Isolation Procedure_V01
Isolation Procedure_V01
Table of Contents
1. Goal and Purpose..............................................................................................................................3
2. Scope..................................................................................................................................................3
4. Responsibilities..................................................................................................................................3
6. Related documents............................................................................................................................6
7. Version table......................................................................................................................................6
Isolation Procedure_V01
This Battery Charger/UPS isolation procedure will be used as a guideline for the isolation of Battery
Charger/UPS at Project/ O&M site.
2. Scope:
This Isolation procedure is to ensure Battery Charger/UPS isolation with standard procedures.
4. Responsibilities:
The O&M manager is responsible for making sure that Battery Charger/UPS is isolated in a
systematic and safe manner.
Following activities will be performed for Isolation of Battery Charger/UPS at the solar power
plants. O&M Engineer’s physical presence is required to witness procedure at project site.
Isolation Procedure_V01
Isolation Procedure_V01
Sl.
Steps Reference
No.
Switch off the MCB of UPS incoming and outgoing and use
2.
LOTO.
Isolation Procedure_V01
6. Related documents
UPS Data Sheet and Maintenance Manual from OEM.