Professional Documents
Culture Documents
Prepared as per the GTU Syllabus. Elective Subject, offered in 7th Semester of B.E. Civil
Syllabus: https://s3-ap-southeast-1.amazonaws.com/gtusitecirculars/Syallbus/3170622.pdf
2.1 LOADS
• Normally building design loads can be taken from the concerned building code of the
country. (e.g. for India it is IS 875_Part 1-5).
• The vertical load comprises of Dead weight (self weight) of the structure, superimposed
load and live loads.
• In precast construction structural members are considered as simply supported. So,
it is easy to organise and accumulate the loads acting from TOP to BOTTOM.
• The calculation of load can be easily done by preparing a load table for particular
reference: https://sites.google.com/site/ae390papadakis/load-path-diagrams
Load Transfer in a skeletal unbraced frame (a) Gravity Loads (b) Lateral Loads
• Limit states are the acceptable limits for the safety and serviceability requirements of
the structure before failure occurs. The design of structures by this method will thus
ensure that they will not reach limit states and will not become unfit for the use for
which they are intended. It is worth mentioning that structures will not just fail or
collapse by violating (exceeding) the limit states. Failure, therefore, implies that clearly
defined limit states of structural usefulness has been exceeded.
LIMIT STATE
• All relevant limit states have to be considered in the design to ensure adequate degree
of safety and serviceability. The structure shall be designed on the basis of the most
critical limit state and shall be checked for other limit states.
(1) Skeletal frame systems: Precast concrete components such as beams, columns, stairs
and hollow core slabs to form the frame of buildings.
✦ They are suitable for low-rise buildings such as commercial buildings, schools,
hospitals, parking structures and sporting facilities, where a high degree of
flexibility in planning of floor areas can be achieved by using large spanning
column-beam layout.
• A pre-cast concrete structure is not a cast in situ Structure cut up into little pieces
making it possible to transport and erect. As it is seen in the Load Path explanation it is
clear that the prefabricated and assembled components in precast structure is quite
different to a monolithic continuous structure.
• Therefore it is good to analyse the global structure and find out the location of the
connections which could be introduced for particular precast structure.
• In following figure 2.5_1, it is shown that the approximate bending moments and
deflected shape in a three storey continuous beam and column frame subjected to
vertical and horizontal loads.
• Looking to the bending moment diagram, there are points of zero moment (contra-
flexure). For gravity load, the beam generates contra-flexure near to the Beam column
joint (approximately 0.1L). For horizontal load the beam generates contra-flexure points
at the mid span (approximately 0.5L).
• In columns the contra-flexure for both the load cases lies at the mid-height of the
column (approximately 0.5H). Hence this could be a good location to introduce a pin
connection (or hinge) between the columns.
• Now, if the strength at the ends of the beam is reduced to zero (i.e. hinge and not fixed)
whilst the columns and foundations untouched, the resulting deformations and
bending moments is as shown in figure 2.5_2.
• The beams will not transfer moments, but only shear forces and axial forces. The
foundation will have to be still rigid (fixed). This mechanism is known as pin jointed
skeletal frame.
• In taller structures (more than 10m height), columns will have greater loads and
moments resulting into large c/s dimensions leading to impractical and uneconomical
columns.
• Bracing can be a good solution to this. Full height bracing is called ‘Fully Braced’ frame
and bracing ending/starting at certain level is called ‘partially braced’ frames.
• U-frame: Another option could be a portal frame (inverted-U frame) where beam-
column connections are kept rigid (similar to the frame shown in fig 2.5_1) but, the
lower ends of the columns can be kept with zero flexural rigidity (i.e. hinge). Moment
diagrams and deflections for this frame analysis is shown in fig 2.5_4. But, this is not a
good practical solution for factory casted large span frames, so better for in-situ
constructions.
• L-frame: A better alternative to this is L-frame. Especially, for long span beams and low
storey heights, like parking structures. In this, one end of the beam is rigid whereas the
other one hinge. All the lower ends of the columns can be kept as hinge, accept for the
foundation columns. Refer fig 2.5_5.
• H-frame: If pinned connections can be incorporated at the point of contra-flexures of the
columns (around mid-height), the structural behaviour of the frame is somewhat
similar to a rigid frame. The beam end can either be both rigid or one pin and one rigid.
