RIBA Phase RIBA Phase Service AIA O-A Stages AIA Phase Service - Owner Archtect Agreement AIA

AIA O-A Stages AIA Phase Service - Owner Archtect Agreement AIA O-DB Stages AIA Phase Service - Owner Design-Builder Agreement CoA (India) Services as per Conditions of Engagement
Stage 0: No Role of Designer
Strategic Definition NA NA NA NA NA NA

Stage 1: 1. Consider the likely composition of the design team and discuss Stage 1: 1. Schedule and conduct meetings with the Owner and any other
Preparation and Brief this with the client. Pre-Agreement necessary individuals or entities to discuss and review the Owner’s
Criteria

2. Assemble the project team and define the members’ roles and 2. Again meet with the Owner to discuss a preliminary evaluation of
responsibilities. the Owner’s Criteria.
3. Agree the Schedule of Services, Responsibility Matrix and 3. The preliminary evaluation shall address possible alternative
Information Exchanges. approaches to design and construction of the Project and include the
Design-Builder’s recommendations, if any, with regard to accelerated
or fast-track scheduling, procurement, or phased construction.

4. Establish or review project quality management procedures, 4. The preliminary evaluation shall consider cost information,
together with relevant quality procedures for all design team constructability, and procurement and construction scheduling issues.
members.

5. Identify the need for a Project Execution Plan and agree its 5. Shall provide a written report to the Owner, summarizing the
format with the client and design team. Design-Builder’s evaluation of the Owner’s Criteria, containing:
a. allocations of program functions, detailing each function and their
square foot areas;
b. a preliminary estimate of the Cost of the Work, and, if necessary,
NA NA recommendations to adjust the Owner’s Criteria to conform to the NA NA
Owner’s budget;
c. a preliminary schedule, which shall include proposed design
milestones; dates for receiving additional information from, or for
work to be completed by, the Owner; anticipated date for the Design-
Builder’s Proposal;and dates of periodic design review sessions with
the Owner; and
d. Any other as required

6. Check the scope of professional services agreed with other


consultants as they are appointed.
7. Establish arrangements for communication between the client’s
representative, the Principal Designer, the Project Lead and the
lead designer.

8. Establish a programme for design team meetings.


9. Establish procedures for regular reporting to the client.

Stage 1: 1. Ascertain the Client's requirements, examine site constraints &


Concept Design potential and prepare a design brief for the Client's approval

2. Prepare report on slte evaluation, state of existing buildings, If any ;


and analysis and Impact of existing and/ or proposed development on
its immediate environs.

3. Prepare drawings and documents to enable the Client to get done


NA NA NA NA NA NA the detailed survey and soil investigation at the site of the project.

4. Furnish report on measures required to be taken to mitigate the


adverse impact, if any, of the existing and / or proposed development
on its immediate environs.

5. Prepare conceptual designs with reference to requ, rements given


and prepare rough estimate of cost on area basis.

Stage 2: 1. Responsibility Matrix should be prepared. Stage 1: 1. Review the program and other information furnished by the Owner Stage 2: 1. Upon the Owner’s issuance of a written consent to proceed under Stage 2: 1. Modify the conceptual designs incorporating required changes and
Concept Design Schematic Design Preliminary Design Section 4.2.3, the Design-Builder shall prepare and submit a Preliminary Design prepare the preliminary drawings, sketches, study model, etc., for
Preliminary Design to the Owner approval along with a preliminary estimate of cost on an area basis.

2. Agree input to the stage by design team members. 2. Review laws, codes, and regulations applicable to the Architect’s 2. The Preliminary Design shall include a report identifying any
services. deviations from the Owner’s Criteria
3. Review the Design Programme and update it as necessary. 2. Prepare a preliminary evaluation of the Owner’s program, schedule, 3. It shall include the following:
budget for the Cost of the Work, Project site, the proposed a. Confirmation of the allocations of program functions;
procurement and delivery method, and other Initial Information, each b. Site plan;
in terms of the other, to ascertain the requirements of the Project. c. Building plans, sections and elevations;
d. Structural system;
e. Selections of major building systems, including but not limited to
mechanical, electrical and plumbing systems;
f. Outline specifications or sufficient drawing notes describing
construction materials.

4. Establish or review project quality management procedures 4. Notify the Owner of (1) any inconsistencies discovered in the 4. The Preliminary Design may include some combination of physical
together with relevant procedures of all design team members. information, and (2) other information or consulting services that may study models, perspective sketches, or digital modeling.
be reasonably needed for the Project.

