Professional Documents
Culture Documents
(orBlastholeStoping)
Introduction
The stope is often very large with the largest dimension in the
vertical direction. The method only applies to vertical or steeply
inclined ore bodies.
To prevent the collapse of the hanging wall, large ore bodies are
divided into 2 or more stopes. Pillars are left between the stopes to
ensure the stability of the hanging wall. These pillars could be
horizontal or vertical.
1
Main levels are driven at pre-determined places and between these,
sublevels are driven. The ore is attacked from both main levels and
sublevels.
The ore is drilled and blasted from the sublevel and main level
drifts. Large pieces of ore fall into the empty stope and transported
from the bottom of the stope to the loading stations.
Applications
Developments
Production
2
1) The traditional and conventional method called Ring
Drilling. The method uses long hole extension rods to
achieve the required length.
These rods are normally 1.2 – 1.8 m (4 – 6 ft) long. The bit
diameter is approximately 5 cm. The hole length varies but it
cannot usually exceed 24m. Longer holes are possible but due to
the increased risk of deflection, they are not usually applied.
3
In sublevel stoping, drilling can be done independently of the
other operations. Large sections of the ore can be drilled and
left in place for blasting later. Machine utilization factor is
therefore high and hence the method can afford to use highly
specialized andexpensive machines. These machines allow
controlled and accurate hole alignment.
Mineral Transport
i) The ore may be loaded through chutes and directly into the
cars.
ii) Slushers may be used to draw the ore from the draw points
and load it into mine cars. This system solves the problem of
boulders.
iii) Overhead loaders can be used to load the ore from the draw
point into mine cars. LHD loaders are used in practice in
many large mines that have a trackless transport design.
4
Conclusions
5
- A thorough knowledge of the geology of the area. This is
important when designing the stope. Also important when
mining. It is enhanced by concentration.
- Good knowledge of ore boundaries
- Careful hole alignment control specially in parallel system
6
Advanced sublevel Stoping
Stope design
2) Stope height
7
Factors affecting the decision are
8
- Orientation with the main transport level for optimum
loader maneuverability and ground stability at
intersections.
Also from safety point of view, it is essential that these are kept
stable and safe since the presence of workers is more in here than
anywhere else.
9
Undercutting
Undercut should not be more than a few (2-4) steps in front of the
blasting on the sublevels (for back stability).
Production drilling
10
- Electro-hydraulic rotary-percussive drills
11