• Connections between frames are made at mid-storey height positions.
• The foundation to half-storey height ground floor columns must be rigid. The
connection at the upper end of the column may be pinned if it is located at a point
of contra-flexure. If not the connection must possess flexural strength as shown in
fig 2.5_6, where the H-frame has been used in a number of multi-storey
grandstands.
Figure 2.5_6: H-frames (a) structural system (b) deformations & moment diagrams
Figure
The height 3.1.1_1:
of voids should not(a) A typical
exceed most
h − 50 mm, common
where Hollow
h is the overall core
depth floor
of the unit.unit (b) stacking of 1200 mm wide floor units
The diameter of circular voids is usually h − 75 mm. The minimum flange thickness depends
waiting for delivery within 7 days after casting
on the overall depth of the unit h, given by 1.6 h. However, because of cover requirements
it is usually necessary for the bottom flange to be at least 30 mm thick. The minimum width
of a web should not be less than 30 mm.
Hollow core units were developed in the 1950s when the dual techniques of long-line
prestressing and concrete production through machines were being developed by companies
such as Spiroll in the United States and Roth in Europe. Precast concrete engineers contin-
PRECAST CONSTRUCTION 3170622 16
ued to optimise the cross section of the units leading to the so-called double-tee unit, shown
in Figure 4.8, achieving even greater spans and reduced mass compared with hollow core
units. Although the finer points of detail of double-tees vary in many different countries, the
Figure 4.5 Stacking 1200 mm wide hollow core floor units awaiting delivery within seven days after casting.
Figure 4.6 Two 600 mm wide hollow core floor units made from 1200 mm wide casting bed, 400 mm wide
Figure 3.1.1_2: Two 600 units
mmarewide hollow core floor units made from 1200 mm wide casting bed, 400 mm
also possible.
wide units are also possible Precast concrete floors 129
unit comprises two deep webs, reinforced for strength, joined together by a relatively thin
1. Not being able to provide sufficient pretensioning force to satisfy the available section
as strands can only be placed in pairs at the bottom of the webs, forcing more strands
to be positioned higher in the web-reducing eccentricity.
Figure 3.1.1_3:
FigureThe 2.42.4mmwide
4.7 The hollow
wide hollow corecore floormanufactured
floor units units manufactured
by Preconco Ltd.,by Preconco Ltd., Barbados.
Barbados.
includes infilled joints between units. Exposure = XC1, fck = 45 N/mm2, fctm = 3.80 N/mm2.
• Typical widths are 2.4 m – 3.0 m, and depths range from 400 mm to 1200 mm. The void
ratio is about 70%, allowing the unit to span over longer spans and with less weight per
area than the hollow core unit.
• Table Figure
3.1.1_24.10 lists some
Multi-rib unitstypes of prestressed
with tapered double-tee
half joint and special end detailunits having
suitable 2 no. design,
for continuous websat160 mm
Samsung, South Korea.
Structural properties
wide Table
at the4.2bottom, togetherofwith
double-tee
theirfloor units (without
moments structural toppings)
of resistance and shear capacity.
Overall Flange Web breadtha Self-weight MsR (kNm/m MRd (kNm/m VRd,c (kN/m
Depth (mm) depth (mm) (mm) (kN/m2) width) width) width)
Table 3.1.1_2: Structural properties of prestressed double-tee floor units
300
Table 4.2 Structural75 180
properties of double-tee floor 2.60 69.8
units (without structural 116.4
toppings) 68.0
400 75 180 2.96 124.1 201.2 89.6
Overall Flange Web breadth a Self-weight MsR (kNm/m MRd (kNm/m VRd,c (kN/m
500
Depth (mm) 75(mm)
depth 180
(mm) 3.32 2)
(kN/m 190.4
width) 303.0
width) 106.5
width)
600 75 180 3.68 271.2 427.6 120.5
300
700 75
75 180
180 2.60
4.04 69.8
362.3 116.4
566.4 68.0
133.2
400
800 75
75 180
180 2.96
4.40 124.1
471.0 201.2
733.8 89.6
144.9
500 75 180 3.32 190.4 303.0 106.5
a Web breath refers to the breadth of each web near the centroidal axis.
