Professional Documents
Culture Documents
REPUBLIC OF YEMEN
Public Disclosure Authorized
TAIZ GOVERNORATE
TAZCW 1
Rehabilitation of Water Network in Eastern Part ofTaiz
TAZCW2
Rehabilitation of Water Network in Western Part ofTaiz
Public Disclosure Authorized
TAZCW3
Rehabilitation of Wastewater Treatment Plant and Extension
of Main Trunk line in Easter Taiz
TAZCW5
Rehabilitation and Extension of Sewerage System
TAIZ GOVERNORATE
I
3.4 Negative Environmental Impacts ........................................................ 29
3.5 Environmental Mitigation Measures .................................................. 33
3.6 Main Findings .................................. " ... , ............. ' ..... , .. , ............... 36
3.7 Recommendations. . . . . .. . ............................. , ................ , ................. .3 7
3.8 Photographs .............................................................................. ".38
CHAPTER FOUR............................................................................. 41
4.1 Project Description ......................................................................... 42
4.2 Governmental Coordination & Consultation ............... , .......................... ..4 3
4.3 Public Consultation ...................................................................... ..44
4.4 Negative Environmental Impacts ....................................................... .44
4.5 Environmental Mitigation Measures .................................................... .47
4.6 Main Findings ........... , ................................................................. 51
4.7 Recommendations .. , ........... , ........................................................... 51
4.8 Photographs ........................................ , .......... , ........................... 52
II
LIST OF ABBREVIATIONS
IDA fu~rn~~n~D~cl~mem~eocy
WB World Bank
III
REGISTER OF TABLES
IV
INTRODUCTION
The Urban Water Supply and Sanitation Project (UWSSP) is one of the biggest projects
working in water and sanitation sector in Yemen. The project aims to provide efficient
and sustainable service to ensure environme~tal and social stability in accordance to the
Five Year Development Plan, the Millennium Development Goals and Poverty Reduction
Strategy.
The total cost of the project is approximately (US$150) million of which the approved
credit amount by the International Development Agency (IDA) -for phase (1)- is
approximately (US$130) million and the committed amount by the Government of
Yemen (GoY) is (US$20) million.
Urban Water Supply and Sanitation Project has included Environmental Impact
Assessment (EIA), along with Environmental Management Plan (EMP) and Mitigation
Program for civil works contracts signed by the project.
One of the overall objectives of the Environmental Management Plan (EMP) and
Mitigation Program is to ensure the possibility of correcting the planed measures to
mitigate adverse impacts. Many of these impacts have been foreseen, but the degree of
each impact may differ from the one expected.
CHAPTRER ONE
2
1.1 Project Description
-Project name: Rehabilitation of Water Network in Eastern Part ofTaiz
- Contract dates
• Commencement date: 25.05.2005
• Contract period: 18 months (547 days)
• Extension time awarded: 313 days
• % of work Executed: 91
For more information about contract 1, please refer to the Monthly Progress Report
(June-July2007).
3
Table 1.1: Scope of Work and Work Executed
%
I Scope of work Work executed
Complete
• 6000 m3.
I I
4
1.2 Governmental Coordination & Consultation
All construction works on contract #1 are coordinated with governmental sector through
the information and provision of related authorities with drawings for locations and
. .
timings for schedule constructions works. However, closer consultation was done through
the existence of representative of related authorities. Such representatives included
representatives of:
Potential impacts of construction phase on environment -as identified in the EIA study-
are assessed in table 1.2.
5
Table 1.2: Potential Negative Impacts during Construction Phase
I Issue Impact
Degree of actual
i
Impact
Noise and Construction Nuisance value that may in extreme cases Low
. Disturbance affect health
Nuisance value that may in extreme cases
affect health of general population. Low
Air Quality (excL dust)
Vulnerable groups could have much higher
I health threats.
I
Dust i Traffic on local dirt roads Moderate
• Archaeology/Cultural Negligible
Negligible
Heritage
Material Stockp'les
I Access Not significant
i
resource needs.
i I
6
I Access and construction Mix of heavy construction traffic and existing Low
traffic traffic will be a potential source of accidents
I
Resource Use
I
i Water Effect on existing resource users Low
Permanent Impacts
Low
Storage and use of hazardous chemicals.
