Reply of Report-I section Queries communicated by dated- 1.09.

2023
Sl. No. Queries Reply
1. Scrutiny of documents revealed that Rs.1.72 crore was DDA has also to pay Rs.1.77 cr. to
paid in excess by CISF to DDA. However, excess CISF as refund of excess payment
amount has been mentioned as Rs.1.77 crore in the already made to DDA for the
draft paragraph. The same may be examined and deficit land measuring 0.58 acre
commented upon. against 7 acres land.
2. Reasons for delay in clearing Running Account Bill on It is apprised that there is no delay
the part of CISF, as claimed by NBCC, may be in payment of RA Bill by CISF (the
examined and commented upon. details of RA Bills is enclosed of
Appendix-A), only the 9th and 10th
RA Bill were halted because the
deviation in Qty was not as per the
original BOQ but later on the Bill
was paid.
3. On reconciliation, the amount of Running Account A detail copy of RA bills and
Bill did not tally with the amount claimed as paid by payment is enclosed herewith
CISF to NBCC. Reason for discrepancy may be (Appendix’ A’) and no additional
arranged from CISF and the amount reconciled. payment was made to NBCC
during the period 14.03.2022 to
31.05.2023
4. Interest accrued/receivable on excess amount paid by
CISF to DDA for the retention period may be worked
out and intimated for inclusion in the draft paragraph.
5. A copy of letter of approval by Ridge Management A copy of all the clearances
Board, as well as other authorities, may kindly be obtained from Ridge Management
furnished. Board and other agencies is
furnished. (Copy enclosed)
6. Monitoring aspect at MHA and CISF level may please Lapse of scheduled tome for
be elucidated upon so that responsibility for delay in completion and remaining work has
completion of the project can be fixed. been halted since January 2020 i.e.
for more than three years.
7. Present status of the project as well as (i)At present CISF Unit GBS
refund/adjustment of interest may be furnished. purposed to adjust short acquisition
of land Rs.1,76,98,267.00 against
DDA Ground Rent from 2015 to
2024 Rs.4,33,88,640.00
(Rs.48,20,960 per annum) and
requested MHA to pay
2,56,90373.00 to DDA (letter encl)
(ii) Construction work at
Maidangarhi ( physical progress ) is
37%.
(iii) Vide letter no. 100823 date
10.08.2023 NBCC demanded
47,19,63,530.00 for completion of
balance work at Maidangarhi . Vide
letter no.333 dated 16.08.2023 the
same has been forwarded to NCR
HQrs.