op die
regbank inneem, en toe Jan Emmer se naam uitgeroep word, kon ’n
mens ’n speld hoor val.
Die beskuldigde stap met lustelose tred die boks binne, en dit
moes ’n hart van staal gewees het wat op daardie oomblik g’n
medelyde met hom gehad het nie. Die versreël uit Gesang IV het my
onwillekeurig te binne geskiet: „Wordt ergens zo betreurenswaard ’n
schepsel Gods gevonden?” toe ek my oë op hom rig.
Met geboë hoof, arms wat slap langs sy liggaam hang, en oë wat
te skaam is om op te kyk, staan hy daar, waarlik ’n
betreurenswaardige skepsel Gods. Sy klere is nog vuil van die rooi
stof van die diekens, en sy hare hang in toiings oor sy voorkop. Ja,
ek kon sweer dat selfs oor die juts se gesig ’n sweem van jammerte
vir ’n oomblik geflits het.
„Jan Emmer, pleit jy skuldig of onskuldig op die aanklag?” vra die
publieke aanklaer.
„Skuldig,” klink die nouliks hoorbare antwoord.
„Jy pleit skuldig op die aanklag dat jy onwettig ’n ruwe diamant van
’n kaffer gekoop het,” sê die regter, „en as delwer behoort jy tog te
weet dat dit as ’n baie ernstige oortreding in die oog van die wet
beskou word. Jy weet ook wat die straf is in so ’n geval. Sover ek
weet was daar g’n versagtende omstandighede wat jou tot so ’n
misdaad gedrywe het, gewees nie, en daarom vonnis ek jou tot......”
Onverwags klink daar ’n stem van uit die gehoor in die hofsaal.
Verstoord kyk die regter in daardie rigting, en aan die uitdrukking op
sy gesig was dit duidelik te sien dat hy daardie persoon sonder
verder versuim gaan laat uitgooi. Dog tot aller verbasing verander
die kwaai uitdrukking op die juts se gesig, en op byna vriendelike
toon vra hy: „Weet u miskien iets van die saak af en wil u getuienis
aflê?”
„Ja, edelagbare,” sê Koos Blikkies, en sy stem klink helder deur
die hofsaal.
„Nou kom dan vorentoe en kom lê jou getuienis hier in die
getuiehokkie af,” herneem die regter.
Sonder om ’n oomblik te aarsel vleg Koos Blikkies sy weg deur die
gedrang na die getuieboks toe, en met ’n diep buiging aan die regter
en die jurielede begin hy sy verklaring, wat egter meer ’n pleidooi
was as iets anders:
„Edelagbare regter, en here lede van die jurie, ek weet ek praat
namens al die delwers van Kreepoort as ek u my hartlike dank
toebring vir die geleentheid om ’n woordjie ter verdediging van Jan
Emmer te spreek.” Ek het my verbaas oor die keurige taal waarvan
Koos Blikkies hom bedien en kon merk dat die regter en die jurie
ewe verbaas was as ek. „U het soewe van versagtende
omstandighede gewag gemaak,” gaan Koos voort, „en edelagbare
regter en lede van die jurie, as daar ooit versagtende omstandighede
bestaan het, dan was dit in hierdie geval wat u nou geroepe word om
vonnis oor te vel. Hier het u voor u ’n man wat beter dae geken het;
’n man uit ’n goeie huis, fyn opgevoed en getroud met ’n dame ewe
goedgekonnekteer as hy. Sonder sy eie toedoen bevind hy hom met
famielie en al op Kreepoort vandag; sy sogenaamde vriende,
waarvan party gegoede mense is, het hom tot die bedelstaf
gedrywe. Maar ek wil u kosbare tyd nie alte lank in beslag neem nie,
en sal dus nie verder oor die beskuldigde se verlede uitwei nie... Op
die delwerye het dit met die beskuldigde van sleg tot erger gegaan.
Die eerste ses maande het hy ’n blink geloop, en tot oormaat van
ramp word sy vrou en kind ernstig siek. Die dokter besoek die
delwerye, en op mooipraat van enige delwers beskuldigde se tent.
„‚Jou vrou en kind moet see-toe,’ raai die dokter aan, ‚anders gee