Flushing and Disinfection
Disposal of wastes and resources use
7
1.5 Environmental Mitigation Measures
As identified in the EIA study, the project may cause some negative impact to the
environment. Therefore, some measures were put to mitigate these impacts. Potential
negative impacts, mitigation measures, implementation responsibility and situation are
summarized in table 1.3.
8
Table 1.3: Potential Impacts and Mitigation Measures
,--~~
----
Sewage from destroyed Contamination from proper Controlled transport to WWTP. Temporary Contractor Not applicable
cesspit and households disposal of sewage disposal measures and waste dilution if
necessary. Cesspit Sampling. ,
Improved living Increase in incidence of A malaria abatement program will be ESO in conjunction No Program was
conditions for malaria designed and implemented under the project with local malaria designed
Anopheles and health officials
f--~ .
Dned wastewater Improper use and lack of ~ Sludge re-use policy study to be performed PIU Not applicable
sludge storage space and financed under the project
I Industrial pollution Contamination of urban Survey of Polluting Industries ESO Not applicable
environment and sewage
system
~-~
Effluent and influent ' Low quality wastewater Regular Sampling will be included in the Independent Not applicable
monitormg at WWTP mitigation measures sampling contractor
----
Soil & Ground Water Contamination soil and Proper clothing and worker education. Proper Contractor, Not applicable
groundwater in construction disposal if warranted. Soil and groundwater independent sampling
areas and downstream of downstream of the WWTP and in the project contractor (lab tests)
WWTP area will be monitored to determine if
contamination has occurred
~~~
9
~~~
Disturbance during Use of heavy equipment restricted from 7 p.m Contractor, Works restricted to •
construction to 6 a.m. proper noise muffling devises, independent sampling daytime hours. No
traffic routing and monitoring contractor (lab tests) complaints received.
r---~
Dust Disturbance during Use of dust suppression measures such as Contractor, Contractor sprayed
construction wetting, dust covers and speed restriction. independent sampling water on soil in
Monitoring will be carried out. contractor (lab tests) project areas. No
complaints received
r-
Water use: on and off Water contamination. Contractors will be required to bring all water Contractor, Pill, Contractor using own
site Reduced public water level on site in tankers and only be allowed to fill TWSLC water sources. Water
their tankers at approved sites. Water storage use on site is minimal.
provisions must be made.
!-----~~
Hazardous chemicals Improper disposal of Supply of proper training and safety gear. Contractor Contractor supplying
chemicals used to flush water Spill contingency plan training to workers.
lines Contractor disposing
chemicals at approved
sites
. Concentrations limited to WWTP's technical TWSLC, WWTP Concentration limited
capacity to treat Staff, Independent to WWTP's technical
sampling contractor capacity to treat
(lab tests)
~~~.--
10
-Medical Clinic Construction site related A temporary clinic will be established in ;0 Unn "'''''''''''' "f)'
mJunes project areas that do not have easy access to
local facility
Public Consultation Unnecessary disruption of An extensive public consultation program will PIU Interviews with
affected communities continue to be undertaken, including the use residents in project's
of radio, TV, town meetings, and household area have been
surveys undertaken. No larger
scale interview
performed
I ESO & Infonnation Non-Compliance with An Environmental Safety Officer (£SO) will PIU, TWSLC
ESO is contracted
Campaign Management Plan be hired to monitor mitigation measures and
since Aug.2007
disseminate relevant information
--------
i Environmental Non Compliance with Semi-annual reviews performed to examine ESO, with assistance To be implemented
Reviews Mitigation Plan compliance with mitigation plan, regulatory from WB
requirements, and to identify potential Environmental
environmental problems Specialist as part of
IDA supervision
mission
11
1.6 Main Findings
1- During site visit to the reservoirs # 3&4, it was noticeable that measures for
workers safety were not completely practiced. Although workers applied some
safety measures, other measures were neglected like wearing protective
helmets.
