Professional Documents
Culture Documents
GENERAL
1. CLIMATIC CONDITIONS
2. STANDARDS
All details of the equipments, materials and installations standard shall comply
with this specification and the current standards and regulations as described in
Volume 11.
Where the materials or equipment offered comply with other standards, the
Contractor shall demonstrate they meet the requirements of this specification
and details shall be provided to be approval
3. SUBMISSION
a. All submissions must be made early enough in the Contract to enable the
Engineer to fully check such item prior to ordering. Generally, a period of at
least two months before any equipment requires to be ordered to meet the
main contractor’s program.
b. No claims for extensions of time or additional costs shall be entertained as
a result of the contractor’s failure to make his submissions in adequate
time.
c. If, in the opinion of the Engineer, the Contractors failure to make his
submissions in adequate time may result in a delay in the completion of the
whole project, then the Engineer shall have the authority to instruct the
Contractor to order materials and/or equipment of a type from a source
approved and nominated by the Engineer at no increase to the Contract
sum.
The cost of all such orders, including freight, shipping, insurance, handling and
administrative charges shall be deducted from the contract sum or recovered in
any other method at the discretion of the Employer.
4. EQUIPMENT
This item shall include all information necessary for the engineer to
ascertain the equipment comply with this specification and drawings data
and sales catalogue of a general nature will not be accepted.
h Before ordering equipment the contractor shall provide the engineer with
full details of the weights and electrical characteristics of the equipment for
purposes of determining floor loading , power consumption etc.
i Manufacturer test certificate shall be submitted.
a. The engineer shall be free to reject any plant, materials and workmanship
which not complying with the requirements of which are in any way
unsuitable and to order their removal and replacement, without additional
cost.
b. The engineer’s decision as to what constitutes compliance with
requirements and suitability shall be final and binding , the true intent and
meaning of the contract being that the whole of the contract works shall be
completed and acceptable by the E ngineer.
c. No rejected item shall be considered as a reason of a delay to meet the
completion date of the project
7. AS-FlTTED DRAWINGS
drawings together with one transparent negative of each drawing for the
whole installation. As fitted drawings shall show the complete installation
including all, piping. equipment, electrical wiring , maintenance accesses,
maintenance facilities and all necessary details for the proper maintenance
and operation of the system.
b. The exact scope and details of the manual shall be as describe in the
relevant section of the specification and agreed by the engineer.
9. BUILDERS WORK
a. All foundations ,footings, pits, gases, structural ducts, trenches holes and
other civil work required for the installation will be provided by the main
contractor.
The contractor shall supply ,full particulars dimensions of the together with
the weights of all equipment.
b. The contractor shall supply detailed working drawings, mark out on the site,
provide foundation embedding material and give all necessary details for all
the builders work. The contractor shall monitor that the work is carried out
in accordance with his requirement and he will be responsible for the cost
of all such work and material due to lack of supervision, in correct
submitted information or details and late submission of working drawings.
c. The contractor shall provide all sleeves and inserts required before the
floors and walls are built, sleeves shall be provided for all mechanical
piping passing through floor slabs and wall constructions, unless otherwise
indicated sleeves shall be of the same materials as the pipes which passing
through.
d. Where any work pierces water proofing including water proof concrete the
method of installation shall have the approval of the engineer. The
contractor shall provided all necessary sleeves ,caulking and flashing
required to make opening absolutely water tight.
a. The contractor shall liaise with the main contractor and other contractors
and tradesmen who will be carrying out other services work on the site prior
to the commencement of actual installations, due to ensure that the work of
all trades are occupy for the same pipe and duct space in ceiling void.
All contractor shall be aware to leave clear access for future provision of
these services within builders work shafts, plants, plant rooms and false
ceiling. etc.
b.No claims shall be entertained for noncompliance with this clause.
If the test results show that the plant and equipment is not functioning in a
satisfactory manner or providing the requirements due to incorrectness of faulty
work by the contractor and if this be the case, the contractor shall, when called
upon, carry out at his own expense such alterations, replacements and
adjustments which may be required , which is acceptable by the engineers.
The contractor shall provide removable guards or railings for moving or rotating
parts.
14. LABELS
The contractor shall provide labels for all equipment, fuses, terminals, switches,
handles, keys, instruments, gauges, valves, circuit and piping diagrams,
indicators and wherever their provision will facilitates the proper operation and
maintenance of the system.
All lettering will be English with a translation into Indonesian adjacent to it.
contractor and without prejudice to such other rights as the employer may
have under the contract.
d. Other requirement shall be as described in the relevant section of the
specification.
At the time of handover of the contract works after the period of maintenance
the whole installation shall be in “ as new” condition.
The contractor shall , during the course of the contract , protect all plant and
equipment and shall restore I repaint I repair as necessary before completion of
the contract.
18. CONTRACTOR
a. What is meant by the Contractor in this specification is the implementing
agency that has been selected and been awarded a work contract for the
supply and installation of air conditioning installation of major equipment
until completion.
b. Contractor must learn and understand all laws and regulations,
general requirements along with their supplements, requirements
set up by the manufacturers manufacturing the air conditioning units,
tender document books, bundle of drawings as well as written instructions
that have been issued.
c. Contractor may request an explanation to the Board of Directors /
PMSC / Planners or a designated party when in its opinion on the tender
documents, drawings or other matters there have been things that need
clarifications.
d. Contractor shall study and also examine the implementation of the work
carried out by any other Contractors who also participate in working on the
project if the work of others can affect the smoothness of the Contractor ‟s
work. Whenever an interruption occurs, then the Contractor shall act
upon the suggestions for improvement for all parties.
must be done upon receipt by the contractor the first warning issued by the
Directors / Construction Management / Planners. The Contractor shall repair
any damages caused by the execution of this job.
If the Contractor neglects this warning or the repair work they have done is
not perfect or not as expected, the Construction Management is entitled
to ask someone else to repair or replace at the contractor‟s account.
After the maintenance period elapses and any damage or deficiency has
been remedied or repaired properly by the contractor, then the work may be
handed over for the second time.
23. PERMITS
a. All permits and requirements necessary for carrying out this installation
shall be done by the Contractor and the Contractor shall bear all the
associated costs.
b. All inspection, testing and other particulars along with their official
statements which may be required for the implementation of this
installation shall be conducted by the contractor and the costs related
thereto shall be borne by the Contractor.
c. The Contractor shall be responsible for the use of patented tools, the
possibility of compensation claims and costs required for this. The
Contractor shall submit a written statement regarding this.