5. Check the scope of professional services agreed with other 5. Present its preliminary evaluation to the Owner and shall discuss 5. The Owner shall review the Preliminary Design and, if acceptable,
consultants as they are appointed. with the Owner alternative approaches to design and construction of provide the Design-Builder with written consent to proceed to
the Project. development of the Design-Builder’s Proposal. The Preliminary Design
shall not modify the Owner’s Criteria unless the Owner and Design-
Builder execute a Modification.
6. Confirm the Stage 2 timetable for services and note its 6. Reach an understanding with the Owner regarding the
relationship to the project timetable as agreed with the client. The requirements of the Project.
timetable should show critical points by which information from
the client and design team members will be required.

7. Confirm the programme and pattern for design team meetings. 7. Shall prepare and present, for the Owner’s approval, a preliminary
design illustrating the scale and relationship of the Project
components based on the Project requirements agreed upon with the
Owner.

8. Prepare the Architectural Concept, including outline proposals 8. Based on the Owner’s approval of the preliminary design, the
for structural design, services systems, landscape, Outline Architect shall prepare Schematic Design Documents for the Owner’s
Specification and preliminary Cost Plan along with relevant Project approval. The Schematic Design Documents shall consist of drawings
Strategies. and other documents including a site plan, if appropriate, and
preliminary building plans, sections and elevations; and may include
some combination of study models, perspective sketches, or digital
representations. Preliminary selections of major building systems and
construction materials shall be noted on the drawings or described in
writing.

9. Undertake Design Reviews as appropriate. 9. Consider sustainable design alternatives, such as material choices
and building orientation, together with other considerations based on
program and aesthetics, in developing a design that is consistent with
the Owner’s program, schedule and budget for the Cost of the Work.

10. Prepare Outline Specification. 10. Submit to the Owner an estimate of the Cost of the Work
11. Coordinate with BIM and digital technology team 11. Submit the Schematic Design Documents to the Owner, and
request the Owner’s approval.

Stage 3: 1. Prepare drawings necessary for Client's/ statutory approvals and


Drawings for ensure compliance with codes, standards and legislation, as applicable
NA NA NA NA NA NA Client's/Statutory Approvals and assist the Client in obtaining the statutory approvals thereof, if
required.

Stage 3: 1. Establish or review project quality management procedures Stage 2: 1. Prepare Design Development Documents for the Owner’s approval Stage 3: 1. The Design-Builder shall prepare and submit the Design-Builder’s Stage 4: 1. Prepare working drawings, specifications and schedule of quantities
Spatial Coordination together with relevant procedures of all design team members. Design Development based on the Owner’s approval of the Schematic Design Documents, Design Builder's Proposal Proposal to the Owner. The Design-Builder’s Proposal should include Working Drawings and sufficient to prepare an estimate of cost and tender documents
and on the Owner’s authorization of any adjustments in the Project the following: Tender Documents including code of practice covering aspects like mode of measurement,
requirements and the budget for the Cost of the Work. method of payments, quality control procedures on materials and
works and other conditions of contract.

2. Check the scope of professional services agreed with other 2. The Design Development Documents shall illustrate and describe • A list of the Preliminary Design documents and other information,
consultants as they are appointed. the development of the approved Schematic Design Documents and including the Design-Builder’s clarification, assumptions and deviations
shall consist of drawings and other documents including plans, from the Owner’s Criteria, upon which the Design-Builder’s Proposal is
sections, elevations, typical construction details, and diagrammatic based;
layouts of building systems to fix and describe the size and character
of the Project as to architectural, structural, mechanical and electrical
systems, and other appropriate elements.

3. Agree input to the stage by design team mem-bers. 3. The Design Development Documents shall also include outline • The proposed Contract Sum, including the compensation method
specifications that identify major materials and systems and establish, and, if based upon the Cost of the Work plus a fee, a written
in general, their quality levels. statement of estimated cost organized by trade categories,
allowances, contingencies, Design-Builder’s Fee, and other items that
comprise the Contract Sum;

4. Confirm the programme and pattern for design team meetings. 4. Update the estimate of the Cost of the Work prepared • The proposed date the Design-Builder shall achieve Substantial Comple

5. During this stage the structural engineer should collaborate in 5. Submit the Design Development Documents to the Owner, advise • An enumeration of any qualifications and exclusions, if applicable;
developing the design, and advise on structural options and the Owner of any adjustments to the estimate of the Cost of the Work,
preferred solutions. The architect is responsible for coordination and request the Owner’s approval
and integration of these into the overall design concept. This will
include checking that structural proposals are compatible with the
space and access requirements of the services installations.