600 75 180 3.68 271.2 427.6 120.5
Axis distance to pretensioning strands = 50, 100, 150 and 200 mm (12.5 mm dia.). Final prestress at bottom σpo (excluding
700
self-weight) = 18.0 – 75 180 on the availability
19.0 N/mm2 depending 4.04 of positions362.3
of tendons. Some566.4
tendons debonded 133.2
at the
support.
800 Exposure = XC1,
75 data based on180fck = 45 N/mm2, f4.40
ck(t) = 30 N/mm 471.0
2, 25% final losses of pretensiong force.
733.8 144.9
a Web breath refers to the breadth of each web
a Web breath nearto
refers thethe
centroidal
breadthaxis.of each web near the centroidal axis.
Axis distance to pretensioning strands = 50, 100, 150 and 200 mm (12.5 mm dia.). Final prestress at bottom σpo (excluding
Comparison
self-weight) = with
18.0 –Table 4.1 2isdepending
19.0 N/mm interesting,
on thefor example
availability serviceofmoment
of positions of resistance
tendons. Some M sR foratthe
tendons debonded the
400 mm Exposure
support. deep hollow
= XC1,core and double-tee
data based units
on fck = 45 N/mm fck2, 25%
ckas follows (see
2, f (t) = 30 N/mm = Section
45 N/mm
final
2 , fck(t) = 30 N/mm2
4.3.3
losses for terminology):
of pretensiong force.
Area M
• Comparison onwith
Comparison Tab. 3.3.1_2
Table
Self-weight withPrestress
4.1tendons Tab.
is interesting, for at 3.1.1_1
example is interesting,
bottom service for example,
moment of resistance for the service
sR
MsR(kNm/m
400 of
mmresistance
deep hollow
(kN/m )core Aand σb units
double-tee (N/mmas follows (see mm
Section
p (mm )
mm )deep Ic (×10
coreZ4.3.3
) b (×10for
and mm terminology):
) width)
2 2 2 6 4 6 3
moment MsR for the 400 hollow double-tee units as
Hollow core 5.03 1266 12.86 4646 24.44 339.9
follows:
Double-tee 3.32 Area
1116 18.70 3776 13.24 MsR
124.1
Self-weight tendons Prestress at bottom (kNm/m
(kN/m2) Ap (mm2) σb (N/mm2 )
2 I (×106mm4) Z (×106 mm3) width)
M sR = (σb + fctm) Zb /b, where fctm = 3.8 N/mm , b = 1.2 cm and 2.4 m for
b
hollow core units
and double-tee units.
Hollow core 5.03 1266 12.86 4646 24.44 339.9
Double-tee
PRECAST CONSTRUCTION 3.32 1116 18.70
3170622 3776 13.24 124.1 19
M sR = (σb + fctm) Zb /b, where fctm = 3.8 N/mm 2 , b = 1.2 m and 2.4 m for hollow core units
and double-tee units.
support. Exposure = XC1, data based on fck = 45 N/mm2, fck(t) = 30 N/mm2, 25% final losses of pretensiong force.
Nominal mesh
reinforcement In situ concrete
topping
Main beam
Bearing pad
Precast planks
Figure 3.1.1_6: Composite beam and plank flooring comprising precast primary and secondary beams,
Figure 4.11 Composite beam and plank flooring
precast plankscomprising precast
and structural primary and secondary beams, precast
topping.
planks and structural topping.
75–100 mm
• The precast concrete planks that may be shaped to suit non-rectangular, even curved,
Up to 2400 mm
building layouts.
• It is usual for a structural topping to be applied to the floor, and this is reinforced using
a mesh. The final constructed floor resembles a double-tee floor in structuralAlternative
form edge
and
details
Prestressed (psc)
has a similar void ratio of about 70%, but the way in which
Precast concrete floors 133
each of these has been
precast plank
75–100 mm
Up to 2400 mm
(b)
134 Precast Concrete Structuresrc or psc precast unit. Figure 4.12 (a) Composite plank floor options. (b) Reinforced lattice girder and rebar cage for composite
Min. width 300 mm (c) plank floor. (Continued )
(a)
(c) (d)
(b)
Figure 4.12 (Continued) (c) Precast concrete stage of composite plank lattice floor. (d) Construction
Figure 3.1.1_7 (a): Cross section of composite planks, (b)stage plank with lattice
of composite plank reinforcement, (c)of plank
lattice floor. (Courtesy ready
Pfeifer Seil und Hebetechnik
Figure 4.12 (a) Composite plank floor options. (b) Reinforced lattice girder and rebar cage for composite
for installation, & (d) construction stage of composite Memmingen, Germany.)
