EMPLOYEES’ TRUST FUND BOARD

PARTITION CONSTRUCTION

AT 22nd AND 23rd FLOORS – MEHEWARA PIYESA, COLOMBO 5

BILL OF QUANTITY

BOQ Description Unit Qty. Rate (Rs.) Amount (Rs.)


Item
A Aluminium Partition Work
Supplying, fabricating and installing Glass
& Boards two/ three rows of panels, black
colour matt finished anodized Aluminium
partition frame work with 0.9mm thick,
1 ½”x 1” rectangular Aluminium extrusions
as per the drawing. One row consist of
glass panel (5mm) in partition frame work
and other rows consist of 3mm (double
side PVC coated) single board. Rate
inclusive of necessary fasteners etc.
2 row partition Sqft 650.00
3 row partition Sqft 570.00
Supply and fixing 04 Nos. of 25mm x
50mm 1.2mm GI box bar support along
the Aluminium partition in 15’ gap, from
floor level to soffit. Painting new Item 01
galvanized iron GI Adhesion Promoter One
coat and One coat of Dulux metal primer
Zink chromate duco oil primer or
equivalent.
Supplying and fixing 2’x2’ ceiling panels
with necessary holes for GI extrusions. Nr 4.00
Panels should be similar to existing panels.
B Aluminium Doors
Supplying, fabricating and installing Glass
& Boards Aluminium Door sash with 0.9
mm thick, 1 ½”x 1” rectangular black
colour matt finished anodized Aluminium
extrusions as per the drawing details. One
row consist of glass panel (5mm) in frame Sqft. 105.00
work and other row consist of 3mm
(double side PVC coated) single board.
Rate inclusive of necessary fasteners, U
channels, rubber beadings etc.
Supplying and Fixing Stainless Steel Door
Handle for Aluminium door with necessary Nos. 12.00
accessories.
Supplying and Fixing UNION Butt Hinges,
4”x 3”x 2mm (thick) stainless steel, for pairs 9.00
Page 1 of 2
Aluminium doors with pop rivets.
Supplying and Fixing Door Closer (new star
or eq.) with necessary accessories Nr 4.00
Supplying and Fixing Door Lock (Alpha) for
Aluminium Door with necessary Nr 4.00
accessories to working order.
Bolts tower, 3”, heavy quality supplying Nr 2.00
and fixing with screws, rivets.
C Sand Blast Stickers
C1 Supplying & Fixing of Gauge 100 Microns Sqft. 260.00
sand blasting sticker including surface
preparation as per working order.
Sub Total 01
Contingencies ~10%
Sub Total 02
Allow For 15% VAT
Total Estimated Cost

Please Note:

1. Bidder shall visit the site before quoting and get an idea of the proposed work. Drawings of
same could be inspected at the ETF Board – Procurement Section, 23rd Floor, Mehewara Piyesa,
Colombo 5.
2. Contractor shall take necessary actions to avoid inconveniences causing to the office staff
during the works in progress.
3. Contractor shall carry out the works matching with existing partitions and provided drawings
4. Contractor shall take responsible that carrying the materials to upstairs from the ground floor.it
could be much convenience arranging after Office hours or on a Saturday or Sunday.
5. The Contractor shall provide all necessary tools equipment, Labours etc.

Name of the Contractor:

Address :

Contact person :

Contact Nos. :