Professional Documents
Culture Documents
Method Statement For Lifting Operations.
Method Statement For Lifting Operations.
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE
Table of Content
1.0 Purpose 2
2.0 Objective 2
3.0 Scope 2
4.0 Quality of Installation 2
5.0 Risk Assessment 2
6.0 Equipment 2
7.0 Qualifications, Experience, Information 3
Make Sure that the Lifting Tackle: 3
Load 3
Make Sure That the Load Itself Is: 3
Travelling 3
Workers 4
8.0 Health & Safety Hazards 4
9.0 Responsibilities 4
10.0 Procedure 4
Project Manager 4
Project Engineer 4
Supervisor 5
Method of Statement
Method Statement Page 2 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE
1.0 Purpose
The general purpose is to ensure that a Safe System of Work (SSOW) applies to the risks associated with lifting,
moving, and lower pipes, concrete rings etc. Each activity has been carefully considered and appropriate
controls implemented. The specific purpose of this Method Statement procedure is to describe the method of
lifting, moving, and install Port cabin.
2.0 Objective
This method statement is critical to the health and safety (H&S) of the activity it relates to. It is too followed and
adhered, any deviation or changes must be first authorized by the site supervisor
3.0 Scope
We will be using a mobile Crane to lift, move, and install port cabin. The excavations will be in smooth area and
involve following procedure.
Transportation
Lifting
Installation
Method of Statement
Method Statement Page 3 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE
6.0 Equipment
Before any lifting operation, ensure that the relevant safety checks have been undertaken on the [Crane/Heavy
Lifting Machinery] and any other equipment being used:
● Leather Gloves
● Hard Hat
● Goggle Glass
● Dust Mask
● First Aid Kit
● Two-way radio
● Measuring equipment
Method of Statement
Method Statement Page 4 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE
9.0 Responsibilities
Project Manager
• Project Manager shall be responsible for overall project execution.
Method of Statement
Method Statement Page 5 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE
Project Engineer
• Lifting, moving, are carried out according to the specifications and approved method statement.
• Provision of all necessary information and distribution of responsibilities to his Lifting team in
consultation with the Lifting manager.
• The work progress is monitored following the required program and reports the same to the Lifting
Manager.
• The implementation of any request that might be raised by the Consultant.
• Allocation of manpower, materials and equipment’s in consultation with Lifting Manager also
monitoring their timely supply at the Lifting location.
Supervisor
• The carrying-out the work and the proper distribution of all the available resources in coordination with
the Site Engineering daily.
• Daily reports of the works are achieved and coordinated for future planning with the site Engineer.
• Incorporate all the QC and Safety requirements as requested by the concerned Engineer.
• Meeting with any type of unforeseen incident or requirement.
Procedure
• The unloading operation shall be carried out under supervision of competent person who is aware of
precautions to be taken
• The area where container to be unloaded must be suitable for unloading to be done safely
• The area to unloaded should be checked by Manage/supervisor and make sure that safe to proceed
• Crane operator must be certified for unloading Container
• All people include Driver he must remain in vehicle and he must be clear off working area during lifting
operation
• The person in control of the lifting Equipment/ container must ensure that the lifting operation can be
carried out safely before the work starts
Method of Statement
Method Statement Page 6 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE
• The following Standards and General Instructions apply to marine and offshore cranes, hoists, hooks,
slings, rigging, personnel work platforms, and personnel carriers. Consulting Services Department shall
resolve all disputes regarding conflicts between these Standards, and the appropriateness
of substituting other international standards, i.e., G.I
G.I. 2.100-Work Permit System
G.I. 6.020-Personnel Floatation Devices for Work On, Over or Near Water
G.I. 7.025-Mobile Heavy Equipment Operator Testing and Certification and Investigating Procedures
G.I. 7.026-Cranes & Heavy Equipment Incident Reporting and Investigating Procedures
G.I. 7.027L-Personnel Work Platform Operations (Manbasket)
G.I. 7.028-Crane Lifts: Types and Procedures
G.I. 7.029-Inspection, Use and Maintenance of Below-the-Hook Lifting Equipment for Cranes
G.I. 7.030-Inspection and Testing Requirements of Elevating/Lifting Equipment
Method of Statement