Professional Documents
Culture Documents
Bridge Terminology
BRIDGE ENGINEERING
Kandahar University
Engineering Faculty
Civil Department
Samiullah Qani
1
2022/3/9
Deck
Deck is the main surface of a bridge over which traffic passes.
Deck transmit loads to the Girders
The purpose of the deck is to provide a smooth and safe riding surface for the
traffic.
Parapet
• Parapet is a railing system made of reinforced concrete along the outside edge of
a bridge deck used to protect vehicles and pedestrians.
2
2022/3/9
Kerb
Kerb a raised portion of road way slab on both sides .
kerbs serve to lessen the chance of vehicles crossing onto the sidewalk.
Kerb
Bearing
Bearings are supports on a bridge pier or pier cap.
Bearing transmit all loads from the superstructure to the substructure.
Permit longitudinal movement of the superstructure due to thermal expansion and
contraction.
3
2022/3/9
Pier
Pier is the part of the substructure that supports the superstructure
Pier transmit loads of the superstructure to the foundations.
The shape and size of pier mainly depend on aesthetics, site, space and economic
constraints of the construction.
Pier
Pier Cup
The highest part of a bridge pier on which the bridge bearings are seated.
Pier cup transmit loads from superstructure to the pier.
Pier cap provides sufficient seating for the girders.
Distributes the loads from the bearings to the piers.
4
2022/3/9
Abutments
• The end supports of superstructure of a bridge are called abutments
• They transmit the load from the superstructure to the foundation
• The depth of abutment should be adopted based on calculations
Approach Slab
• The slab provided to join the approach road with the bridge is known as
approach slab.
• One of its end should rest on the backfill of the abutment and should extend
into the approach at least by 3.5m.
• It should cover the full width of road
• The thickness of the R.C.C approach road maybe adopted as 15cms
10
5
2022/3/9
Approach Slab
11
Wingwall
o Wing walls are provided at both ends of the abutments to retain the earth
filling of the approaches.
o This wall can be constructed either integrally or independent with the
abutment wall.
Wing wall
12
6
2022/3/9
Aesthetics
The appearance is a measure of aesthetics
13
Backfill
• The material used to fill the space at the back of the bridge is known as backfill
• It may be broken stone, gravel, sand etc.
• It should be compacted at layers
• Cohesive backfill should be compacted in layers by rollers at optimum moisture
content to obtain the maximum dry density
• The backfill should be clean
14
7
2022/3/9
Economical span
The span for which the cost of super structure is equal to the cost of substructure
15
Diaphragm
Diaphragm – structural element(s) that distribute stresses and improve strength
and rigidity.
16
8
2022/3/9
Carriage Width
The minimum clear width of a road way is called carriage width
For a single lane bridge, the minimum carriage width should be a 4.5m
For a double lane, it should be 7.5m
For every additional lane, a minimum width of 3.5m must be allowed
17
Effective Span: The center to center distance between any two adjacent
supports of a bridge is called effective span
18
9
2022/3/9
Bedrock
The solid rock layer beneath sand or silt.
19
Bed Block
• The block resting over the top of the pier or abutment is called the bed block
• It provides bearing surface to the supports of superstructure
• Disperses loads from bearings to the pier or abutment more evenly
20
10
2022/3/9
Culvert
A culvert is a pipe or other type structure that allows water to pass under a road
or railroad.
Usually the clear span of a culvert is less than 8m
21
Box Culvert
A rigid frame used for square or rectangular openings with spans up to 4m is
called box culvert
22
11
2022/3/9
Vertical Clearance
The clearance between the high flood level and the lowest point of the structure
is known as vertical clearance.
23
Scour depth
The depth up to which a flowing stream erodes soil is known as scour depth
Scour usually occurs when the velocity of the flowing water increases or crosses
the limiting value that the soil particles can easily handle.
24
12
2022/3/9
Afflux
The rise in water level of the river near the bridge over the flood level due to
constriction of water created by the construction of piers, abutments and
wing walls is called afflux
25
Expansion Joint
A gap between the structure is provided to take care of the expansion of the
member due to change in the surrounding temperature
They are provided in the full depth of the member
26
13
2022/3/9
Construction Joint
Joint provided whenever placement of concrete has to be stopped temporarily
before the construction of the entire monolithic portion under construction is
called construction joint
In concrete construction, it is a joint between two parts of a concrete structure that
are placed separately
for instance, in a retaining wall, the footing may be poured first, and then after it is
set, say 24 hours later, the wall is poured. The joint between is called a
construction joint or “cold joint”.
27
Construction Joint
Cold joints, or construction joints are usually placed where there is a natural time
difference between placements.
Perhaps, you can only do so much in one day and need to come back the next day
to place the remaining concrete.
The interface between the old and the new concrete is a construction joint.
For example, when placing concrete columns, you generally will have a footing.
The construction joint will be between the footing and the column. This is because
they usually tie the bar for the footings, and a portion of the column, before placing
the concrete for the footing, or foundation.
28
14
2022/3/9
29
15