6. Prepare the Spatially Coordinated design, including coordinated • A list of the Design-Builder’s key personnel, Contractors and
and updated proposals for structural design, services systems and suppliers; and .6 The date on which the Design-Builder’s Proposal
landscaping, Outline Specification, Cost Plan and Project Strategies. expires.

7. Undertake Design Studies at regular intervals as required. 2. The submission shall constitute a representation by the Design-
Builder that it has visited the site and become familiar with local
conditions under which the Work is to be completed.

8. Finalise the Spatially Coordinated design. The presentation to 3. Shall execute the DesignBuild Amendment setting forth the terms of
the client of Stage 3 proposals is particularly important. their agreement.

Stage 5: 1. Invite, receive and analyse tenders: advise Client on appointment of


NA NA NA NA NA NA Appointment of Contractor contractors.
Stage 4: 1. Establish or review project quality management procedures Stage 3: 1. Prepare Construction Documents for the Owner’s approval based on Stage 4: 1. Shall prepare Construction Documents. The Construction
Technical Design together with relevant procedures of all design team members. Constructions Document the Owner’s approval of the Design Development Documents, and on Construction Documents Documents shall establish the quality levels of materials and systems
Phase the Owner’s authorization of any adjustments in the Project required. The Construction Documents shall be consistent with the
requirements and the budget for the Cost of the Work. Design-Build Documents.

2. Check the scope of professional services agreed with other 2. The Construction Documents shall illustrate and describe the further 2. Shall prepare Construction Documents. The Construction
consultants as they are appointed. development of the approved Design Development Documents and Documents shall establish the quality levels of materials and systems
shall consist of Drawings and Specifications setting forth in detail the required. The Construction Documents shall be consistent with the
quality levels and performance criteria of materials and systems and Design-Build Documents.
other requirements for the construction of the Work.

3. Agree input to the stage by design team members. 3. The Owner and Architect acknowledge that, in order to perform the
Work, the Contractor will provide additional information, including
Shop Drawings, Product Data, Samples and other similar submittals,
which the Architect shall review

4. Establish the information exchange programme. 4. Incorporate the design requirements of governmental authorities
having jurisdiction over the Project into the Construction Documents

5. Prepare a drawing programme/schedule. 5. Architect shall assist the Owner in the development and preparation
of
(1) procurement information that describes the time, place, and
conditions of bidding, including bidding or proposal forms;
(2) the form of agreement between the Owner and Contractor; and
(3) the Conditions of the Contract for Construction (General,
Supplementary and other Conditions).

NA NA

6. Have an agreed policy for coordinating information on drawings 7. Update the estimate for the Cost of the Work prepared
and between documents.
Coordinated project information should be introduced at the
earliest possible stage in information preparation.

7. Confirm the programme and pattern for design team meetings. 8. Submit the Construction Documents to the Owner, advise the
Owner of any adjustments to the estimate of the Cost of the Work,
take any action required under Section 6.5, and request the Owner’s
approval.

8. Monitor, coordinate and integrate input from design team 1. The Architect shall assist the Owner in establishing a list of
members and specialists. Appraise input from specialist firms, prospective contractors. Following the Owner’s approval of the
including potential subcontractors and suppliers Construction Documents, the Architect shall assist the Owner in (1)
obtaining either competitive bids or negotiated proposals;
(2) confirming responsiveness of bids or proposals;
(3) determining the successful bid or proposal, if any; and,
(4) awarding and preparing contracts for construction.

9. Check that any instructed design changes are recorded and


subject to the Change Control Procedures.
10. Coordinate and integrate information from de-sign team
members.
11. Confirm with design team members the ar-rangements for
inviting specialist tenders.

Stage 5: 1. Check the scope of professional services agreed with the client Stage 4: 1. The Architect shall advise and consult with the Owner during the 1. The Design-Builder shall maintain at the site for the Owner one copy Stage 6: Construction 1. Prepare and issue working drawings and details for proper
Manufacturing and for continued presence of the design team members as members Construction Phase Construction Phase Services. of the Design-Build Documents and a current set of the Construction Drawings execution of works during construction.
Construction of the project team. Documents, in good order and marked currently to indicate field
changes and selections made during construction, and one copy of
approved Submittals.

