You are on page 1of 3

4/1/2023

BACHELOR OF THE SCIENCE OF ENGINEERING IN CIVIL


ENGINEERING DEFINITION
• A process of obtaining/ acquiring goods, services
LECTURE NO. 02 or work
PROCUREMENT IN CONSTRUCTION • A framework within which construction is brought
about, acquired or obtained
• A strategy to satisfy clients’ development and/or
operational needs with respect to the provision of
constructed facilities for a discrete life-cycle

By
Ch. QS. Gayan Fernando
Chartered Quantity Surveyor/ Lecturer
B.Sc. (Hons) in QS, LLB (Hons)
M.Sc. in CL&DS, Dip. in Arb., AIQSSL.
2

SCOPE OF PROCUREMENT ACTIVITIES PROJECT DELIVERABLES


Land acquisition / Functional facility
selection
Leasing or … time, cost, quality
managing facilities
Demolition

Procurement should achieve or enhance:


Activities • overall efficiency and economy in the delivery
Design Commissioning
of projects.
Managing the
Financing
project
• best value and quality in the delivery of
facilities and programmes.
Construction …etc. • identification and selection of most appropriate
3
contractor. 4

1
4/1/2023

STRATEGIC FRAMEWORK PROCUREMENT SYSTEM


• Traditional Procurement System (Separated
Procurement System)
• Alternative Procurement System (Modern
Procurement System)
o Intergrade Procurement System
o Management Oriented Procurement System
o Collaborative Procurement System

5 6

TRADITIONAL PROCUREMENT TRADITIONAL PROCUREMENT


SYSTEM SYSTEM
• Called as Traditional/ Conventional Procurement
System Arch

Design Team
• Rigid separation of design from construction QS Employer

• Consultants is usually appointed by the client to Eng


prepare a complete design
Building Contractor
• Once design is completed, client involves in
bidding process to select a contractor

NSC DSC
DSC
Money
Contractual
7 8
Functional

2
4/1/2023

TRADITIONAL PROCUREMENT TRADITIONAL PROCUREMENT


SYSTEM SYSTEM
Advantages Disadvantages
• Satisfactory basis for: interim valuations for • This procedure tends to be slow
payment, valuation of variations.
• Contractor’s expertise not exploited in the design
• High degree of certainty before commitment to
build • Contractor has no legal standing to suggest the
cost-saving alternative
• Clear accountability and tight control
• Opportunity to combine best design and • Associated with inter-party conflicts
contracting skills • Engenders incomplete designs & future problems
• Allows for nomination of specialists
• Allows certain amount of flexibility

9 10