A. SCOPE OF WORK
1. EXTENT OF WORK.
The work described in this specification covers, the supply, installation, testing,
commissioning and maintenance of mechanical ventilation and air conditioning
installation of the building in accordance with this specification and associated
drawings, and without abrogating the more extensive described elsewhere in
the specification and drawing includes the following:
a. Supply and installation of all equipment Split air conditioner (split wall, free
standing), fans etc as shown on the drawing.
b. Supply and installation of ventilation air duct, complete with splitter damper,
support, hanger and other necessary material to get proper installation.
c. Supply and installation of intake I fresh air and exhaust grille, complete
with, support, hanger, including frame and all auxiliaries.
d. Supply and installation anti vibration mounting for all equipment.
e. Supply and installation of all access manhole to ceiling space where
required and platform around lU above ceiling for maintenance purposes.
f. Supply and installation of Exhaust Air Fan, Toilet Exhaust and fan units,
following ducting systems and other equipment with the capacity, type and
amount of equipment in accordance with the schedule.
g. The procurement and installation of flue systems following the air
outside and inside insulation, damper, dampers, diffuser / grille, hanger
and other fittings.
h. Painting and labeling of duct and pipe work and equipment as necessary.
i. The carrying out of testing, adjusting, balancing and commissioning
of all equipment and air conditioning systems, including carrying out
measurements and make a report.
j. Training of the employers staff for proper operation of the entire system.
k Provide operation and maintenance guide book.
2. IMPLEMENTATION REQUIREMENTS
a. Installation that is stated in this specification shall be accomplished in
accordance with the applicable laws and regulations currently in force in
Indonesia and do not conflict with the provisions of the Work Safety Service
Agency.
b. All the terms of acceptance of materials, equipment, methods of
installation, the quality of work and others for this installation system shall
PT. PRAPANCA ENGINEERING TS - 10
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
4. REFRIGERANT PIPE
a. Refrigerant pipes should all be carefully done and as good as possible. All
parts of these pipes must be clean, dry and free from dust and dirt.
Copper pipe of type L or K that is "dehydrated" & "sealed" should be used.
b. Connection
Pipe of "hard drawn tubing" type should be connected with the mediation
of "wrought copper fittings" or "non purous brass fittings." It is
recommended that silver solder with the blowing of mupia gas such as dry
Nitrogen gas into a pipe that is being connected to avoid the formation of
oxide scale in the pipes.
Soft solder such as "50-50" shall not be used. Solder of "95-95" can be
used except in the pipe hot gas "discharge" pipes.
Pipes of "soft drawn tubing" type can be connected with solder, or other
flame that is suitable for refrigerant pipe. When "precharged refrigerant lines"
are provided by the manufacturer, manufacturer's instructions should be
seriously and truly observed.
If there is excess of "precharged" pipes, a coil should be established
and supported on a flat field
c. Installation
Refrigerant piping should be well supported to prevent from flexing.
Vibration dampers should be installed to prevent the forwarding of vibration to
the building. Where applicable, vibration dampers should be mounted on the
pipe.
Refrigerant pipe planned and installed in the field shall be implemented
in accordance with the "ASHRAE GUIDE BOOK" or the
manufacturer's recommendation. The height difference and distance
between the condensing unit and the evaporator blower unit should still
meet the requirements of the manufacturer. After the pipe installation work
is complete then the entire circuit must be tested against leakage.
Pipe Insulation
- Suction pipes / discharge line refrigerant must be insulated with
thermal insulation such as armaflex, superlon or similar.
PIPE DIAMETER 16-25 mm 25-50 mm
Isolator Thickness 20 mm 25 mm
- On the roof insulation should be covered with a layer of moisture-
resistant metal jacket type. Pipes must be supported at every 2 meters
and at every turn and branching.
5. DRAIN PIPING
The Contractor shall install drainage pipes (drain) of the AIR
CONDITIONING machines up the closest place of disposal in the
hidden and unobtrusive channels.
a. Material
For waste water (drain) the PVC pipe shall be used, of AW type complete
with the thermal insulation.
b. Equipment
Drain condensation pipes must be equipped with a control basin, swan neck
and other equipment that are needed. An insulation layer up to the
length of 3 meters or up to areas where condensation does not occur the
outer part of the pipe section.
c. Wall penetration
Whenever penetrating walls, floor plate etc., these pipes shall be given
the vibration damping layer and protected with a larger size pipe.
d. With the piercing work taking place for air conditioning installation purposes,
it is the responsibility of contractor to carry out closure and the putting back of
the work to normal and guaranteed no leaks occur.
There shall not be any pipes supported or hung on the other pipes.
All hanger / leverage for isolated pipes must not penetrate the insulation
material.
All the pipes in the room shall remain to be supported with the leverage
that prevent forwarding of vibration (vibration eliminating, hangers, rubber in
shear).
All hangers, pipe supports shall have their materials made of steel, can
be adjusted for height (adjustable), originally painted with anti-rust paint and
finished with black color.
The distance between the support may not exceed the size below without
the approval of the project owner / Supervisor / Planner.
Size of Pipe Maximum Support Distance (M)
20 25 – 2,00
32 150
– 2,40
150 above 2,50
● Vertical riser that goes through the floor, on the floor that is
penetrated shall be supported by the type of "collar" or "clamp" in
which the pipes are clipped at an "angle" firmly. Around the riser pipe
that there is still a gap / hole shall be closed tightly with a rubber seal.
It is not justifiable to close such cracks with cast concrete.
● When the pipe and clamp are different in terms of their material, a
gasket shall be installed between the pipe and the clamp.
All the pipes that are supported (hung) / they shall be supported in
such a way so that they will not cause any pressure on pump isolation.
Protective metal plate at least a minimum of BjLS 100 with the length of
150 mm (6 ") on both sides of the clamp saddle or roller.
7. WORK BY OTHERS
Concrete inertia bases for pumps including steel frame works and
PT. PRAPANCA ENGINEERING TS - 14
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
8. REGULATIONS
Not with standing anything to the contrary contained herein pertaining to this
installation , it shall be the contractors responsibility to ensure all the works is in
strict accordance with following statutory obligations , regulations and
specifications together with any amendments made thereto.
a. Air conditioning standard as ASHRAE , ARI , SMACNA
b. The regulations for electrical installation published by the institution of
electrical engineers, London
1. SCOPE.
The scope of this section set out the requirement of the ac units sets for Office
building , Warehouse, Utility and etc.
2. GENERAL
a. This section specifies to furnish on site assembled AC units of the type size
and capacity as described attached. Unit fan and coil performance shall be
certified in accordance with ARI standard 430 -66 for fans and 410 —72 for
coils.
b. All units and accessories shall be supplied by manufacturers experienced
in the design and construction of similar equipment and who have made Air
Cooled Packaged units.
c. Condensing unit shall be suitable for operate at outdoor condition.
d. Before ordering the equipment ,The contractor shall furnish the following
information for each unit to the consultant for approval.
+ Complete manufacturers printed catalog.
+ Main dimension and weight.
