Professional Documents
Culture Documents
Introduction
• When a panel or an area in a seam is
developed by Bord and Pillar method, the
developed pillars in the panel are finally
extracted. This process of extraction of the
developed pillars is called Depillaring.
• Depillaring operation should always
commence from the dip most pillar of the
panel or the mine and progress to the rise
side.
Advantages of depillaring from dip most pillar
• The goaf line i.e. the line adjacent to the worked
out areas lies along the dip side, preventing flow
of water, gas etc to the other workings
• In the event of fire or spontaneous heating,
isolation of the area is easier.
• The goaf area may be filled with water, thereby
preventing spontaneous heating.
• In case of stowing, the stowing water does not
come to the working area.
Methods of depillaring
• Depillaring with caving
• Depillaring with stowing
• Partial extraction
Depillaring with caving
Stook
Method of extraction of Stooks
Full moon method
I
II
III
IV
V
VI
RP
Half moon method
I II III IV V
Half moon method with remnant pillar
I II III
Slicing method
• Each pillar is divided into two equal parts either
by driving a level split or a dip split.
• Each stook is then extracted by taking slices one
after another leaving a rib of about 1-1.5m in
between two slices, which can be robbed down
as much as possible during retreat.
• The maximum width of the slice is permitted upto
4.8m. The allowable area of exposure in any
slice vary depending on the conditions of roof
and depth of working. This is generally 60m2,
90m2, 120m2 or 150m2.
Slicing method
For caving operation, at any point of time, extraction of more
than one slice in a pillar is not permitted. In case of stowing,
two slices in a pillar can be under extraction at any point of
time.
Rib
Slice
Sequence of pillar extraction
• The success of depillaring operation with
caving depends on the correct line of
fracture of strata and rate of roof break.
• After depillaring, settlement of the goaf is
advantageous for the miners as well as
mining, at the same time, the working
faces needs to be kept safe.
• In abnormal conditions where roof does not
break, the following operations are done:
– The length of goaf line is increased so that the roof
breaks.
– No remnant pillar is left near the goaf line.
– If necessary, drilling and blasting may be adopted for
breaking the roof.
– The orientation of goaf line should be chosen such
that the roof breaks.
– Large overhang roof should not be allowed.
Orientation of goaf line
• Straight line of extraction
• Diagonal line of extraction
• Step diagonal line of extraction
• Steep diagonal line of extraction
1 2
1
3 2
3 3 3 3 3
1
2 22 2 2 2 2
11 12 1 1 1 1
Diagonal line of extraction
4 3
4 3 2
4 3 2 1
Step Diagonal line of extraction
• The goaf line moves at an angle of 30 degree with
the panel barrier laid along the strike direction
– During extraction of any two slice in a pillar, the next
slice remains safe.
– This type of goaf line becomes necessary to have wider
face under weak layer of roof.
– Due to regular roof fall, the extraction of middle slices
becomes easier.
– If the caving of roof strata gets delayed due to high
strength, then two slices or stooks when extracted,
allow the roof to get caved.
Step Diagonal line of extraction
12 11 10 9 8 7
10 9 8 7 6 5
8 7 6 5 4 3
6 5 4 3 2 1
Steep Diagonal line of extraction
14 12 10 8 6 4
13 11 9 7 5 3
12 10 8 6 4 2
11 9 7 5 3 1
Requisites of depillaring operation
• Depillaring operations are so planned and
connected that (a) there is least danger to the
safety of the mine and the miner.
• Maximum possible extraction is achieved.
• Extraction of other seam/section is not
hampered
• Extraction is economic
• Danger from premature collapse of pillars, influx
of noxious gases, inundation etc are avoided.
Preparatory arrangement before
depillaring
• The following arrangements are necessary before
depillaring operation is started:
– Determination of panel size taking into account
incubation period and rate of extraction, if development
has not been done by panel system
– Obtaining permission from DGMS for depillaring in all
cases, from railway authority if depillaring is to be
conducted below railway line and from the district
authority if depillaring is conducted below district board
roads.