2- Stairs used to reach the roof of reservoir # 3&4 were not provided with side
protective bars. Stairs of reservoir 4 was not safely fixed with enough
supporting stands.
3- Reservoir 4, inside TWSLC, has open chamber that holds outlet pipes of the
reservoir. This chamber is not designed with a water exit which means that the
open chamber will be collecting water in each rain event. This shall create a
potential media for water transmitted diseases and also increase the corrodibility
of pipes inside the chamber.
1.7 Recommendations
12
1.8 Photographs
13
Republic of Yemen
Ministry Of Water and Environment
Urban Water Supply and Sanitation Project
CHAPTRER TWO
14
2.1 Project Description
-Project name: Rehabilitation of Water Network in Western Part of Taiz
The contract scope of work is mainly to replace the deteriorated water network in west
part of Taiz (see table
- Contract dates
• Commencement date: 25.05.2005
• Contract period: 18 months (547 days)
• Extension time awarded: 306 days
• % of work Executed: 89
For more information about contract 2, please refer to the Monthly Progress Report
(June-July2007).
Table 2.1: Scope of Work and Work Executed
15
2.2 Governmental Coordination & Consultation
Coordination between the PIU and governmental sector was mainly achieved through
representatives of main related authorities which are:
Potential impacts of construction phase on environment -as identified in the ElA study-
are assessed in table 2.2.
16
Table 2.2: Potential Negative Impacts during Construction Phase
Degree of actual
Issue Impact
Impact
I Noise and Construction Nuisance value that may in extreme cases Low
Disturbance affect health
Nuisance value that may In extreme cases
affect health of general population. Low
Air Quality (excl. dust)
Vulnerable groups could have much higher
health threats.
17
Mix of heavy construction traffic and existing i Low
Access and construction traffic
traffic will be a potential source of accidents
Resource Use
Water Low
• Effect on existing resource users
J
i Permanent Impacts
None None
I Property take
None None I
I Cultural Properties
Not significant
I Flora and Fauna Minor
i
•
Malaria Threat to public health Not significant
Low
Storage and use of hazardous chemicals.
Flushing and Disinfection
Disposal of wastes and resources use
18
2.5 Environmental Mitigation Measures
As identified in the EIA study, the project may cause some negative impact to the
environment.
. Therefore, some measures were put to mitigate these impacts. Potential
.
negative impacts, mitigation measures, implementation responsibility and situation are
summarized in table 2.3.
19
Table 2.3: Potential Impacts and Mitigation Measures
---
Improved living Increase in incidence of A malaria abatement program will be designed ESO conjunction No Program was
conditions for malaria and implemented under the project with local malaria and designed
Anopheles health officials
--- --
Dried wastewater I Improper use and lack of Sludge re-use policy study to be performed and PIU Not applicable
I sludge storage space financed under the project
Industrial pollution Contamination of urban Survey of Polluting Industries ESO Not applicable
environment and sewage
system
--- !---- .
I Effluent and influent Low quahty wastewater Regular Sampling will be included in the Independent sampling Not applicable
monitoring at WWTP mitigation measures contractor
Soil & Ground Water Contamination soil and Proper clothing and worker education. Proper Contractor, Not applicable
groundwater in construction disposal if warranted. Soil and groundwater independent sampling
areas and downstream of downstream of the WWTP and in the project area contractor (lab tests)
WWTP will be monitored to determine if contamination
has occurred
-
20
Noise Disturbance during Use of heavy equipment restricted from 7 p.m to Contractor, Works restricted
construction 6 a.m. proper noise muffling devises, traffic independent sampling to daytime
routing and monitoring contractor (lab tests) hours. No
complaints
received.
r--~ ~--~~
. Dust Disturbance during Use of dust suppression measures such as Contractor, No complaints
cons truction wetting, dust covers and speed restriction. independent sampling received
Monitoring will be carried out. contractor (lab tests)
Water use: on and off ! Water contamination. i Contractors will be required to bring all water on Contractor, PIU, Contractor usmg
. site Reduced public water level site in tankers and only be allowed to fill their TWSLC own water
tankers at approved sites. Water storage sources. Water
provisions must be made. use on site is
mmimal. I
r--=~:::~ ~----- ~-- ~---~
Hazardous chemicals Improper disposal of Supply of proper training and safety gear. Spill Contractor Contractor
chemicals used to flush water contingency plan supplying
lines training to
workers.