+ Technical details ( cooling capacity ,Fans performance. curve sound
power level ,vibration mounting ,etc)
+ Spare parts.
e. All units and accessories shall be of minimum vibration and noise level
during operation ,should these be excessive and not within normal
acceptable standard ,the contractor shall be responsible for provision of
adequate vibration isolation and sound attenuation as recommended and
required by the consultant.
f. All unit and accessories shall be of the highest commercial standard and
shall be designed , constructed, rated , and tested in accordance with an
approved authority.
3. MATERIALS.
a. Unless specially state otherwise ,alI units shall be assembled on site, Type
C. AIR DUCT
1. SCOPE
The scope this section sets out the type, material construction, dampers
insulation ,accessories diffuser, grilles and installation of the ducting to be used
on this project and as indicated on the accompanying drawings.
3. GENERAL.
a. Unless specifically stated otherwise , the tern “ air duct when used in a
general context shall mean all duct work , fitting , dampers, supports,
gauges and all other component and accessories required for the complete
installation of the system as shown on the accompanying drawings.
b. All ductwork shall be manufactured as far as practicable to site dimensions
taken by the sub contractor, where site dimensions cannot be taken in
advance, dimensions shall taken from architectural / structural detail
dimensioned drawings and the sub contractor shall make suitable
provisions to accommodate any discrepancies that may occur between the
drawings and the site dimensions.
c. Within six months of being awarded the syb contractor ,or at least two
month prior to commencing work on site , whichever is the sooner, the
contractor shall submit to the consultant for approval complete shops
drawings for all ductwork system included in the contract.
d. Shop drawing shall included plant, sections, elevations, schematic and
detail of all systems and shall show locations and details of all dampers ,
splitters, hangers, supports, supply, return ,intake and exhaust air fittings,
joints flexible connections, test points, insulation, linings, kitchen hoods,
etc.
e. All ductwork and materials including linings, adhesives, flexible connection
gaskets, sealants fiberglass boards, etc shall satisfy in respect of
resistance to penetration of fire and spread of flame and smoke.
4. MATERIALS
a. Generally, all ductwork shall be of hot dipped galvanized steel sheet to SII
or BJLS (Baja Lapis Seng).
b. All detail of cross joints, longitudinal joints , take - offs bends, transitions
and shall be as shown on the drawings.
c. The dimension shown on the accompanying drawing in this specification
are clear internal size.
Where internal insulation is used , the thickness of the insulation must
be added to the dimensions shown on the drawing to determine the actual
PT. PRAPANCA ENGINEERING TS - 18
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
duct size.
d. The thickness of galvanized metal sheet shall be accordance with the
following schedule:
Longest – side Gauge
Up to 300 mm BJLS 5O
325 to 750 mm BJLS 6O
775 to 1350mm BJLS 80
1375 to 2100mm BJLS 100
2125 to above BJLS 120
e. Jointing for flanged joints shall be formed from a rubber gasket or other
approved materials to thickness not less than 4 mm.
f. Test point for measuring air flow shall be provided:
- For all fans (in the straightest section of duct near to the outlet).
- For cooling coils (both before and after the coil).
- At other position indicated on the contract drawing.
Test hole shall be 50 mm diameter and fitted with an effective removable
cover.
2. GENERAL
a. Drawings and specifications only show the length of each chimney
size, equipment within the ducting and arrangement of air flue system
path. If there are deviations from the contract drawings that were deemed
appropriate by the contractor, then details of such deviation and the
reasons shall be submitted in writing to the Engineer /Construction
Management/ Planner for approval.
b. Deviations that have been approved shall be undertaken by the Contractor
at no additional cost except when it causes changes in design or
requirement.
4. CONSTRUCTION
a. Construction requirements for the implementation of air chimney
installation:
● This installation system uses a low speed Ductwork. All duct
installation should be able to withstand speeds up to 2,000 ft per
minute and static pressure up to 2.5 to 3.5 inches of water.
● The contractor shall test the installation of ducting for leaks that
may occur.
● All of the connections that occur must be as tightly as possible
(airtight) if necessary a seal shall be given.
● Changes in the size of the duct must be approved in writing by the
Engineer/ Construction Management/ Planners.
b. Ducting system that is not enclosed by walls or the ceiling (outside the
building, inside coridor in a room without a ceiling), must be made of
alluminium sheet given good reinforcement (bracing) and supported /
hung on a solid building construction The thickness of duct is as follows
(for zinc Bjls):
THE BIGGEST SIZE PLATE TABLE
Up to 24 inches 20 US Gauge
24 inches to 48 inches 18 US Gauge
28 inches and above 18 US Gauge
PT. PRAPANCA ENGINEERING TS - 20
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
c. Ducting system shall be made of "Zinc Coated Steel" and shall provided
with good reinforcement (bracing) and supported / hung on a sturdy
construction. The thickness of the duct is as follows (for Zinc Bjls):
SIZE OF DUCT BJLS
12" Bjls 60
13" up to 30" Bjls 70
31" up to 54" Bjls 80
54" up to 84" Bjls 100
84" and above Bjls 100
5. TURNS
All of the turns (elbow) should be made in accordance with their drawings
and specifications. All the turns/elbows in the supply duct should be
equipped with steering angles (vanes) in accordance with drawing
specifications.
All the turns / elbows shall be of "long radius elbow" type except
where circumstances do not allow. Sharp turns / elbows (90) should be
given the steering angles (vanes) in the form of appropriate aerodynamic
profile. Rounded corner with the inner radius less than the side of the duct,
the turns / elbows should be given the thin steering angles (single thickness
vanes).
Materials and installation methods for all flexible connections between ductwork
systems and equipment shall be of lead impregnated vinyl.
a. All air supply, grille, diffuser, return and exhaust fittings shall be provided of
the types shown on the contract drawings.
b. Unless otherwise stated or indicated on the document drawings, all supply
fittings shall have an opposable volume control device, the vanes or which
shall be spring — loaded or otherwise arranged so that they remain
permanently in their set position without vibration or noise ,where shown on
the contract drawings, return and exhaust air fittings shall also have
opposed blade dampers.
c. All grille, register and diffuser shall be capable of being removed easily
2. INSTALLATION
F. VENTILATING FAN
1. SCOPE.
This section describes the need for tools, equipment and installation of mechanical
ventilation system for this project:
- Procurement and installation and testing of exhaust / intake fan, and
ducting installation.
- Exhaust / Intake Fan for engine room, Toilets and Warehouse. -
Exhaust / Intake Fan for Pump room, STP room and others.
- Exhaust / Intake Fan for Transformer room, etc.
- To provide fresh air intake fan for office space as noted on the drawing.
- To provide exhaust air fan from toilet, storage, etc as noted on the
drawing.
2 GENERAL
The following is in general terms concerning ventilation and ventilator,
for technical specifications to be followed which is special is in accordance
with the schedule indicated on the machine schedule drawings.
