EASTERN RAILWAY

( Construction Department )
Fig in thousand
Sl.No. Name of Work Allocation Department Revised Expenditure Expected Final
upto Expdr from Modification
Pink Book Grant
FEB-22 &
Item distribution January-22 MARCH-22 Estimate
1 564/2021-22 Liluah-Modernisation 43679 50000
417/08-09 of workshop PLAN HEAD 42

2 572/2021-22 Liluah (J-Shop) -AC PLAN HEAD 42 4826 10000


502/15-16 Overhauling facilities

621/2021- Liluah workshop- PLAN HEAD 51 5000


22541/16-17 underground storm
3 waterdrinage system to
preventflooding(phase-I)

599© LLH-Upgradation and UMBRELLA WORK


(V)/2018- Augmentation of
19131/2020- infrastructural facility for
4 21 overhauling of RMPU during
POH of LHB coaches
ESTIMAT UNDER
PROCESS
599© LLH-Improvement in UMBRELLA WORK

5
(vi)/2018-19 infrastructure for critical
132/2020-21 coach component shops ESTIMAT UNDER
PROCESS
Liluah augmentation of PLAN HEAD 42 600
periodical/intermediate
6 overhauling of LHB coaches
from 10 to 30 coaches per
month.