You are on page 1of 6

Method Statement Page 1 of 6

(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE

Table of Content
1.0 Purpose 2
2.0 Objective 2
3.0 Scope 2
4.0 Quality of Installation 2
5.0 Risk Assessment 2
6.0 Equipment 2
7.0 Qualifications, Experience, Information 3
Make Sure that the Lifting Tackle: 3
Load 3
Make Sure That the Load Itself Is: 3
Travelling 3
Workers 4
8.0 Health & Safety Hazards 4
9.0 Responsibilities 4
10.0 Procedure 4
Project Manager 4
Project Engineer 4
Supervisor 5

Method of Statement
Method Statement Page 2 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE

1.0 Purpose
The general purpose is to ensure that a Safe System of Work (SSOW) applies to the risks associated with lifting,
moving, and lower pipes, concrete rings etc. Each activity has been carefully considered and appropriate
controls implemented. The specific purpose of this Method Statement procedure is to describe the method of
lifting, moving, and install Port cabin.

2.0 Objective
This method statement is critical to the health and safety (H&S) of the activity it relates to. It is too followed and
adhered, any deviation or changes must be first authorized by the site supervisor

3.0 Scope
We will be using a mobile Crane to lift, move, and install port cabin. The excavations will be in smooth area and
involve following procedure.
Transportation
Lifting
Installation

4.0 Quality of Installation


Quality of installation and materials at the site will be ensured by the project team consisting of a Project Manager,
Project Engineers, and the site Supervisor. All the installation at the project will be according to the project
specification. applicable standards and /or industry norms. All installation work shall factually adopt and carry out
as per the Manufacturer's/Client's Consultant's Health & Safety recommendations for handling and use of the
materials/substance. Main Contractor/Sub-Contractor/Third party shall ensure that all workers are aware of the
applicable H&S requirements.

5.0 Risk Assessment


Before proceedings to any lifting work, Risk hazard Identification to be conducted for the particular lifting
operation. This is required to be done for every lifting operation activity/work. If a series of similar operations are
to be undertaken one RA may be sufficient, but check carefully that something critical has not changed, for
example, if the size and/or weight of the load is much greater than for the previous lift then a new RA will need
to be undertaken.
This method statement provides a generic safe system of work for lifting operations, but the specific hazards of
the work, as determined by the risk assessment, will have to be added if not already covered here.

Method of Statement
Method Statement Page 3 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE

6.0 Equipment
Before any lifting operation, ensure that the relevant safety checks have been undertaken on the [Crane/Heavy
Lifting Machinery] and any other equipment being used:
● Leather Gloves
● Hard Hat
● Goggle Glass
● Dust Mask
● First Aid Kit
● Two-way radio
● Measuring equipment

7.0 Qualifications, Experience, Information


● The Project Manager (PM) will supervise the entire lifting operations. Both Site Managers/Project
Engineer must be experienced in using a [Crane/Heavy Lifting Machinery] and have the relevant and
current qualification and certification. For every lifting task, one competent person must be
assigned/allocated the role of Lift Manager and take accountability for the Risk assessment/hazard
Identification and give instructions for the lifting operation.
● Only qualified workers will be allowed to use mechanical tools and equipment.
● After Risk assessment/hazard Identification has been accomplished and details added to this method
statement, all workers involved in the lifting operation will be inducted on the work; given details of the
Risk assessment & Method Statement (RAMS), and any other information they require.
Make Sure that the Lifting Tackle:
1. Is appropriate for the task?
2. Will fit the lifting lugs and/or holes on the rings, pipes and biscuits be accurately and properly secured?
3. Is rated for the force that will be strived during the lift operation?
4. Is properly adjusted so that the angle at which the wires/chains/bars are working is appropriate for the
lift and is not leading to forces greater than the tackle can bear?
5. Has appropriate blocks and shackles etc. where needed?
6. Is undamaged and in good condition?
Load
The Site Lift Supervisor must make sure that the load can be safely lifted, carried and lowered by the Crane. The
load must be within the safe lifting load and a safe working load of the Crane. The lift supervisor will need to be
sure that the Crane can carry the load at the jib extension that will be required for the lift, moving and lowering,
remembering that the larger the load the further out the jib will have to move. And larger here also means
heavier.