Ventilation equipment shall be installed in accordance with the ones shown in
the drawings and / or the requirements below. The entire installation of
mechanical ventilation should comply with local requirements, ordinances and
/ or regulations that apply.
Contractor shall provide and install electric fan in accordance with drawings
and specifications. All fans are of the axial type fan, propeller,
centrifugal or determined in accordance with dynamic specifications
and tested by the manufacturer. Once installed fan should not create
excessive noise. All fans shall be mounted with rubber around them
(vibration dampening) before installation.
Contractor is required to file for approval prior to the consultant about the
product, type and specifications of equipment to be used in this project.
All fans must be approved for use by the Engineer /Construction Management
/ Planners before the installation work can be done.
PT. PRAPANCA ENGINEERING TS - 25
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
a. The contractor shall select all fan as mentioned and scheduled on the
drawing.
b. Maximum fan/motor rotation is 1500 rpm for propeller fan and 1000 rpm
for axial fan.
c. Fresh air supply for office space shall be provided with silencer at
discharge side.
d. Exhaust from toilet which used main / central exhaust fan at roof level is
axial fan and shall be provided with silencer at suction side.
e. The silencer shall reduce fans noise at 20 DB.
f. Fan shall be installed with used of anti vibration mounting of spring or
rubber in shear.
g. Connection to air duct shall used flexible like canvas or similar material to
protect transferring of fan vibration through the duct.
3. AXIAL FAN
a. Fan housing are to be round type casing made of hot dipped galvanized
steel. b. bearings
- fans and motors shall be provided with grease packed close tolerance
ball bearing, designed for quiet operation and calculated life time of
100.000 hours under the particular duty of the fan
- Bearing shall be installed in grease relief housings with dust seals
,grease nipples shall be provided in accessible positions and piped to
bearing housing to allow greasing of bearings without removing any
components.
b. Motors
Motors shall have a kW rating not less than that specified on the
schedule. Motor rating are nominated as a basis for tendering only the
shall be checked before ordering to ensure that they have a minimum of
120 % of the power required by the fan for the installed duty.
Ensure that motors mounted in the fan airway have frame sizes an
shapes consistent with the manufacturer’s air quantity and noise level
data.
Motors shall comply with the following specifications:
- Totally enclosed type for direct driven type
- Winding insulation class E.
- Horizontally mounted.
c. Impellers.
Impellers have aerofoil blades and shall be statically and dynamically
balanced .certification of balance shall be submitted.
Impeller blade pitch shall be readily and accurately adjustable of blade
pitch on site will not affect the static or dynamic balance.
4. PROPELLER FAN
5. EXHAUST FAN
a. All the fans should have a pilot light and on/off switch in the location /
panel shown in the drawings and can be monitored and / or can be
remotely controlled from the central control room in the available control
panel.
b. Fan with power 1 Hp or smaller can be “phased” as a "single phase".
c. In principle, the exhaust fan to be installed is an exhaust fan of the
type commonly used, where: Capacity : According to the plan drawings.
Type : According to the plan drawings Static Pressure : According to the
plan drawings. The exhaust fans to be installed are of the types commonly
used, where : Exhaust fans shall have a damper that automatically operate
driven by motor or in other words if the exhaust fans are turned off the
damper must be be to close and the around.
1. GENERAL
This section covers the general requirement for electrical work to be installed
under this specification.
The contractor shall supply and install all electric wiring , control panel and level
control etc, for the complete, safe and satisfactory operation of the plant
covered by the specification.
The entire electrical installation shall be in accordance with the regulation and
requirement of all relevant authorities having jurisdiction over the installation.
The requirement of I. E. E wiring regulation (l 5th Edition ) shall be taken as the
minimum standard for this installation.
3. ELECTRICITY SUPPLY
The electricity supply will be 220 V/I phase/50 Hz and 380 V/3 phase/50 Hz,4
wire. All equipment shall be designed to operate with —+ 19 % voltage
tolerance without a loss of rated output.
The contractor shall be responsible for extending the supply from the above
mentioned isolator/distribution board and shall include all electrical works
including control panels, starter, conduits and wiring etc. necessary for the
satisfactory operation of their equipment offered.
6. MATERIALS
All materials used must be of top quality, made in Germany, USA, or
equivalent unless otherwise stated separately.
The executor of the work should coordinate with other parties as far as
possible to obtain uniform equipment equipment from the same brand for all the
work in this project.
7. EQUIPMENT, ETC
a. Each unit of equipment shall be equipped with a safety system
separately.
b. For each phase the panel should be given an indicator light or measuring
tools.
c. All AC power panels use a thick plate of minimum of 2 mm and
should be given an anti-rust paint layer.
d. All the existing panels, switches, indicators, measuring tools and others
should be provided with a clear name and is should not easily be
damaged.
e. All measuring tools that are installed should be from the most appropriate
and accurate working area 2%.
8. RESERVES FUSES
For each panel should be provided as many as spare fuses which are
available and stored in a special place and given a badge.
9. CABLE SPLICING
All cable connections should be made in accordance with the existing
requirements of which among others are:
a. Connection of copper wire connector should use the appropriate
copper and coated with white lead.
PT. PRAPANCA ENGINEERING TS - 30
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
10. CABLES
All wiring shall be carried using PVC insulated stranded single core cupper
conductor cable to B.S. 6004, 6231, 5345 or 6500 as appropriate.
The conductor shall confirm loads and sizes of cables prior to placing orders.
All main conductors (including neutral if needed, in this project using
autotransformer and no need neutral for the Main building and office building)
shall be colored in accordance to PUlL for their length , and the phase to which
they are connected All control wiring shall be colored coded using spiral stripe
tracer on base color.
All PVC insulated wiring including earth wires shall be enclosed in conduit or
approved trucking.
To eliminate the possibility of damage to cable due to thermal expansions
allowance for movement shall be made by the introduction of bend or set in
each cable / core adjacent to the terminal.
Cable shall , at all times , be handled with care and every effort made to avoid
damage .they shall always be pulled from top of the drums. Care shall be
exercised when breaking the rotation of the drums and under no circumstances
shall babble be dragged over loose earth of concrete .Approved type of cable
rollers shall be used,
After installation, all cables shall be tested for continuity and insulation
resistance and record of test submitted to the engineer for approval single core
c able shaft be pullet into conduit only after the whole network ,or a complete
section of conduit has been installed , tested for continuity and swabbed
through.
The contractor will be deemed to have allowed in his tender sum for applying
sufficient lengths of cables of each type and size to complete the installation ,
including the due allowances for additional lengths for cutting and waste.
