Professional Documents
Culture Documents
MATERIAL REQUIREMENT
PLANNING (MRP I & MRP II)
Wheeled Coach
Largest manufacturer of
ambulances in the world
International competitor
12 major ambulance designs
18,000 different inventory items
6,000 manufactured parts
12,000 purchased parts
Wheeled Coach
Four Key Tasks
Material plan must meet both the
requirements of the master schedule
and the capabilities of the production
facility
Plan must be executed as designed
Minimize inventory investment
Maintain excellent record integrity
Management Engineering
Return on Aggregate Design
investment production completion
Capital plan
Change
production
Master production plan?
schedule
No Is capacity Is execution
Realistic? plan being meeting the
met? plan?
Yes
Execute capacity
plans
Execute
material plans
MPS Examples
For Nancy’s Specialty Foods
Lead Times
The time required to purchase, produce, or assemble an item
For production – the sum of the order, wait, move, setup, store,
and run times
For purchased items – the time between the recognition of a need
and the availability of the item for production
Amp-booster
2 weeks
E
2 weeks 1 week
G C
3 weeks
F
1 week
D
| | | | | | | |
1 2 3 4 5 6 7 8
Time in weeks
MRP by period
BOM Master report
production schedule
MRP by date
report
Lead times
(Item master file) Planned order
report
Inventory data
Purchase advice
Material
requirement
planning programs
(computer and
software) Exception reports
Purchasing data
Order early or late or
not needed
Benefits of MRP
1. Reduction in work-in-progress.
2. Priority benefits.
3. Effective utilization of capacity.
4. Improved customer service.
5. Reduction in lead time.
6. Reduction in past due orders.
7. Increased productivity.
8. Increased inventory turn over.
Industrial Engineering and Management, BME III/I
By: Khem Gyanwali, Thapathali Campus, IOE,TU
17
3. Benefits and limitations
Limitations of MRP
1. Incorrectness in suppliers lead time or in
manufacturing lead time causes incorrectness in MRP
calculations.
2. Highly computational intensive approach of MRP
causes overdependence on MRP outputs. Any
inaccuracy causes failure of MRP to a large extent.
3. The data used in MRP system should be reliable.
Unreliable inventory data can cause a failure of MRP
system.
4. Bill of material and inventory status should be
computerized.
5. The product structure must be assembly oriented.
Week
5 6 7 8
A. Units (lead time 1 week) 100
Labor: 10 hours each 1,000
Machine: 2 hours each 200
Payable: $0 each 0
B. Units (lead time 2 weeks,
2 each required) 200
Labor: 10 hours each 2,000
Machine: 2 hours each 400
Payable: Raw material at $5 each 1,000
C. Units (lead time 4 weeks,
3 each required) 300
Labor: 2 hours each 600
Machine: 1 hour each 300
Payable: Raw material at $10 each 3,000
Elements of JIT
1. Eliminating waste.
2. Continuous improvement.
3. People involvement and employee
empowerment.
4. Total Quality Management.