ek hul nog uiters ses maande om te lewe.’ Edelagbare, stel u nou in
die plek van die beskuldigde! Ek weet u het ook ’n dierbare eggenoot
en kinders,—wat sou u gedoen het as u onder daardie
omstandighede die kans aangebied is om geld in hande te kry om
die kosbare lewe van u dierbares te red?—As u anders sou
gehandel het as Jan Emmer, dan is u van beter stoffasie gemaak as
hy en ek en die gewone delwer.”
Hier breek Koos Blikkies se woordevloed vir ’n oomblik af, en die
hoofde van al die teenwoordiges gee ’n nouliks sigbare knik van
instemming met sy pleidooi.
„Ten volle bewus van Jan Emmer se ellendige toestand,” vervolg
Koos Blikkies, „stel Midas, wat u ’n speurder noem, maar vir wie ons
’n minder vleiende naam het, sy trep vir hom.” Met moeite bedwing
die spreker hom, en met ’n stem wat van verontwaardiging tril, bars
hy uit: „Is dit nou reg en geregtigheid, edelagbare regter en here lede
van die jurie, om ’n man wat in Jan Emmer se gemoedstoestand
verkeer, te trep?—Dis die werk van die duiwel, edelagbare, dis uit
die bose!”
Koos bly weer ’n rukkie stil. ’n Mens kon sien dat èn die juts èn die
jurie getroffe was. „Ons pleit vir die ligste straf wat u kan oplê,
edelagbare. As dit moontlik is, vra ons om die genade van die hof.
Kan dit egter nie, dan versoek ons nederig om ’n opgeskorte vonnis
of ’n geldelike boete, want dié sal ons betaal, en namens die
delwersgemeenskap beloof ek dat ons sal sorg dra dat die
beskuldigde saam met sy vrou en kind see-toe sal gestuur word.
Ons onderwerp ons volgaarne aan u uitspraak.”
Koos Blikkies gaan sit, en die atmosfeer is nou so gespanne dat ’n
mens amper bang voel om asem te haal.
Die jurie is sigbaar aangedaan, en hoewel die regter niks laat
merk nie, kon ’n mens tog aan sy stem hoor dat ook hy onder die
betowering van Koos Blikkies se welsprekendheid geraak het.
„Ek simpatiseer met jou, Jan Emmer,” sê die regter eindelik, „want
die bose self kon nie ’n beter tyd en geleentheid uitgesoek het om
jou val te bewerkstellig as wat Midas die speurder geprakseer het
nie. Maar jy is skuldig, en die wet moet gehoorsaam word. Ek maak
jou straf egter so lig as ek kan, en hiervoor moet jy die vriend wat so
’n kragtige pleidooi vir jou gelewer het, danksê. Dis jou eerste
misdaad, en die vonnis van die hof lui: agtien maande tronkstraf,
opgeskort vir agtien maande! Laat dit vir jou ’n waarskuwing wees!”
Noudat die spanning van die laaste paar uur verby is, vergeet die
delwers glad waar hulle is. Dit klap in die hande en stamp met die
voete dat hoor en sien vergaan. Dit het moeite gekos om weer stilte
in die hof te verkry.
Dit was die merkwaardigste hofsitting wat ek ooit in my lewe
bygewoon het.
Seal is gevonnis, en Midas se medepligtigheid het met die verhoor
uitgekom. Hy is saam gevonnis en later uit die diens ontslaan.
Jan Emmer se vrou en kind is fris en gesond, en hulle woon nie
meer op die delwerye nie. Hy is voorman op Koos Blikkies se plaas.
Laasgenoemde se geluk het spreekwoordelik geword op Kreepoort,
en ’n jaar na die hofsitting het hy genoeg geld gemaak om ’n mooi
plaas te koop en kontant af te betaal.
Ek hoop ek klap nie uit die skool as ek aan die nuuskierige leser
vertel dat Koos Blikkies in die jaar 18... een van die briljantste
debatteerders was wat ooit op die Kollegebanke in Kaapstad gesit
het.
HIERDIE BOEK IS GEDRUK DEUR
MASKEW MILLER BEPERK,
IN HUL STANDERD-PERS, KAAPSTAD.