Unless specifically instructed by the engineer to the contrary, the size of cable
employed for various type of wiring, shall not less than the following list:
- power circuits 2,5 mm 2
- Earth circuits 2,5 mm 2
- control circuits 1,5 mm 2
PT. PRAPANCA ENGINEERING TS - 31
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
11. STARTER
• RelayFacility : 0-120 Hz
• Analog Input : 0 -10 V, 0-20 mA, 4-20 mA,20-
4 mA, 20-0 mA
• Digital Input : 0 24 V
Executor / Contractor shall perform all the testing, test and balancing
equipment of air conditioning system installation, witnessed by the
Supervisory Consultant / Planners / Project Owners and other parties whose
presence should be needed.
Before carrying out measurements and TAB (Testing, Adjusting & Balancing),
the Contractor shall propose methods of work Pressure Test &
Commissioning, quantities to be measured and measuring tools that are
used, to Supervisory Consultant and the Planners Consultant and ask for
approval, no later than 2(two) weeks before the job is executed.
The entire cost of this work shall be borne by the Contractor and shall be
included in the bid.
temperature and pressure of water in and out and the water flow rate from
all AHU units and pumps.
b. Air Distribution System
Testing methods should be made to the leakage of overall
connections and ducting branches, ducting supply, return ducting,
ducting freshair and exhaust ducting.
For the smoke method the contractor must provide a generator / unit
for the method of smoke, according to the method of test and
measurement of ANSI / ASHRAE III-1988, SMACNA standards.
Testing should be done to leaks at the connection, temperature,
speed and amount of air flow in the branches of ducting, diffuser, grille,
test holes in the supply duct and fresh air ducts.
Balancing and adjusting all the existing damper to obtain the appropriate
price. Quantities to be measured and recorded include:
Temperature and RH of air in and out of cooling coil of all the AHU.
Temperature, RH and air flow on the main chimney (main duct) of air
supply and return as well as the branching and the fresh air intake.
Temperature, RH and air flow discharge at all outlets diffuser and grille.
c. Electrical
Measurement and test of the strength of currents and voltages, rpm
every phase of motor compressor units and the existing power-
management system. Comparison with the planned price or
manufacturer's data.
d. Temperature, RH and Room Noise Level
Measuring and testing of the temperature and humidity in the room
which are conditioned at several measuring points and the noise that
occurs in the room.
The precise method of carrying out the following test shall be agreed with the
engineer prior to commencement.
The following items shall be tested in the sequence indicated and a completed
report shall be by the contractor and submitted to the engineer for approval.
All materials that are to be supplied and installed by the Contractor shall be
brand new and such materials shall be suitable for installation in the tropics.
Materials must be of good quality products from the latest production. For
the materials mentioned below then the Owner must ensure that the goods
are good and new by mean so for showing the delivery of mail order from
the dealers / agents / factory.
Contractor must be willing to replace the material that is not approved due
to deviating from the specifications or other matters, where such
replacement is at no extra cost.
b. List of Materials
For all the materials offered, the Contractor must complete a list of materials
that mentions the brand, type, class complete with a brochure / catalog that
shall also be attached at the time of tender. The lists table of these materials
are preferred for the components in the form of goods produced in factories.
c. Reference to Brand / Product Factory
If in the technical specifications or on the drawing a number of particular brands
or quality class of the certain materials or components, especially for
materials that the level of quality / factory mentioned, if at a later date during
the course of the project it happens that the materials listed on the label
material cannot be acquired by the Contractor for a very strong reason
acceptable to Owners, Engineer, Construction Management, and
Planners then those brands that cannot be
available can be replaced by other types with a certain sanction to the
Contractor.
A. SCOPE OF WORK
1. EXTENT OF WORK
The work embraced by this specification covers the supply ,installation, testing ,
PT. PRAPANCA ENGINEERING TS - 35
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
a. Supply and installation of complete soil, waste and anti symphonize / vent
piping systems and floor drains as shown on the drawing.
b. Supply and installation of rain water piping, outlet, etc as shown on the
drawings.
c. Installation and connection of all the sanitary fixtures I fittings/ accessories
including various taps, traps and cleaning of the fixture and protection after
installation.
d. supply and installation of the complete domestic water distribution system
including pumps, motors, controls, fittings, pipe works, pressure switches,
water meters, water hammer arrestors, pressure reducing valve set etc,
and any accessories as indicated on the drawings.
e. Supply and installation of all electrical works , including cables, isolators,
starters for pump motors, contactors, indicating lamps, conduits, control
wiring and switch cubicles for the proper automatic operation of the pumps.
f. supply and installation of all manhole covers, gully pit covers and surface
channels, gratings etc, as shown on the drawings.
g. Painting of pipe work and equipment.
h. Testing and commissioning
i. Training of the employers staff for proper operation of the entire system.
Supply and the building in of all pipe sleeves , puddle flanges and equipment
holding down bolts, where required to be built in during construction The
contractor shall work in coordination with the main contractor.
Access hatches doors and panels as required in false ceiling, masonry riser,
masonry shaft, walls, roof spaces , plant rooms and at other places by the main
contractor and in accordance with his details to allow access for adjustment,
maintenance and cleaning.
All cutting ,patching ,framing up ,furring in, chasing and making good
associated with the building construction for the passage of duct work pipes,
conduits, and grilles, etc.
flashing of all roof penetrations for cables and pipes, over flashing by the
plumbing contractor.
Construction of all manholes, gully pits, surface channels, connect support etc.
2. REGULATIONS
Not with standing anything to the contrary contained herein pertaining to this
installation , it shall be the contractor responsibility to ensure all the works is in
strict accordance with the following statutory obligations, regulations and
specification together with any amendments made there made thereto.
a. The relevant British and Indonesia Standard and Codes of Practice for
Plumbing works.
d. Domestic water quality shall comply with the local regulation (issued by
Minister of Health No.01 I BIRHUKMAS /1/1975).
1. GENERAL
a. The contractor shall be responsible for the coordination and location of all
2. SCOPE OF W ORK
a. Time Frame
b. Material
The Contractor shall ensure all units of equipment imported are free of
defective materials, improver material and guarantee the quality or quality
of goods in accordance with objective of the specifications, and must refer to
the standards of ISO 14000 / 14001, Environmental Management System.
d. Design Drawings
The design drawings that are included in the scope of plumbing work in
the Tender Documents are the drawings with the drawing code number
PL. Contractor shall check the design against the possibility of errors /
discrepancies in terms of quantities and the diameter of the pipe installation
and others. The things above should be submitted in writing or in the form of
drawings during the pre-bid clarifications meeting . These design drawings
are not meant to refer to all the pipes, fittings, valves and fixtures in detail. All
the parts mentioned above, although not described or mentioned in the
specification should be adjusted and installed by the Contractor, if necessary,
in order to complete this installation and can work well in accordance with the
implementation of the fair.
e. Working drawings
Working drawings for all work must always be at the field (site). Including
changes or other proposals and so forth. As long as the implementation of
this installation is running, the Contractor shall provide the signs with the
pencil / red ink on the set of drawings for any amendments, deletions or
additions to the installation, Such working drawings must be made in a
number of 1 (one) set tracing paper and 3 (three) sets of blue print.
f. Images Implementation
The Contractor shall make a detailed installation drawing (shop drawings) to
be approved by the Engineer, also must submit the Implementation
Drawings (As Built Drawings), which includes floor plans, as-built installation,
installation detail. Details of equipment from all over the installations
drawn on tracing paper. Implementation of the installation must meet the
general requirements that apply and follow the Guidelines for Plumbing
Indonesia in 2000. As-built drawings shall be made in a number of 1 (one)
set of tracing paper and 3 (three) sets of blue print.
g. Examples of Goods
The Contractor shall submit samples of materials to be used in
the implementation, to the Construction Management or the brochures
of the equipment and wait for approval from the Construction Management
before the tools are installed.
