VEMAGIRI POWER GENERATION LIMITED SECTION: B

TITLE SHEET
SPEC. NO. COMBINED CYCLE POWER PLANT – 4
TCE.3837A-H-500-001 PROJECT INFORMATION

1.0 Owner : Vemagiri Power Generation Limited

2.0 Project Title : 370 MW CCPP at Vemagiri

3.0 Location : Located in Vemagiri, East Godavari District,


Andhra Pradesh, India

4.0 Power Station Site


Elevation Above
Mean Sea Level (MSL) : Finished Ground Level of Site : 24.5 m

5.0 Nearest Railway Station : Rajahmundry ( Distance from site– 5 km)

6.0 Nearest Town : Rajahmundry

7.0 Nearest Airport : Vizag ( Distance from site – 165 km)


Rajamundry ( With Deccan Aviation Service)

8.0 Nearest Sea Port : Vizag ( Distance from site – 165 km)
Kakinada (Distance from site – 50 km)

9.0 Road Approach : Nearest National Highway NH5 is 1.5 km from


project site.

10.0 Site Ambient Conditions

10.1 Highest ever temperature


recorded : 47.20C

10.2 Lowest ever temperature : 13.90C


recorded

10.3 Average Dry Bulb Temperature : 29.20C

10.4 Highest Wet Bulb Temperature : 27.60C

10.5 Average Wet Bulb Temperature : 24.90C

10.6 Relative Humidity

 Maximum – 81%
 Minimum – 61%

ISSUE
R0

CONSULTANT : TCE CONSULTING ENGINEERS LIMITED


VEMAGIRI POWER GENERATION LIMITED SECTION: B
TITLE SHEET
SPEC. NO. COMBINED CYCLE POWER PLANT – 4
TCE.3837A-H-500-001 PROJECT INFORMATION

11.0 Design Conditions for Combined Cycle Power Plant

11.1 Gas Turbine Building


Elevation : 500 mm above finished ground level
of site.

11.2 Dry Bulb Temperature : 29.2 0C

11.3 Relative Humidity : 71 %

11.4 Fuels for Combined Cycle Power plant : Natural Gas - Refer Table – 1

11.5 Raw Water Analysis : Refer Table – 3

11.6 Guarantee Conditions for Cooling Tower Performance:

11.6.1 Design Wet Bulb Temperature : 24.9 oC

11.6.2 Maximum Wet Bulb Temperature : 27.6 oC

12.0 Rainfall

12.1 Average Annual Rainfall : 1171.9 mm

13.0 Design Dry Bulb Temperature


for electrical equipment / System : 50 oC

14.0 Out Door Design Conditions : 43.5 oC Dry Bulb


for air conditioning and ventilation : 27.800c Wet Bulb
system.

15.0 Basic Wind speed : 55 m / sec

16.0 Earthquake Design Factor : Seismic zone III as per IS 1893

17.0 Auxiliary Power Supply : Auxiliary equipment to be supplied


against this specification shall
be suitable for operation on
the following supply.

ISSUE
R0

CONSULTANT : TCE CONSULTING ENGINEERS LIMITED


VEMAGIRI POWER GENERATION LIMITED SECTION: B
TITLE SHEET
SPEC. NO. COMBINED CYCLE POWER PLANT – 4
TCE.3837A-H-500-001 PROJECT INFORMATION

17.1 AC Motors
above 200 kW
:
6.6 kV, 3 , 3 wire, AC Supply
(Medium resistance earthed)
17.2 AC Motors
below 200 kW and other
:
415 V, 3 ,
3 wire, AC Supply
LT loads (Effectively earthed)

17.3 Plant lighting, utility power



sockets, space heating of : 240 V, 1 , AC Supply (Effectively
panels and space heating earthed)
of motors > 30 kW

17.4 Control Circuit of local


panels (like compressor : 110 V, 1 , 
AC Supply System
control, crane control etc.) (Derived from 415/110V step down
and 415 V switchgear transformer)
outgoing feeder modules
controls.

17.5 Utility power sockets :


required for hand lamps for 24 V, 1 , AC Supply
inspection of internals of
condensers, boilers, etc.

17.6 For control of switchgears, : 220V DC Supply


switchyard equipment, DC
emergency drives, DC
emergency lights,
switchyard and generator
protection panels, etc.