MASKEW MILLER SE

LEES-MET-LUS
LEESBOEKE
DEUR
P. IMKER HOOGENHOUT, B.A.,
J. P. BOTHA, B.A., en P. M. van der LINGEN, B.A.
(Skoolinspekteurs in Transvaal.)
Die boekies bevat ’n groot aantal illustrasies, waarvan die
meerderheid heeltemaal origineel, en die inhoud van die boekies is
fris en lewendig.
Dit is die bedoeling van die skrywers om ’n serie Leesboeke in die
skool te bring wat alles wat tot dusver uitgegee is, sal oortref.
VIR SUB-STANDERD A. OF GRAAD I.

Eerste Boekie
Twede Boekie

VIR SUB-STANDERD B. OF GRAAD II.

Derde Boekie

VIR DIE STANDERDS:

Standerd Een.
Standerd Twee.
Standerd Drie.
Standerd Vier.
Standerd Vyf.
Standerd Ses.
Standerd Sewe.

Maskew Miller Beperk


KAAPSTAD

MASKEW MILLER’S

English Readers
FOR

SOUTH AFRICAN SCHOOLS


AND SCHOLARS
A Series of Ten Books, including a Teachers’ Handbook
THE WHOLE UNDER THE EDITORSHIP OF
Mr. JAMES RODGER, M.A.
Inspector J. F. SWANEPOEL, B.A.
Inspector CHARLES HOFMEYR, B.A.
The Series referred to above is the result of many months
thought and practical experiment on the part of the editors, two of
whom—Inspectors of Education for the Cape Province—have for
some years made the teaching of English to Afrikaans-speaking
children a special study, and it is in a measure to provide a well
graded series, with a distinct South African atmosphere, that this
work has been undertaken.
The format of the series will be uniform in style and size with that
highly successful series of Afrikaanse Leesboeke „Lees met Lus.”
MASKEW MILLER, LIMITED
CAPE TOWN
*** END OF THE PROJECT GUTENBERG EBOOK OP DIE
DELWERYE ***

Updated editions will replace the previous one—the old editions will
be renamed.

Creating the works from print editions not protected by U.S.


copyright law means that no one owns a United States copyright in
these works, so the Foundation (and you!) can copy and distribute it
in the United States without permission and without paying copyright
royalties. Special rules, set forth in the General Terms of Use part of
this license, apply to copying and distributing Project Gutenberg™
electronic works to protect the PROJECT GUTENBERG™ concept
and trademark. Project Gutenberg is a registered trademark, and
may not be used if you charge for an eBook, except by following the
terms of the trademark license, including paying royalties for use of
the Project Gutenberg trademark. If you do not charge anything for
copies of this eBook, complying with the trademark license is very
easy. You may use this eBook for nearly any purpose such as
creation of derivative works, reports, performances and research.
Project Gutenberg eBooks may be modified and printed and given
away—you may do practically ANYTHING in the United States with
eBooks not protected by U.S. copyright law. Redistribution is subject
to the trademark license, especially commercial redistribution.

START: FULL LICENSE


THE FULL PROJECT GUTENBERG LICENSE
PLEASE READ THIS BEFORE YOU DISTRIBUTE OR USE THIS WORK

To protect the Project Gutenberg™ mission of promoting the free


distribution of electronic works, by using or distributing this work (or
any other work associated in any way with the phrase “Project
Gutenberg”), you agree to comply with all the terms of the Full
Project Gutenberg™ License available with this file or online at
www.gutenberg.org/license.

Section 1. General Terms of Use and


Redistributing Project Gutenberg™
electronic works
1.A. By reading or using any part of this Project Gutenberg™
electronic work, you indicate that you have read, understand, agree
to and accept all the terms of this license and intellectual property
(trademark/copyright) agreement. If you do not agree to abide by all
the terms of this agreement, you must cease using and return or
destroy all copies of Project Gutenberg™ electronic works in your
possession. If you paid a fee for obtaining a copy of or access to a
Project Gutenberg™ electronic work and you do not agree to be
bound by the terms of this agreement, you may obtain a refund from
the person or entity to whom you paid the fee as set forth in
paragraph 1.E.8.