When these materials are questionable in terms of their quality they will be
sent to the investigation office at the expense of the Contractor.
If it turns out that there are materials that have been declared not good / not
be used by the Construction Management, then the Contractor shall
haul the materials out of the field within 3 (three) days, and they shall have
been removed out of the site.
h. Implemention Personnel
All work must be performed well by the experienced / capable people in their
own field (Skilled Labour), in order to provide the best and neat work.
For the specific implementation, Contractor shall provide a statement which
proves that the craftsman-builders who carry out such work do have the
experience and skill.
i. Security
The contractor is responsible for preventing materials / equipment for
this installation from theft or damage. Materials / equipment that are lost or
damaged must be replaced by the Contractor at no additional cost.
j. Coordination
k. Permits
2)All inspection, testing for feasibility of use from the relevant Office and
others along with its official statement that may be needed for
the implementation of this installation should be done by the contractor
and the costs related thereto shall be borne by Contractor.
3)Contractor shall be responsible for the use of patented tools, the possibility
of claims for compensation and the costs needed for this. Contractor
shall submit a written statement regarding this.
l. Correlation Jobs
1)For all the existing excavation and piling work which shall be done by
other parties the Contractor shall provide the data, measurements
and drawings if any to the other parties who carry them out
2)All work on installing the machine holders shall be done by the Contractor.
Contractor shall provide the data, measurements, drawings and
equipment necessary to others who need them.
3)All pulling of electrical cables to the equipment panels shall be carried out
by other parties. The Contractor shall provide the data and
drawings needed to the other parties who carry out such work.
4)All pulling of water pipes including clean water pipes, sewage pipes that
are not listed in the drawings and specifications that shall be
conducted by the other parties, the Contractor shall coordinate and
provide the data, the size and the drawings to the other party who are
doing those work.
m. Sub Contractors
1)Where appropriate experts or specialized personnel who are supposed to
do the works are not able to carry out installation, adjustment,
testing and other then the Contractor may give up some other
installations to the Sub Contractor upon approval of the Construction
Management.
2)Contractor shall be fully responsible for all scope of work, either alone or
that have been implemented in the sub-contracted.
n. Field Supervisor
1)All work covered in this installation must be supervised by an experienced
staff. He is fully responsible for all installation work on this project.
2)Names, details of work experience, organizational structure should be
provided by the Field Supervisor Contractor to the
Construction Management to request approval.
3)If it turns out that in the opinion of the Construction Management,
consultants or authorities the designated Field Supervisor is ill-
equipped to lead the work the contractor must replace them with
others.
For this purpose a certificate shall be given stating the test results by
the party authorized to give the same.
o. Field Cleanup
1) Field that is used every day after work shall be cleaned by
Contractor. Contractor should contact the other parties to coordinate
the cleaning field
2) Immediately after the contract is completed, the Contractor shall
remove all remaining materials except the work and equipment that
are still needed for maintenance.
p. Operating Instructions
1)At the time of the handover for the first time the Contractor shall submit
drawings, data equipment operating instructions and methods
of maintenance of the machines installed under this Contract
in the Indonesian language.
2)These data must be submitted to the Owner of 3 (three) sets and the
Consultant 1 (one) set.
3)At the time of the first handover the following must be submitted :
Instruction Manual, Instalation Manual, Maintenance Guide,
Operating Instructions, Trouble Shooting Instruction and original
brochures.
a. Regulations / Requirements
Code of practice and other guidance relating to development regulations
which are in force in the Republic of Indonesia. During the execution of this
Contract to rigorously be adhered to. In general the following rules are
related to the article as follows:
1) Top Reservoir
Capacity : In accordance with the design drawings
- All pumps that are ON can with a sudden become OFF and the
alarm is ON, when the water level in the tank drops to a
threshold hidap LL until water is replenished again reaching the
threshold L.
6. MATERIAL
a. Sump Pit
ITEM TECHNICAL SPECIFICATIONS
2) Ventilation Piping
For ventilation pipe is fitted together with the wall 1 1 / 4 "for each of the
fixtures in need. Then forwarded by the main ventilation pipe which are
on the shafts in which final release on the roof floor is equipped with a
vent-cup.
3) Manhole
- Manhole consists of frame and lid made of cast iron and covered
with
bitumen paint.
- Frame and the lid take the form of a trap, so that once filled
with the
gease will be formed odors retainers.
- The diameter of the hole to pass the minimum of 500 mm, while
for the
passing of equipment shall be in accordance with the number
of equipment.
- The finishing of the surface of the manhole shall be adjusted
to the
designation of the location.
4) Sewage Tank
- If specified in the planning drawings, a sewage tank shall be
made as described here.
- Sewage tank shall be made of a reinforced fibre panel,
watertight bodies while the lid should be air-tighted.
- Each section should be able to be pumped, then the bed of the
Sewage Tank should be slanted 1: 10 in the direction of the pump,
while all the end angles should be made 135 degrees.
- Sewage tank should be completed with :
a.Sewage pipe sleeve for entry and exit .
b.Sleeve for vent pipe, Sleeve for cables
c.Level switch for a flood alarm, Level switch for pump
control
d.Manhole for the pump to go through (for maintenance
purposes)
PT. PRAPANCA ENGINEERING TS - 50
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
5) Sump Pumps
- Every sump pump shall be installed a minimum of two Sump
pumps.
- Type of pumps shall be submersible centrifugal pumps complete
with :
a. Cast iron casing, cast iron vortex impeller type
with a Knife
b. Stainless steel shaft, Mechanical seal
c. Heavy duty bearing grease lubricate
d. Stainlees steelcasing guide rail support
e. Quick discharge coupling
- Specification of the motor is as follows:
a. squirrel cage induction type, a class E Winding
insulation
b. W ater tight, Vertically mounted
- Pump motor control system
a. Start and Stop is set automatically by the level switch which
is under the sewage tank.
