WORKFLOW FOR APMT STAIRS INSTALLATION

ACTION NARRATION RESPONSIBILITY TIMELINE COMMENTS


 Emptying and With the acceptance of Total / APMT 30th August – 8th APMT will be charged
airing of the 3 APMT, the white tank 1 September, 2023 N1.00 for whatever
black tanks will be at the lowest by 1st volume is consumed from
September 2023 to the black tanks.
enable pumping of
products from the black
tanks.
 Mobilization of The contractors will be IPME - Contractor / APMT 4th -8th September, 2023 APMT requires all the
Contractors to delivering their contractors to undergo
Site equipment to APMT site. their Safety Induction.
APMT will provide a safe The health certificate will
place for the contractors be required of all
to keep their equipment contractors coming to
and materials work at APMT
 Work Permits NPA and APMT work APMT 30th August – 8th
permits need to be gotten September, 2023
as the fabrication will
include hot work.
 Fabrication Welding and construction Contractors 11th – 29th September,
of the platforms, stairway, 2023
and walkways
 Installation Putting the stairway and Contractors 2nd – 6th October, 2023
platform on the tanks
 Calibration /tank The black tanks will be APMT/ SGS 9th – 13th October, 2023 After calibration of the
integrity test recalibrated, and other black tanks and product is
integrity tests will be available for APMT’s
conducted before product consumption. The white
is discharged into it tank 2 and 3 should be
washed and recalibrated.
SGS will advice on how
white tank 1 will be
cleaned and calibrated.