1.B. “Project Gutenberg” is a registered trademark. It may only be


used on or associated in any way with an electronic work by people
who agree to be bound by the terms of this agreement. There are a
few things that you can do with most Project Gutenberg™ electronic
works even without complying with the full terms of this agreement.
See paragraph 1.C below. There are a lot of things you can do with
Project Gutenberg™ electronic works if you follow the terms of this
agreement and help preserve free future access to Project
Gutenberg™ electronic works. See paragraph 1.E below.
1.C. The Project Gutenberg Literary Archive Foundation (“the
Foundation” or PGLAF), owns a compilation copyright in the
collection of Project Gutenberg™ electronic works. Nearly all the
individual works in the collection are in the public domain in the
United States. If an individual work is unprotected by copyright law in
the United States and you are located in the United States, we do
not claim a right to prevent you from copying, distributing,
performing, displaying or creating derivative works based on the
work as long as all references to Project Gutenberg are removed. Of
course, we hope that you will support the Project Gutenberg™
mission of promoting free access to electronic works by freely
sharing Project Gutenberg™ works in compliance with the terms of
this agreement for keeping the Project Gutenberg™ name
associated with the work. You can easily comply with the terms of
this agreement by keeping this work in the same format with its
attached full Project Gutenberg™ License when you share it without
charge with others.

1.D. The copyright laws of the place where you are located also
govern what you can do with this work. Copyright laws in most
countries are in a constant state of change. If you are outside the
United States, check the laws of your country in addition to the terms
of this agreement before downloading, copying, displaying,
performing, distributing or creating derivative works based on this
work or any other Project Gutenberg™ work. The Foundation makes
no representations concerning the copyright status of any work in
any country other than the United States.

1.E. Unless you have removed all references to Project Gutenberg:

1.E.1. The following sentence, with active links to, or other


immediate access to, the full Project Gutenberg™ License must
appear prominently whenever any copy of a Project Gutenberg™
work (any work on which the phrase “Project Gutenberg” appears, or
with which the phrase “Project Gutenberg” is associated) is
accessed, displayed, performed, viewed, copied or distributed:
This eBook is for the use of anyone anywhere in the United
States and most other parts of the world at no cost and with
almost no restrictions whatsoever. You may copy it, give it away
or re-use it under the terms of the Project Gutenberg License
included with this eBook or online at www.gutenberg.org. If you
are not located in the United States, you will have to check the
laws of the country where you are located before using this
eBook.

1.E.2. If an individual Project Gutenberg™ electronic work is derived


from texts not protected by U.S. copyright law (does not contain a
notice indicating that it is posted with permission of the copyright
holder), the work can be copied and distributed to anyone in the
United States without paying any fees or charges. If you are
redistributing or providing access to a work with the phrase “Project
Gutenberg” associated with or appearing on the work, you must
comply either with the requirements of paragraphs 1.E.1 through
1.E.7 or obtain permission for the use of the work and the Project
Gutenberg™ trademark as set forth in paragraphs 1.E.8 or 1.E.9.

1.E.3. If an individual Project Gutenberg™ electronic work is posted


with the permission of the copyright holder, your use and distribution
must comply with both paragraphs 1.E.1 through 1.E.7 and any
additional terms imposed by the copyright holder. Additional terms
will be linked to the Project Gutenberg™ License for all works posted
with the permission of the copyright holder found at the beginning of
this work.

1.E.4. Do not unlink or detach or remove the full Project


Gutenberg™ License terms from this work, or any files containing a
part of this work or any other work associated with Project
Gutenberg™.

1.E.5. Do not copy, display, perform, distribute or redistribute this


electronic work, or any part of this electronic work, without
prominently displaying the sentence set forth in paragraph 1.E.1 with
active links or immediate access to the full terms of the Project
Gutenberg™ License.
1.E.6. You may convert to and distribute this work in any binary,
compressed, marked up, nonproprietary or proprietary form,
including any word processing or hypertext form. However, if you
provide access to or distribute copies of a Project Gutenberg™ work
in a format other than “Plain Vanilla ASCII” or other format used in
the official version posted on the official Project Gutenberg™ website
(www.gutenberg.org), you must, at no additional cost, fee or expense
to the user, provide a copy, a means of exporting a copy, or a means
of obtaining a copy upon request, of the work in its original “Plain
Vanilla ASCII” or other form. Any alternate format must include the
full Project Gutenberg™ License as specified in paragraph 1.E.1.

1.E.7. Do not charge a fee for access to, viewing, displaying,


performing, copying or distributing any Project Gutenberg™ works
unless you comply with paragraph 1.E.8 or 1.E.9.