plank floor system
plank floor. (Continued )
similar variation ideal for making both floors and beams continuous in Germany. The tops of
• The cross section of composite planks
the beamsis asbeshown
may in interface
provided with Fig. 3.1.1_7 (a).
shear loops To speed
to make erection
a composite beam. Lightweight
infill blocks (e.g. dense polystyrene) are sometimes placed on to the tops of the planks to
rates, the planks may be up to 3 m wide
reduce (but
weight 1.2 and
by about 2.4the
25%, but mweight
are common).
saving blocks may cost more than the displaced
concrete. It isrelatively easy to form large-size voids in this floor and to add site reinforcement
• Fig. 3.1.1_7 (b & c) show the twotostages of precast
cater for stress production
raisers at corners etc. from a UK manufacturer
and Fig. 3.1.1_7 (d) a similar variation ideal for making both floors and beams
continuous in Germany. In this type the beam and the planks are filled with the in-situ
(d)
concrete together for better integrity and bonding.
Figure 4.12 (Continued) (c) Precast concrete stage of composite plank lattice floor. (d) Construction
stage of composite plank lattice floor. (Courtesy of Pfeifer Seil und Hebetechnik
Memmingen, Germany.)
Statically
• Solid slabs, oftenreinforced
called concrete may be limited
‘solid planks,’ in termsdesigned
are usually of span and depth, mainlywith
compositely due to
an in situ
deflection or crack width criteria which can be overcome by prestressing. The other type of
topping as discussed
half-slab earlier.
is shown in Figure These
4.13, units solid
a prestressed are plank,
majorly used with
reinforced when a 12
up to domestic
no. 5 or sound
7 mm wires, or between 4 and 9 no. 7-wire helical strands, depending on depth and loading
insulation requirement is to be met. The depths vary between 75 mm to 200 mm, a usual
requirements. Solid slabs, ‘often called solid planks,’ are usually designed compositely with
depthanis 100topping
in situ mm.asA limiting
discussed span4.4.1.
in Section of The
4.5m is preferred
precast soffit section by most 100
is typically manufactures
mm
deep, but depths of between 75 and 200 mm are possible. Solid planks are often used in
considering
domesticlifting andwhere
properties handling of the planks.
the requirement for 300 kg/m 2 sound insulation can easily be met
using a 75 mm precast soffit (12 no. 7 mm wires at 20 mm cover) and 50 mm topping, and
for an imposed live load of 1.5 kN/m 2 plus 1.2 + 0.6 kN/m2 for finishes, services and ceiling,
spans of 5.0 m are possible without temporary propping, or 5.5 m with propping. Propping
Each
helps toofoptimise
the flooring systems
the design introduced
where the limiting spanearlier has successively
is controlled almost equallyeroded
by servicethe
major advantages in the and
stress, final deflection usedeflection
of precastafterconcrete floors
finishes (see over
Section competitors
4.6.2). suchspan
In fact, a limiting as timber
of 4.5 m (length/depth
or cast in situ floors. = 4500/75 = 60) due to lifting and handling may be imposed by some
manufacturers.
Each of the flooring systems introduced earlier has successively eroded the major advan-
Since
tages inthethe1960s, the hollow
use of precast core
concrete market
floors in Europe
over competitors recently
such as timber passed
or cast1000M
in situ m
2
(about 300
floors.soccer pitches
Since the perhollow
1960s, the month!) The advantages
core market withpassed
in Europe recently precast1000Mare:m2 – about
300 soccer pitches per month! The advantages with precast are
i. Manufacture of units simply and economically
1. Manufacture of units simply and economically
ii.2. Safe
Safe and
andrapid erection
rapid of floors
erection of floors
3. Possiblity to create a structurally complete precast floor
iii.4. Possibility to create
Use of minimum amountsa of
structurally complete
in situ reinforcement and precast floor
wet concrete
iv. Usethese
However, of minimum amountswith
may be in competition of in situcriteria
other reinforcement and access,
depending on-site wet concrete.
structural
design requirements, interface with other trades, availability of expensive or cheap labour,
services requirements, etc. Specifiers must therefore study all available options.