Contractor
disposing
chemicals at
21
-----
approved sites
,
---
Medical Clinic Construction site related A temporary clinic will be established in project ESO Unnecessary
injuries areas that do not have easy access to local facility
Public Consultation Unnecessary disruption of An extensive public consultation program will PIU Interviews with
affected communities continue to be undertaken, including the use of residents in
radio, TV, town meetings, and household surveys project's area
have been
undertaken. No
larger scale
interview
performed
ESO & Information Non-Compliance with An Environmental Safety Officer (ESO) will be PIU, TWSLC ESO is
Campaign Management Plan hired to monitor mitigation measures and contracted since
disseminate relevant information Aug.2007
-------
22
En vironmental Non Compliance with Semi-annual reviews performed to examine ESO, with assistance To be
Reviews Mitigation Plan compliance with mitigation plan, regulatory from WB implemented
requirements, and to identify potential Environmental
environmental problems Specialist as part of
IDA supervision
mlSSlon
23
2.6 Main Findings
1. It was noticed that the some of the open trenches were left with remainings of
the excavation works in place without safety sings and tapes. Such trenches
were noticed in main roads which disturb the traffic and form a hazard to
drivers and pedestrians especially during night hours.
2. Noise was limited to working hours and no complains were received from
civilians against the contractor as project works were primarily implemented
during daytime hours.
4. As outlined in the EMP, the public was warned from open trenches through
the use of security tapes and signs. This method proved to be effective in
warning public from open trenches, however, in many cases these tapes and
signs are removed by children or stolen -especially during night hours- due to
the large area of the project which unable working staff from preventing the
removal of these tapes and sings.
5. ESO field visit for contract #2 came during the preliminary handing over of
the project. So it should be mentioned that this report is based mainly on
observations made for the very limited remaining construction sites.
2.7 Recommendations
24
2.8 Photographs
25
Republic of Yemen
Ministry Of Water and Environment
Urban Water Supply and Sanitation Project
CHAPTRER THREE
26
3.1 Project Description
- Contract dates
• Commencement date: 25.05.2005
• Contract period: 18 months (547 days)
• Extension time awarded: 316 days
• % of work Executed: 98
For more information about contract 3, please refer to the Monthly Progress Report
(June-J uly2007).
completed.
I
27
2- Supply and installation of about 2200m 98
UPVC pipe of DN 150mm including of
about 220 on site Manholes for house
connection.
5- Grit Chamber
6- Parshall Flume
28
3.2 Governmental Coordination & Consultation
Coordination with governmental sector was mainly done through the existing
representative of related authorities. These people represent local authorities of:
Public were mainly consulted during the project implementation by informing them about
the project activities and responding to their opinions and complaint However, no large-
scale public consultation was performed.
Potential impacts of construction phase on environment -as identified in the EIA study-
are assessed in table 3.2.
29
Table 3.2: Potential Negative Impacts during Construction Pbase
General Impacts
\ Noise and Construction Nuisance value that may in extreme cases Moderate
Disturbance affect health
Air Quality (excL dust Nuisance value that may in extreme cases Low
affect health of general population .
. Vulnerable groups could have much
i higher health threats.
Waste Soil Material Removal and disposal of non usable soil Low
materials
Hydrogeology, Geology and Negligible Negligible
Topology
. Fauna, Flora and Ecology Effect on local flora and ecology Low
I
I
i Equipments Maintenance and Storage and use of Chemicals, industrial Low
I Cleaning waste disposal (especially oils).
I Borrow Pits Potential scale of operation. Possibility for Low
numerous new sites. Access requirements.
Water resource needs.