17.7 For Instrumentation & :  24 V DC or 48V DC or 110 V AC


Control supply (These voltage levels shall be
derived from 220 V DC supply)

19.0 Unless otherwise specified all electrical system shall be designed for
the following voltage and frequency variations :

19.1 A C System:

a) Voltage variations :  10 %
b) Frequency Variation : 5%
c) Combined Voltage &
Frequency Variation : 10 %

ISSUE
R0

CONSULTANT : TCE CONSULTING ENGINEERS LIMITED


VEMAGIRI POWER GENERATION LIMITED SECTION: B
TITLE SHEET
SPEC. NO. COMBINED CYCLE POWER PLANT – 4
TCE.3837A-H-500-001 PROJECT INFORMATION

19.2 DC System :

a) Voltage variation (220V) :  10%


b) Voltage variation : To suit equipment of I&C system
(24V or 48V)

19.3 UPS :  10 %

TABLE – 1

NATURAL GAS ANALYSIS

Source : Krishna Godavari Basin, Andhra Pradesh

Sl No Composition % Volume

1.1 Methane 91.01


1.2 Ethane 3.12
1.3 Propane 1.41
1.4 f- Butane 0.22
1.5 n – Butane 0.35
1.6 I - Pentane 0.08
1.7 n – Pentane 0.08
1.8 Nitrogen 0.09
1.9 Carbon-di-oxide 3.33

1.10 Hexanes 0.31

Analytical Data of fuel at 15C and 14.73 PSI

1. Compressibility factor Z3 - 0.9978


2. Specific Gravity – 0.6854
3. Calorific Value (Net) kcal / s m3 – 8489
4. Calorific Value (Gross) kcal / s m3 – 9382

Terminal point pressure of gas at plant boundary is 35 bar, temperature 150c.


and gas flow 1.64 million cu. metre per day at 35 bar pressure and 150 c temperature.

ISSUE
R0

CONSULTANT : TCE CONSULTING ENGINEERS LIMITED


VEMAGIRI POWER GENERATION LIMITED SECTION: B
TITLE SHEET
SPEC. NO. COMBINED CYCLE POWER PLANT – 4
TCE.3837A-H-500-001 PROJECT INFORMATION

TABLE –2

HIGH SPEED DIESEL ( HSD) ANALYSIS FOR EMERGENCY DG SET

CHARACTERISTIC QUALITY

1. Relative Density @ 15 oC / 15 oC 0.96

2. Flash Point FMCC oC Min. 32

3. Kinematic Viscosity cST 2.0 / 7.57 @


38 oC

4. Pour Point oC Max. 6(W) / 18 (S)

5. Sulphur % by weight Max. 1.0

6. Sediment % Weight Max. 0.05

7. Ash Weight Max. % 0.01

8. Water Content Vol. Max %. 0.05

9. Gross Calorific Value Kcals / 10500


kg (Avg.)

10. Meets IS : 1460 - 1974

ISSUE
R0

CONSULTANT : TCE CONSULTING ENGINEERS LIMITED


VEMAGIRI POWER GENERATION LIMITED SECTION: B
TITLE
SHEET 6 OF 6
SPEC. NO. COMBINED CYCLE POWER PLANT –
TCE.3837A-H-500-001 PROJECT INFORMATION

TABLE - 2

RAW WATER ANALYSIS

PARAMETER YEAR - 2000


JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
H
P 8.55 8.60 8.50 8.60 8.80 8.95 8.45 8.70 8.30 8.30 8.30 8.30
Turbidity (NTU) 13.70 8.50 7.60 7.00 4.40 19.40 29.80 42.50 12.90 17.50 15.70 12.40
Conductivity 240.00 230.00 230.00 220.00 230.00 210.00 200.00 200.00 220.00 230.00 250.00 240.00
us/cm
‘M’ Alka (ppm) 108.00 110.00 106.00 100.00 104.00 90.00 92.00 90.00 96.00 100.00 114.00 112.00
‘Ca’ Hard (ppm) 48.00 46.00 48.00 44.00 44.00 36.00 36.00 38.00 46.00 46.00 52.00 52.00
‘Mg’ Hard (ppm) 44.00 40.00 36.00 36.00 38.00 32.00 32.00 30.00 32.00 34.00 40.00 40.00
Chlorides (ppm) 32.00 34.00 34.00 34.00 34.00 32.00 28.00 30.00 32.00 32.00 26.00 32.00

ISSUE
P0
VEMAGIRI POWER GENERATION LIMITED SECTION: B
TITLE
SHEET 7 OF 6
SPEC. NO. COMBINED CYCLE POWER PLANT –
TCE.3837A-H-500-001 PROJECT INFORMATION

ISSUE
P0
VEMAGIRI POWER GENERATION LIMITED SECTION: B
TITLE SHEET
SPEC. NO. COMBINED CYCLE POWER PLANT – 4
TCE.3837A-H-500-001 PROJECT INFORMATION

ISSUE
P0