You are on page 1of 6

ADITYA BIRLA RENEWABLE SPV1 LTD

Isolation Procedure_V01

Isolation Procedure for Battery Charger/UPS.

5 MWp PV Plant, Location: Sewagram, Vayor – Gujarat. 1|Page


ADITYA BIRLA RENEWABLE SPV1 LTD

Isolation Procedure_V01

Table of Contents
1. Goal and Purpose..............................................................................................................................3

2. Scope..................................................................................................................................................3

3. Terms and Abbreviations.................................................................................................................3

4. Responsibilities..................................................................................................................................3

5. Process and Description...................................................................................................................3

5.1. Required PPE’s............................................................................................................................4

5.2. Needed Accessories.....................................................................................................................4

5.3. General Safety Requirement:......................................................................................................5

5.4. Isolation of Battery Charger/UPS:..............................................................................................5

6. Related documents............................................................................................................................6

7. Version table......................................................................................................................................6

1. Goal and Purpose:

5 MWp PV Plant, Location: Sewagram, Vayor – Gujarat. 2|Page


ADITYA BIRLA RENEWABLE SPV1 LTD

Isolation Procedure_V01

This Battery Charger/UPS isolation procedure will be used as a guideline for the isolation of Battery
Charger/UPS at Project/ O&M site.

2. Scope:

This Isolation procedure is to ensure Battery Charger/UPS isolation with standard procedures.

3. Terms and Abbreviations:

1. O&M : Operation & maintenance


2. LOTO : Lock Out Tag out
3. PPE : Personal Protective Equipment
4. B/D : Breakdown
5. UPS : Uninterrupted power supply
6. BB : Battery Bank

4. Responsibilities:

The O&M manager is responsible for making sure that Battery Charger/UPS is isolated in a
systematic and safe manner.

5. Process and Description:

Following activities will be performed for Isolation of Battery Charger/UPS at the solar power
plants. O&M Engineer’s physical presence is required to witness procedure at project site.

5.1. Required PPE’s:

5 MWp PV Plant, Location: Sewagram, Vayor – Gujarat. 3|Page


ADITYA BIRLA RENEWABLE SPV1 LTD

Isolation Procedure_V01

5.2. Needed Accessories:

1. Logbook for entering details.


2. Torque wrench.
3. Multimeter
4. Infrared temperature gun
5. Spanner set

5 MWp PV Plant, Location: Sewagram, Vayor – Gujarat. 4|Page


ADITYA BIRLA RENEWABLE SPV1 LTD

Isolation Procedure_V01

5.3. General Safety Requirement:

1. Work Permit must be filled for isolation.


2. Use proper & healthy PPE’s.
3. Use proper & healthy tools during work.
4. Only trained persons should perform isolation.
5. Never attend isolation alone.

5.4. Isolation of Battery Charger/UPS:

Sl.
Steps Reference
No.

Obtain Electrical Work Permit from Site In charge in order to


1.
isolate the Battery Charger/UPS.

Switch off the MCB of UPS incoming and outgoing and use
2.
LOTO.

Ensure that residual voltages are discharged after isolation and


3. prior to attend any maintenance or breakdown work.
Disconnect batteries if require.

4. Work can be started after completion of above procedure.

5 MWp PV Plant, Location: Sewagram, Vayor – Gujarat. 5|Page


ADITYA BIRLA RENEWABLE SPV1 LTD

Isolation Procedure_V01

6. Related documents
UPS Data Sheet and Maintenance Manual from OEM.

7. Version table

Creator Reviewer Approver Change(s) Date Version


XX.XX.XX
Hiren xxx xxx First draft V00_01
XX

5 MWp PV Plant, Location: Sewagram, Vayor – Gujarat. 6|Page

You might also like