You are on page 1of 1

PROJECT TITLE : Improvement of Proposed Admin Office of CAAP Area Center III

LOCATION : Clark International Airport, Clark, Pampanga

REMEASURED QUANTITY

REMEASURED
ITEM DESCRIPTION BOQ UNIT LOCATION
QUANTITY
2.02 Tile Works
600mm x 600mm Homogenous Floor Tiles Polished Finish 1,448.00 1,071.00 pcs.
153.00 pcs. Hallway
56.00 pcs. Safety office
104.00 pcs. Planning and engineering office
24.00 pcs. Pantry
64.00 pcs. BAC Conference room
1F
24.00 pcs. COA storage
64.00 pcs. COA
48.00 pcs. Legal office
32.00 pcs. Property office
80.00 pcs. Storage room
324.00 pcs. Administrative / accounting office
35.00 pcs. Finance head
2F
21.00 pcs. File storage
42.00 pcs. Pantry

200mm x 1200mm Vinyl Tiles 300.00 460.00 pcs.


158.00 pcs. Corridor and hallway (left side)
80.00 pcs. Area manager's office
74.00 pcs. 2F Secretary area
112.00 pcs. Reception / Lounge area
36.00 pcs. Legal office

500mm x 500mm Carpet Tiles 185.00 171.00 pcs.


171.00 pcs. 2F Main conference room

300mm x 300mm Homogenous Floor Tiles 41.00 40.00 pcs.


40.00 pcs. 2F Toilet floor

300mm x 600mm Homogenous Polished Tiles 99.00 83.00 pcs.


83.00 pcs. 2F Toilet wall

600mm x 600mm Porcelain Tiles 25.00 24.00 pcs.


7 pcs. 1F Counter top at pantry
7 pcs. 2F Counter top at pantry
10 pcs. 3F Counter top at pantry