1.E.8. You may charge a reasonable fee for copies of or providing


access to or distributing Project Gutenberg™ electronic works
provided that:

• You pay a royalty fee of 20% of the gross profits you derive
from the use of Project Gutenberg™ works calculated using
the method you already use to calculate your applicable
taxes. The fee is owed to the owner of the Project
Gutenberg™ trademark, but he has agreed to donate
royalties under this paragraph to the Project Gutenberg
Literary Archive Foundation. Royalty payments must be
paid within 60 days following each date on which you
prepare (or are legally required to prepare) your periodic tax
returns. Royalty payments should be clearly marked as
such and sent to the Project Gutenberg Literary Archive
Foundation at the address specified in Section 4,
“Information about donations to the Project Gutenberg
Literary Archive Foundation.”

• You provide a full refund of any money paid by a user who


notifies you in writing (or by e-mail) within 30 days of receipt
that s/he does not agree to the terms of the full Project
Gutenberg™ License. You must require such a user to
return or destroy all copies of the works possessed in a
physical medium and discontinue all use of and all access
to other copies of Project Gutenberg™ works.

• You provide, in accordance with paragraph 1.F.3, a full


refund of any money paid for a work or a replacement copy,
if a defect in the electronic work is discovered and reported
to you within 90 days of receipt of the work.

• You comply with all other terms of this agreement for free
distribution of Project Gutenberg™ works.

1.E.9. If you wish to charge a fee or distribute a Project Gutenberg™


electronic work or group of works on different terms than are set
forth in this agreement, you must obtain permission in writing from
the Project Gutenberg Literary Archive Foundation, the manager of
the Project Gutenberg™ trademark. Contact the Foundation as set
forth in Section 3 below.

1.F.

1.F.1. Project Gutenberg volunteers and employees expend


considerable effort to identify, do copyright research on, transcribe
and proofread works not protected by U.S. copyright law in creating
the Project Gutenberg™ collection. Despite these efforts, Project
Gutenberg™ electronic works, and the medium on which they may
be stored, may contain “Defects,” such as, but not limited to,
incomplete, inaccurate or corrupt data, transcription errors, a
copyright or other intellectual property infringement, a defective or
damaged disk or other medium, a computer virus, or computer
codes that damage or cannot be read by your equipment.

1.F.2. LIMITED WARRANTY, DISCLAIMER OF DAMAGES - Except


for the “Right of Replacement or Refund” described in paragraph
1.F.3, the Project Gutenberg Literary Archive Foundation, the owner
of the Project Gutenberg™ trademark, and any other party
distributing a Project Gutenberg™ electronic work under this
agreement, disclaim all liability to you for damages, costs and
expenses, including legal fees. YOU AGREE THAT YOU HAVE NO
REMEDIES FOR NEGLIGENCE, STRICT LIABILITY, BREACH OF
WARRANTY OR BREACH OF CONTRACT EXCEPT THOSE
PROVIDED IN PARAGRAPH 1.F.3. YOU AGREE THAT THE
FOUNDATION, THE TRADEMARK OWNER, AND ANY
DISTRIBUTOR UNDER THIS AGREEMENT WILL NOT BE LIABLE
TO YOU FOR ACTUAL, DIRECT, INDIRECT, CONSEQUENTIAL,
PUNITIVE OR INCIDENTAL DAMAGES EVEN IF YOU GIVE
NOTICE OF THE POSSIBILITY OF SUCH DAMAGE.

1.F.3. LIMITED RIGHT OF REPLACEMENT OR REFUND - If you


discover a defect in this electronic work within 90 days of receiving it,
you can receive a refund of the money (if any) you paid for it by
sending a written explanation to the person you received the work
from. If you received the work on a physical medium, you must
return the medium with your written explanation. The person or entity
that provided you with the defective work may elect to provide a
replacement copy in lieu of a refund. If you received the work
electronically, the person or entity providing it to you may choose to
give you a second opportunity to receive the work electronically in
lieu of a refund. If the second copy is also defective, you may
demand a refund in writing without further opportunities to fix the
problem.

1.F.4. Except for the limited right of replacement or refund set forth in
paragraph 1.F.3, this work is provided to you ‘AS-IS’, WITH NO
OTHER WARRANTIES OF ANY KIND, EXPRESS OR IMPLIED,
INCLUDING BUT NOT LIMITED TO WARRANTIES OF
MERCHANTABILITY OR FITNESS FOR ANY PURPOSE.

1.F.5. Some states do not allow disclaimers of certain implied


warranties or the exclusion or limitation of certain types of damages.
If any disclaimer or limitation set forth in this agreement violates the
law of the state applicable to this agreement, the agreement shall be
interpreted to make the maximum disclaimer or limitation permitted

You might also like