The pressure side of the entrance and exit as required must conform to
those contained in drawings. Must be equipped with equipment for By-
pass.
c. Check Valve
* The size of him. 15 to 50 mm
* Valve body, bronze disc material steam, female thread.
* The size of him. 65 and older
* Cast iron body, flanged end, cast steel disc.
d. Strainer
* The size of him. 15 to 50 mm
* Valve body, bronze disc material steam, female thread, type Y The
size of him. 65 and older
Cast iron body, stainless steel screen, flanged end, the Y type.
e. Flexible Connection
* The size of him. 50 s / d 200 mm
* Synthetic rubber flanged end material
f. Pressure Gauge
* Dial type 4 "
Pressure Range 0 to 10 kg/cm2
g. Valve floater
Bronze body, plastic ball, male thread
h. W ater Level Control 3 electrode
i. Foot Valve Bronze body
9) Roof Drain
a. Roof drain used herein shall be made of cast iron with the
construction of water proof
b. Area through which water from a roof drain cover is 2 (two) times
the size of the pipe discharge
a. All pipe work shall be free from burrs, rust and shall be thought cleaned
before erection. open ends during the progress of work shall be blanked
—off with purpose made metal or plastic caps and the use of wooden
plugs is occur after the various systems have been put into operation
owing to noncompliance with this requirement the contractor shall rectify
the matter at no extra cost to the contract.
b. Pipes shall be installed with correct falls for venting and draining and
attention shall be paid to neatness of installation Pipe. group of pipes
shall be accurately spaced and changed direction together end shall be
struck from a common radius point.
c. The contractor shall note the restricted space available in certain
service ducts and the absolute necessity to ensure that all pipe work is
installed in the correct sequence, manner and position to ensure that
operation of all valves and maintenance possible.
d. All reduction pipes sizes shall be made using approved standard
reducing fittings. Reducing bushed shall not be used without approval.
Connections between lengths of pipes shall be made using standard
fittings.
e. Vent pipes shall be contracted in such a way that no water trap will be
formed in the entire pipe run.
f. All galvanized iron pipes and fittings where buried in walls columns or
slabs, or installed with flanges or in direct contact with concrete, the
pipe work shall be coated with an approved protective tape before
installation.
g. All pipe work in the pump room , plant rooms and on roof level shall be
installed with flanges or unions at intervals not exceeding 6 m for easy
dismantling.
h. Change in direction of pipes shall be made with long radius bent without
the use of fittings.
i. All pipe runs when not installed underground or in duct shall be
concealed as far as possible by careful positioning or shall be chased
into walls , laid in screeds etc or as directed by the engineer.
j. All pipes passing through wall tiling and exposed to sight shall be
provided with wall flanges plugged and screwed to wall.
k. The contractor shall pay particular attention to the installation of
rainwater pipes/waste witch will be cast inside structural members to
ensure that the concealed pipes will not be damaged when pouring
concrete.
8. PIPE SUPPORTS
9. PIPE SLEEVES
a. Where pipes pass outside walls (Outbow), walls , floors, etc the
contractor shall provide pipe sleeves, sleeves for ductile iron, cast
iron ,galvanized iron and copper pipes shall be steel Where sleeves are
fitted through floors, they shall extend to at least 20 mm clear above the
level of the finished floor.
b. Sleeves shall be of sufficient size to allow free movement of pipes and
furthermore where pipes are insulated the sleeves shall be oversized to
allow the insulation to be carried through the sleeves. The contractor,
attention is drawn to the vertical pipe duct at floor levels, where pipes
pass through floors, sleeves shall be provided.
c. Detail of pipes through walls and floors and floors shall be submitted to
the engineer for approval before commencement of the installation.
d. The contractor shall supply sleeves for setting in the walls, floors, etc
and in the shuttering before concrete is poured.
e. Hole which are to be formed in beams shall be provided by the
contractor sufficiently early to meet the programmer of work.
a. General
- All fittings shall be suitable for the required working pressure and
tested as specified elsewhere in this specification.
- Reduction in bore of pipe shall be generally made eccentric for
horizontal pipes (to prevent air locking ) and concentric taper fittings
shall be fitted for vertical pipes unless specifically required to achieve
the required space and invert levels.
Drainage
- Screw joint shall be used throughout, with beaded fitting for
connecting to cast iron sockets with molten lead joints.
Domestic water
- Pipes and fittings shall be screw jointed with unions for diameters 50
mm to below and flanged for diameters 65 and lager size.
For screwed joint, pipe lengths shall be cut with standard jig fitted pipe
cutters, threads cut with clean, shaped standard thread dies and ends
reamed. Pipe treads shall be cut to BS 21-” pipe thread for tubes and
fittings where pressure tight joints are made on thread” Plumbing’s rope
or paint shall not be used to fill improperly cut thread. Litharge and
glycerin or flax and jointing compound used for joint sealing be
thoroughly cleaned prior to application of the joint sealant.
c. UPVC
- All UPVC pipes shall be jointed with sockets and fittings and
recommended by the PVC manufacturer.
- Solvent cement shall be used for all pipe work , particular attention
must be paid
11. VALVES
a. General
The contractor supply and install all isolating valves and as required for
the proper and efficient operation and maintenance of the entire system
and as may be required by local authority.
b. Valve shall be provided as described in the respective sections.
c. All valves shall be full line size.
d. each valves shall have a purpose made reference number plate or label
engraved or stamped indicating the manufacturers catalogue number,
pressure and temperature ratings, valves shall be arranged so that
clockwise rotation of the spindle will close the valve, Demo labels are
not acceptable.
e. All valves shall be packed with an approved packing and threads shall
be coated with oil and graphite in particular packing shall be asbestos
free. Packing should be replaced when found deteriorated on site.
f. Where possible locate all valves at convenient positions of operation
from the floor with valve stems upright.
g. Valves that are flanged shall have the specified table for the pipe work.
h. Plastic or metal plates shall be provide to indicate the open I close
status as well as the use of each valve in the pump.
c. For all check valves on the discharge side of pump , silent check valves
full open type shall be used ( non water hammer type).
a. Drain valves shall be provided at law point of all water risers and mains
to ensure that all sections of pipe work and plant can be drained. Drain
18. STRAINERS
a. The contractor shall provide and fix 50 mm die Traps for floor drain
inside toilets which shall be cast iron traps with 75 mm deep seal.
b. The contractor shall provide and fix 50 mm die cast iron traps for floor
drain in mechanical room as indicated on the drawings.
a. All floor drains inside toilets shall have chromium plate brass grating to
match the floor finishes. Fixing screws shall be chromium plated brass
flat head counter sunk screw.
b. Floor drains for mechanical rooms shall have cast iron prating fitted with
brass flat head counter sunk screw.
c. Floor drains shall be set in position by the contractor. The contractor
shall seal the clearance between the floor drains and the floor slabs
after installation.