Access and construction traffic Mix of heavy construction traffic and I Low
existing traffic will be a potential source
of accidents i
30
I
I Resource Use
i
31
Table 3.2 (Cont.) Impacts Related to Sanitary Projects
l Wastewater Disposal
from theIr dIsposal system.
- - - - I - - - · _ _ · _ · _ _ _ _L _ · _ _ _ _
wastes
i
32
sites, (schools, mosques and !
such like) or other public
buildings.
i
I Operation phase
As identified in the EIA study, the project may cause some negative impact to the
environment. Therefore, some measures were put to mitigate these impacts. Potential
negative impacts, mitigation measures, implementation responsibility and situation are
summarized in table 3.3.
33
Table 3.3: Potential Impacts and Mitigation Measures
34
-
f---.
public clinics.
Interviews with
residents in
An extensive public consultation program will project's area have
Unnecessary disruption
Public Consultation continue to be undertaken, including the use of PIU been undertaken.
of affected communities
radio, TV, town meetings, and household surveys No larger scale
interview
,.- performed
. An Environmental Safety Officer (ESO) will be
ESO & Information Non·Compliance with ESO is contracted
hired to monitor mitigation measures and PIU, TWSLC
Campaign Management Plan since Aug.2007
~. -
disseminate relevant information
ESO, with assistance
Semi·annual reviews performed to examine fromWB
Environmental Non Compliance with compliance with mitigation plan, regulatory Environmental To be
Reviews Mitigation Plan requirements, and to identify potential Specialist as part of implemented
environmental problems IDA supervision
mission
35
3.6 Main Findings
1~ Sludge removed from treatment ponds is piled inside the WWTP and no plan for
reusing the sludge is developed yet.
3- In the construction site of the pump station in Wadi A1 Qadi, some safety
measure like using warning sings and tapes are not applied.
4- According to the local residents, odour is emitted out of manholes and inspection
chambers due to the use of metal covers that are designed with ventilation wholes.
5~ Some concerns are raised about the possibility of erosion of the piled sludge to the
treatment ponds.
7- Potential risk that is posed on public due to the consumption of vegetables that are
irrigated by untreated wastewater is not known.
36
3.7 Recommendations
37
3.8 Photographs
38
Piles of sludge inside Taiz WWTP
39
Upper photo: access of animals to the WWTP
40
Republic of Yemen
Ministry Of Water and Environment
Urban Water Supply and Sanitation Project
CHAPTRER Four
41
4.1 Project Description
-Project name: Rehabilitation and Extension of Sewerage System
The project contract covers 3 main components as shown in table 4.1. All sewer lines are
ready for handing over. This contract is substantially completed and in many cases the
residents have already connected the system.
- Contract dates
• Commencement date: 25.05.2005
• Contract period: 18 months (547 days)
• Extension time awarded: 77 days
• % of work Executed: 98
For more information about contract 5, please refer to the Monthly Progress Report
(J une-July2007).
42
Table 4.1: Scope of Work and Work Executed
Coordination with governmental sector was done through the provision of information
about the project working locations and timing for construction and excavation works to
the related authorities. Coordination was mainly implemented through representative of
related authorities that appointed as permanent coordinators with the project.
Representatives included the local authorities:
43
4.3 Public Consultation
Public were mainly consulted during the project implementation by informing them about
the project activities and responding to their opinions and complai!1t. However, no large-
scale public consultation was performed.
Potential impacts of construction phase on environment -as identified in the EIA study-
are assessed in table 4.2.
General Impacts
N-o-is-e-an-d-C-o-n-s-tr-u-c-t-io-n----r-N-u-l-·s-an-c-e-va-I--u-e-t-h-at-m-a-y--in-e-x-tr-e-m-e-c-a-s-e-s-+---M-o-'d-e-ra-te---1
Air Quality (excl. dust Nuisance value that may in extreme cases Low
affect health of general population.
Vulnerable groups could have much
higher health threats.