2. Confirm that consultants are to supply relevant information for 2. Architect shall be responsible for the Architect’s negligent acts or 2. Changes in the Work may be accomplished after execution of the 2. Approve samples of various elements and components.
the preparation of operating instructions, maintenance manuals, omissions, but shall not have control over or charge of, and shall not Contract, and without invalidating the Contract, by Change Order or
record drawings of installation, etc. be responsible for, acts or omissions of the Contractor or of any other Change Directive, subject to the limitations stated in this Article 6 and
persons or entities performing portions of the Work. elsewhere in the Design-Build Documents.

3. Confirm that consultants are to pass relevant information to the 3. Visit the site at intervals appropriate to the stage of construction, or 3. Check and approve shop drawings submitted by the contractor/
Principal Designer for inclusion in the Health and Safety File. as otherwise required in Section 4.2.3, to become generally familiar vendors.
with the progress and quality of the portion of the Work completed,
and to determine, in general, if the Work observed is being performed
in a manner indicating that the Work, when fully completed, will be in
accordance with the Contract Documents

4. Has the authority to reject Work that does not conform to the 4. Visit the site of work, at intervals mutually agreed upon, to inspect
Contract Documents and evaluate the Construction Works end where necessary clarify and
decisions, offer interpretation of the drawings/specifications, and
attend conferences and meetings to ensure that the project proceeds
generally in accordance with the conditions or contract and keep the
Client informed and render advice on actions, if required.
5. Interpret and decide matters concerning performance under, and 5. In order to ensure that the work at the site proceeds in accordance
requirements of, the Contract Documents on written request of either with the contract documents/drawings and to exercise time and
the Owner or Contractor. quality controls, the day-to-day supervision will be carried out by a
Construction Manager (Clerk of Works/ Site Supervisor or Construction
Management Agency in case of a large and complex project), who shall
work under the guidance and direction of the Architect and shall be
appointed and paid by the Client.

6. Decisions on matters relating to aesthetic effect shall be final if 6. Issue Certificate of Virtual Completion of works.
consistent with the intent expressed in the Contract Documents.

7. Shall render initial decisions on Claims between the Owner and


Contractor as provided in the Contract Documents
8. Shall review and certify the amounts due the Contractor and shall
issue certificates in
9. Shall maintain a record of the Applications and Certificates for
Payment.
10. Review the Contractor’s submittal schedule and shall not
unreasonably delay or withhold approval of the schedule.
11. l review and approve, or take other appropriate action upon, the
Contractor’s submittals such as Shop Drawings, Product Data and
Samples, but only for the limited purpose of checking for conformance
with information given and the design concept expressed in the
Contract Documents.

12. Shall review and respond to requests for information about the
Contract Documents
13. Shall maintain a record of submittals and copies of submittals
supplied by the Contractor in accordance with the requirements of the
Contract Documents.

14. Shall maintain a record of submittals and copies of submittals


supplied by the Contractor in accordance with the requirements of the
Contract Documents.

15. Shall prepare Change Orders and Construction Change Directives


for the Owner’s approval and execution in accordance with the
Contract Documents.

16. Shall maintain records relative to changes in the Work.


17. The Architect shall:
i. conduct inspections to determine the date or dates of Substantial
Completion and the date of final completion;
ii. issue Certificates of Substantial Completion;
iii. forward to the Owner, for the Owner’s review and records,
written warranties and related documents required by the Contract
Documents and received from the Contractor; and,
iv. issue a final Certificate for Payment based upon a final inspection
indicating that, to the best of the Architect’s knowledge, information,
and belief, the Work complies with the requirements of the Contract
Documents.

18. Inspections shall be conducted with the Owner to check


conformance of the Work with the requirements of the Contract
Documents and to verify the accuracy and completeness of the list
submitted by the Contractor of Work to be completed or corrected.

19. When Substantial Completion has been achieved, the Architect


shall inform the Owner about the balance of the Contract Sum
remaining to be paid the Contractor

20. Shall forward to the Owner the following information received


from the Contractor:
(1) consent of surety or sureties, if any, to reduction in or partial
release of retainage or the making of final payment;
(2) affidavits, receipts, releases and waivers of liens, or bonds
indemnifying the Owner against liens; and
(3) any other documentation required of the Contractor under the
Contract Documents.

21. Upon request of the Owner, and prior to the expiration of one year
from the date of Substantial Completion, the Architect shall, without
additional compensation, conduct a meeting with the Owner to review
the facility operations and performance.