• For depillaring with caving method, dewatering of
old water logged working, if any, either by putting
in-seam pumps or by burn side safety boring
machine
• Plans to be updated showing all features
• Adjacent mines, likely to be affected, are informed
• Adequate number of supervisory staffs and
workers having experience in depillaring have to
be appointed.
• There shall be adequate stocks of supports, fire
fighting equipment, stone dust, lime, bricks etc
• Completion of preparatory stopping all around
the panel, if development has not been done in
panel system
• Adequate provision of pumping arrangement
• Establishment of ventilation network
• Advance supporting up to 2 pillars, ahead of the
pillar under extraction, or 60m whichever is more
in all direction as per the approved systematic
support rule.
An exercise on planning of a Bord
and Pillar depillaring panel
Statement
• A coal seam 4m thick, dipping at 1 in 10, occurring
at a depth of 130m have been developed on Bord
and Pillar system along the floor of the seam with
4.5m wide galleries and 30m x 30m c/c pillar.
Describe the method of depillaring of the seam and
propose a suitable design for such a depillaring
panel. Assume your own conditions. Estimate the
production and productivity from the panel.
1. Statement of Basic Assumptions
We assume that there is no surface structure to
be protected, it is proposed to depillar the
seam by caving method with the help of LHD
as loading machine and a combination of
chain conveyor and rope haulage as
district/panel transport.
• 2. State of the Principle
– The layout of the depillaring panel with caving has
been shown in the enclosed drawing.
– After completing all the preparatory arrangement,
such as construction of preparatory stoppings,
grant of permission from DGMS, advance
supporting as per SSR up to 2 pillars etc,
depillaring operation is started from the dip most
pillar in the panel.
– It will progress towards the rise side following
diagonal line of extraction as shown in the
drawing:
3. Splitting operation
– Each pillar is divided into two equal parts by
driving a level split of 4.5 m width and 3 m height,
leaving 1m coal at the roof.
– The splitting operation is restricted up to 2 pillars
or 60m, whichever is less, ahead of the pillar
under extraction.
– However, when the pillar extraction is about to
complete, splitting operation can be extended up
to 4 pillars or 120m from the first pillar to be
extracted.
Extraction of the stook
• After the pillar is splitted, each stook is
extracted by driving a dip slice of 4.5m
width and 3m height, leaving 1m coal at
the roof.
• A rib of coal about 1.5m wide is left in
between two consecutive slices which is
judiciously reduced as much as possible
during retreat.
• The total area of exposure under a slice is
restricted up to 150m2 or the limit specified by
DGMS in the permission letter.
• Only one slice in any one pillar is under
extraction at any point of time. When the slice
is completed, the 1m roof coal is blasted
down in stages during retreat from the slice.
• The splits and slices are supported during
advancing as per S.S.R. once a slice is
completely extracted, the supports from that
slice are completely withdrawn with the help
of chain sylvestor prop withdrawer, and the
roof is allowed to cave.
• A new slice is then started in the similar
manner after setting out goaf edge
supports.
Sequence of operation
The sequence of operations during drivage of
splits and slices are as follows:
– coal winning is affected by drilling 36mm
diameter holes of 1.5m length on parallel cut
pattern using hand held electric coal drill
machine.
– The face is blasted off the solid using P3 or P5
type explosives in conjunction with electric delay
detonators.
– clearance of fumes, face dressing and erection
of temporary supports.
– Loading and transport
• The blasted coal from the face is loaded by
LHD which discharges it on to LDCC laid along
the level split galleries.
• These conveyors discharge the coal onto
MDCC installed along dip-rise gallery.
• Finally, coal is loaded on to 1t coal tubs at the
loading point through a short length bridge
conveyor for onward transport to pit
bottom/surface through a series of endless and
direct rope haulages.
– Support
•All the working slices, original and split
galleries, junctions, and goaf edges
upto 2 pillars ahead of the pillar under
extraction are to be supported as per
SSR approved by DGMS.
•The ideal SSR shall be as follows:
Systematic support rule