Objective:
To qualify the Dawn Friability testing apparatus, for use in friability testing of tablet
Scope:
The scope of this report is limited to Dawn Friability tester
Responsibilities:
Vendor
Purchaser/ Buyer
Model FT-09
Date Received
Instrument Specification
User Required Specification of Friability apparatus
S. Decision
User Requirements Desired features Functions
No Pass Fail
Standard requirement for
1 Rotation per minutes 25(±02)RPM
rpm setting in a equipment ✓
As per USP, BP and EP
monographs the 100 ✓
2 Timer 01 to 200 revolutions required at 25
RPM min, total time required
for testing is 4min
To check the equipment
3 Time setting difference 1 minute
performance is robust, ✓
accurate and precise during
testing
Comments: the equipment received as per URS and USP Specified standards
Decision
S. No User Requirements Desired features Functions
Pass Fail
Ambient temperature of Equipment defriend range for best
1 (5 to 40) ºC ✓
Lab performance
80% upto 31◦C,
2 Max relative humidity decreasing linearly to The humidity threshold of lab set ✓
50% at 40◦C
Supply voltage and Standard voltage supplies available in
3
frequency
220V @ 50/60 Hz
laboratory ✓
This is general requirement to avoid
No direct sun light
4 Sun light
exposure
equipment corrosion and abrasion of ✓
equipment surfaces
Should be inert to The equipment should be designed to avoid
5 Reactive gases
reactive gases any corrosive reaction with reactive gases ✓
Packing List
S. No Description Quantity
1 Drum 1
2 Power Cord 1
3 Instruction Manual 1
Unpack the equipment carefully, Are any items missing against packing list?
Yes No ✓
Yes No ✓
Instrument Safety
✓
Position on level, noncombustible surface indoor
✓
Area free from aggressive/ explosive chemical mixture
✓
Ensure correct power supply and all power switches easily accessible
✓
Read operator manual before use
✓
Unpack and retain packaging
✓
Assembly
✓
Site and content to power supply
✓
As mentioned on instruction manual
Summary Report:
Remarks: successful completion of the proceeding activities and checks indicate that this
instrument has been successfully delivered and installed. The instrument has passed installation
qualification procedure and may now be submitted for operation qualification