Professional Documents
Culture Documents
Learning Outcomes
2
OFFICIAL (CLOSED) \ NON‐SENSITIVE
3
OFFICIAL (CLOSED) \ NON‐SENSITIVE
There are a few ways to create a project schedule: Blank Project, New from
existing project, New from Excel Worksheet, New from SharePoint task List, etc
4
OFFICIAL (CLOSED) \ NON‐SENSITIVE
The figure illustrates the appearance of your screen when you first
open Project based on the default settings. Notice the following
features of the interface:
• Microsoft Fluent Interface (also known as the Ribbon)
• The Quick Access toolbar
• The timeline (to be checked)
• The task entry grid
• The time‐phased Gantt Chart
• The status bar
Status bar 5
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Another way is to
click the “Gantt
Chart” button on
the ribbon and
View Bar the list will also
appear for your
selection.
6
OFFICIAL (CLOSED) \ NON‐SENSITIVE
7
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Basic Settings
1
3
5 Auto Scheduled
Weeks or Months if
6 necessary to change
Go to 1 3, adjust steps 4 to 6 8
OFFICIAL (CLOSED) \ NON‐SENSITIVE
It specifies the work hours for each work day, the work days
for each week, and any exceptions, such as holidays. You can
select a base calendar to use as the project calendar or as the
basis for a resource calendar. You can also apply a base
calendar to specific tasks.
9
OFFICIAL (CLOSED) \ NON‐SENSITIVE
10
OFFICIAL (CLOSED) \ NON‐SENSITIVE
13
OFFICIAL (CLOSED) \ NON‐SENSITIVE
14
OFFICIAL (CLOSED) \ NON‐SENSITIVE
15
OFFICIAL (CLOSED) \ NON‐SENSITIVE
16
OFFICIAL (CLOSED) \ NON‐SENSITIVE
17
OFFICIAL (CLOSED) \ NON‐SENSITIVE
18
OFFICIAL (CLOSED) \ NON‐SENSITIVE
19
OFFICIAL (CLOSED) \ NON‐SENSITIVE
21
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Resources are the people, equipment and supplies required to complete the
project within the defined constraints. Three different types of resources can
be entered using Microsoft Project:
Work resources
Material resources
Cost resource
Material resources are goods used by the work resources and here the
units-of-measure is an important gauge. Example, 20 cans of paint.
22
OFFICIAL (CLOSED) \ NON‐SENSITIVE
23
OFFICIAL (CLOSED) \ NON‐SENSITIVE
24
OFFICIAL (CLOSED) \ NON‐SENSITIVE
25
OFFICIAL (CLOSED) \ NON‐SENSITIVE
26
OFFICIAL (CLOSED) \ NON‐SENSITIVE
27
OFFICIAL (CLOSED) \ NON‐SENSITIVE
28
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Constraint types
As Late As Possible With this flexible constraint, Microsoft Office Project
schedules the latest possible start and finish dates for the task, given other
scheduling parameters. This is the default constraint for new tasks for a
project scheduled from the finish date.
As Soon As Possible With this flexible constraint, Project schedules the
earliest possible start and finish dates for the task, given other scheduling
parameters. No additional date restrictions are put on the task. This is the
default constraint for new tasks for a project scheduled from the start date.
Finish No Earlier Than This moderate constraint indicates the earliest
possible date that this task can be completed. It cannot finish any time
before the specified date.
For projects scheduled from the start date, this constraint is applied when
you type a finish date for a task.
Finish No Later Than This moderate constraint indicates the latest possible
date that this task can be completed. It can be finished on or before the
specified date.
For projects scheduled from the finish date, this constraint is applied when
you type a finish date for a task.
Must Finish On This inflexible constraint indicates the exact date on which
a task must finish. 29
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Constraint types
Must Start On This inflexible constraint indicates the exact date on which a
task must begin. Other scheduling parameters such as task dependencies,
lead or lag time, resource leveling, and delay become secondary to this
requirement.
Start No Earlier Than This moderate constraint indicates the earliest possible
date that this task can begin. It cannot start any time before the specified date.
For projects scheduled from the start date, this constraint is applied when you
type a start date for a task or drag a Gantt bar.
Start No Later Than This moderate constraint indicates the latest possible
date that this task can begin. It can start on or before the specified date.
For projects scheduled from the finish date, this constraint is applied when you
type a start date for a task.
31
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Task in which
constraint is
set
The
constraint
icon
The notes
icon
33
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Question:
How about adding a Lag time with “Print and ship” can
Lead time to a + 3 days only start 3 days after
Task?
“generate proofs” has
been completed
34
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Overallocation of Resources
There are chances that the resources are overallocated in a project plan. In
this Case Study, Carole Roland has been “overallocated” to a few more
tasks, a “red man” start to appear beside each task as shown in the indicator
column.
35
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Overallocation of Resources
You can view overallocation of resources in the “Resource Graph” view.
Overallocated
resource
36
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Resource leveling
You may use the function called “leveling” to delay, split the tasks to resolve
the issue. You can level certain resources or “Level All” to allow the software
to do it.
Resource
leveling
Leveling Leveling all
individual resources
37
resource
OFFICIAL (CLOSED) \ NON‐SENSITIVE
Resource leveling
Once it is levelled, the schedule may be changed to allocate the available
resource. You will observe that the overall duration has been delayed and
some tasks have been split to resolve the issue. Review the change in the
Leveling Gantt Chart view. If you are pleased with the results, save the file.
Areas of
changes
38
OFFICIAL (CLOSED) \ NON‐SENSITIVE
25% of
Completion
39
OFFICIAL (CLOSED) \ NON‐SENSITIVE
41