Method of Statement
Method Statement Page 4 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE

Make Sure That the Load Itself Is:


1. secured and evenly balanced
2. not obstruct the operation of the Crane
3. guided by handling ropes if necessary, so that it does not swing
Travelling
The Lift Supervisor must make sure that the route to be taken by the Crane
with the load is:
1. Level enough for the load to be carried safely firm enough to bear the combined weight of the Crane
2. Load unobstructed wide enough for the load and Crane to pass through easily
3. Not near to excavations which could collapse under the weight of the Crane and load.
Workers
The Lifting Forman must make sure that the workforce involved in the lifting Operation:
1. Understand their role
2. Are competent to undertake that role
3. Have appropriate PPE, including high viz vests
4. Are not required to be positioned where the Crane or load is a hazard for them

8.0 Health & Safety Hazards


Before commencing any lifting, moving work, the team shall strictly follow as per the Manufacturer’s/ Client’s /
Consultant’s Health & Safety recommendations for handling and use of the materials and ensure all involved
personnel shall be aware of the same. The general safety guidelines are given below:

1. Ensure the work area is safe & clean.


2. All employees shall adopt safe working practices.
3. Safety equipment (Safety helmet, safety shoes, coveralls, gloves, goggles, face mask as applicable) to be
worn at all times.
4. When working at a high level, the appropriate safety harness shall be used and secured whilst working-
extra care shall be taken whilst using tools at a high level to prevent dropping.
5. Ensure sufficient lighting is available during all stages of installation & testing.
6. Report all accidents no matter how small to the Safety Officer on duty.
7. Ensure any electrical isolation permit is obtained if required, for installation any electrical equipment,
panel, cable, wires and accessories.

9.0 Responsibilities
Project Manager
• Project Manager shall be responsible for overall project execution.

Method of Statement
Method Statement Page 5 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE

• He will coordinate with the client and head office.


• He is responsible for progress monitoring, attending review meetings and resource management.
• Overall, he will be responsible for the timely completion of the project following all contractual
requirements.

Project Engineer
• Lifting, moving, are carried out according to the specifications and approved method statement.
• Provision of all necessary information and distribution of responsibilities to his Lifting team in
consultation with the Lifting manager.
• The work progress is monitored following the required program and reports the same to the Lifting
Manager.
• The implementation of any request that might be raised by the Consultant.
• Allocation of manpower, materials and equipment’s in consultation with Lifting Manager also
monitoring their timely supply at the Lifting location.

Supervisor
• The carrying-out the work and the proper distribution of all the available resources in coordination with
the Site Engineering daily.
• Daily reports of the works are achieved and coordinated for future planning with the site Engineer.
• Incorporate all the QC and Safety requirements as requested by the concerned Engineer.
• Meeting with any type of unforeseen incident or requirement.
Procedure
• The unloading operation shall be carried out under supervision of competent person who is aware of
precautions to be taken
• The area where container to be unloaded must be suitable for unloading to be done safely
• The area to unloaded should be checked by Manage/supervisor and make sure that safe to proceed
• Crane operator must be certified for unloading Container
• All people include Driver he must remain in vehicle and he must be clear off working area during lifting
operation
• The person in control of the lifting Equipment/ container must ensure that the lifting operation can be
carried out safely before the work starts

Method of Statement
Method Statement Page 6 of 6
(Lifting Operations)
Department Document Ref. No. Issue Date Revision
10/05/2023 00
HSE

APPLICABLE CODES, STANDARDS, REGULATIONS, ANDGENERAL INSTRUCTIONS:

• The following Standards and General Instructions apply to marine and offshore cranes, hoists, hooks,
slings, rigging, personnel work platforms, and personnel carriers. Consulting Services Department shall
resolve all disputes regarding conflicts between these Standards, and the appropriateness
of substituting other international standards, i.e., G.I
G.I. 2.100-Work Permit System
G.I. 6.020-Personnel Floatation Devices for Work On, Over or Near Water
G.I. 7.025-Mobile Heavy Equipment Operator Testing and Certification and Investigating Procedures
G.I. 7.026-Cranes & Heavy Equipment Incident Reporting and Investigating Procedures
G.I. 7.027L-Personnel Work Platform Operations (Manbasket)
G.I. 7.028-Crane Lifts: Types and Procedures
G.I. 7.029-Inspection, Use and Maintenance of Below-the-Hook Lifting Equipment for Cranes
G.I. 7.030-Inspection and Testing Requirements of Elevating/Lifting Equipment

Method of Statement

You might also like