Dust Traffic on local dirt roads Low
Waste Soil Material Removal and disposal of non usable soil Low
l I materials
Hydrogeology, GeOIOgYand-TNegITglbIe----·--·---··-------:-I--Negilg;b-Ie---
: Topology I i
I Fauna, Flora and Ecology Negligible 1 Negligible
J
44
Archaeology/Cultural Heritage Negligible Negligible
I
Off site works
45
I Dried Sludge Disposal of large volume of material Not applicable I
I
J
Table 4.2 (Cont.) Impacts Related to Sanitary Projects
Construction Impact
.-~- ..- ~~~
Use of Sludge and Treated Project is unlikely to alter the Not app It cab Ie]
Water at WWTP i composition of wastes used by I
46
farmers at WWTP
I
Soil Contamination Potentially extensive workforce Significant
contact with contaminated materials
and casual public access (esp.
children)
Operation phase
As identified in the EIA study, the project may cause some negative impact to the
environment. Therefore, some measures were put to mitigate these impacts. Potential
negative impacts, mitigation measures, implementation responsibility and situation are
summarized in table 4.3.
47
Table 4.3: Potential Impacts and Mitigation Measures
---
Potential Negative Impact Implementation Implementation
Item Mitigation Measures
Responsibility Situation
Controlled transport to WWTP. Temporary
Sewage from destroyed Contamination from proper
disposal measures and waste dilution if necessary. Contractor Not applicable
, cesspit and households disposal of sewage
I Cesspit Sampling.
L
Improved living ESO in conjunction
Increase in incidence of A malaria abatement program will be designed No Program was
conditions for with local malaria and
malaria and implemented under the project designed
Anopheles health officials
I
Dried wastewater Improper use and lack of Sludge re-use policy study to be performed and i
Effluent and influent Regular Sampling will be included in the Independent sampling
Low quality wastewater Not applicable
monitoring at WWTP mitigation measures contractor
I
I
Proper clothing and worker education. Proper
Contamination soil and
disposal if warranted. Soil and groundwater Contractor,
groundwater in construction
Soil & Ground Water downstream of the WWTP and in the project area independent sampling Not applicable
areas and downstream of
will be monitored to determine if contamination contractor (lab tests)
WWTP
has occurred
-
48
Works restricted
Use of heavy equipment restricted from 7 p.m to Contractor, to daytime
Disturbance during
Noise 6 a.m. proper noise muffling devises, traffic independent sampling hours. No
construction
routing and monitoring contractor (lab tests) complaints
received.
I-
I Use of dust suppression measures such as Contractor,
Disturbance during No complaints
wetting, dust covers and speed restriction. independent sampling
lDUst cons tructi on
Monitoring will be carried out. contractor (lab tests)
received
Contractor using
Contractors will be required to bring all water on
own water
I Water use: on and off Water contamination. site in tankers and only be allowed to fill their Contractor, PIU, .
sources. Water
I site Reduced public water level tankers at approved sites. Water storage TWSLC
use on site is
provisions must be made.
I minimal.
1-- - - - ~-- ---~-- .---- -- -
Improper disposal of
Supply of proper training and safety gear. Spill
Hazardous chemicals chemicals used to flush water Contractor Not applicable
contingency plan
lines
TWSLC, WWTP Staff,
Concentrations limited to WWTP's technical
Independent sampling Not applicable
capacity to treat
contractor (lab tests)
I -
~~dical Clinic Construction site related A temporary clinic will be established in project ESO Unnecessary
--
49
~ -
Interviews with
residents in
project's area
An extensive public consultation program will
Unnecessary disruption of have been
Public Consultation continue to be undertaken, including the use of PID
affected communities undertaken. No
radio, TV, town meetings, and household surveys
larger scale
interview
performed
-
50
4.6 Main Findings
2. Connecting the new sewer system with the old system in Kelabah area is not
completed yet which resulted in wastewater flooding out to the street at least
in one point.
4.7 Recommendations
champers to avoid the emission of unwanted odour. This minor impact should
be considered when designing future sewer systems.
51
4.8 Photographs
Upper photo: The Manhole where the old and new sewage network
should be connected
~ "i!;""'. - '.
Parts of the network that was cancelled due to the hard topography
52