All soul waste vent pipes shall be terminated above roof level as shown on
the drawings. A copper wire ( Plastic coated ) vent balloon shall securely
fixed to the open ends of all vent pipes. An approved weathering slate /
apron shall be fitted with up stand of 150 mm mm.
a. The contractor shall provide where shown and required, floor and wall
clean outs with cover plates in finished areas.
b. All clean outs shall be easily accessible and shall be leak proof.
1. GENERAL
The pump heads in the schedule drawing are given for tendering guidance
only and the Contractor shall be responsible for checking the total final
resistance of each system, based on the actual pipe runs and equipment
offered, prior to ordering. Any modifications to the system or any of this
component, i.e. pumps, pipe work, motors etc. Which may be required to
meet the scheduled deities and space limitations shall be carried out at the
Contractor’s expenses.
All pumps shall be constructed to meet the required working conditions and
test pressure of the system concerned.
2. PUMP ARRANGEMENT
5. PUMP FITTINGS
a. All pumps shall be fitted with an air-cock and drain plug. Each pump
discharge and suction line shall have a pressure gauge with a dial
diameter of 150mm completed with copper/brass siphon loop tube and
pet cock. Drains shall be piped to floor drain or channel.
b. The contractor shall supply and install flexible pipe connectors at the
pump suction and discharge for each as in the” pipe work” section as
detailed.
c. All flexible connectors shall have flanged joints for the connecting pipe
work and must be suitable for the working conditions and test pressure
of the working conditions and test pressure system concerned.
d. Automatic air release valve shall be fitted in the pump to purge any air
likely to be trapped inside the pump casing. Suitable fittings shall be
used for such connection and the A.A.V. shall not discharge at a
location directly over or not near to the pump motor or any other
electrical equipment.
6. PUMP VALVES
7. PUMP BASES
8. SAFETY GUARDS
All exposed shafts, couplings and moving parts of pumps shall be provided
with suitable galvanized angle iron wire mesh guards which shall be Stoutly
constructed and easily removable; and shall be provided with living handles.
Care shall be taken that these guards do not cause “Ringing” sound and/or
vibrate which will create.
9. INDENTIFICATION
All electrical works associated with the pumps shall comply with the lEE
regulations (latest edition) code of practice, supply rules and regulations and
described in the relevant sections of this specifications.
a. The Contractor shall supply and install level probes in water tanks as
indicated below and shown in the drawings.
b. Each probe shall be of the correct length for its particular application
and tank location. Electrodes shall be of polished stainless steel 20mm
O.D. electrode holders shall be weather proof in all respect.
c. The earthling probes shall be connected and wired to the building earth
systems of the building.
d. Each set of electrodes shall be installed inside a 250mm diameter PVC
pipe acting as a wave barrier.
e. The level switch set shall operate with a stepped down voltage at 24 V
maximum. Stepped down transformers shall be provided for each set of
control probes and shall be installed inside control cubicles.
14. PLUGS
1. GENERAL
The contractor shall supply and install all electric wiring electrical and
control panel and level control etc. for the complete, safe and satisfactory
operation of the plant covered by the specification.
3. ELECTRICITY SUPPLY
The electricity supply will be 220 V/phase/50 Hz and 380 V/3 phase/5OHz,
4 wire. All equipment shall be designed to operate with ± 10% voltage
tolerance without a loss of rated output.
The Contractor shall be responsible for extending the supply from the above
mentioned isolator/distribution board and shall include all electrical works
including control panels, starter, conduits and wirings etc. Necessary
operation of their equipment offered.
Before commencing any work whatsoever on the pump control cubicle, the
contractor shall submit drawings of the proposed layout showing all
dimensions, the total weight, fixing details, cable sizes and cable termination
details of both incoming and outgoing cable to the Engineer for approval.
Approval of drawings will be given I principle only, without abrogation of the
Contractor’s responsibilities in respect of associated details.
Cubicle shall be wall mounted and provided with hinged lockable access
doors with mechanically retained gaskets and hinged top panels containing
control switches, supervisory instruments and pilot light. All exterior door
fitting shall be chrome plated.
Pump control cubicle shall contain a main fused switch, bus work, Brach
switch, bus work, branch switch fuses or molded case circuit breakers,
motor starters, auxiliary relays, control fuses, on/off push buttons,
manual/auto power eon’ lights, pump running and overload lights,
ammeters, terminal blocks, wiring and accessories for the full operation and
control of the associated pumps. All electrical equipment shall comply with
the relevant section of this specifications.
The Plumbing and drainage Contractor shall provide voltage free dry
contacts in from of terminal block inside the pump indication panel for each
respective alarm of the pumps and water tank status. The following points
for each pump water tank/sump pit are required to be monitored:
- Pump Running
- Pump Trip
- Water tank low level
- Water tank high level
The Electrical Contractor responsible the work will obtain the respective
signals from those indication panels only.
5. CABLES
All wiring shall be carried out using PVC insulated stranded single core
copper conductor cable to B.S. 6004,6231,5345 or 6500 as appropriate.
The Contractor shall confirm loads and sizes of cable prior to placing orders.
PUlL for their entire length, and the phase to which they are connected. All
control wiring shall be colored coded using spiral stripe tracer on base color.
All PVC insulated wiring including earth wires shall be enclosed in conduit or
approved trucking. To Eliminate the possibility of damage to cable due to
thermal expansion, allowance for movement shall be made by the
introduction of bend or set in each cable/core adjacent to the terminal.
Cables shall, at all times, be handled with care and every effort made to
shall be exercised when breaking the rotation of the drums and under no
circumstances shall babble be dragged over loose earth of concrete.
Approved type of cable rollers shall be used.
After installation, all cables shall be tested for continuity and insulation
resistance and records of test submitted to the Engineer for approval. Single
core cable shall be pulled into conduit only after the whole network, or a
complete section of conduit has been installed, tested for continuity and
swabbed through.
The Contractor will be deemed to have allowed in his tender sum for
applying sufficient lengths of cables of each type and size to complete the
installation, including the due allowances for additional lengths for cuthng
and waste.
6. ELECTRIC MOTORS
7. ELECTRICAL TESTS.
The precise method of canying out the following test shall be agreed with
1, MATERIALS
All parts of the work installed under this specification shall be painted with
approved first quality enamel paints, except those items specified as being
painted by others or otherwise exempted from painting in this section of the
specification.
All paints used shall be of one approved manufacturer, and finishes shall e
full gloss unless otherwise specified.
Before ordering any primer, undercoat and finishing paint, the Contractor
shall submit the color scheme to the engineer for approval.
The sub-contractor shall select all finishing and painting materials from type
suitable for the surfaces to which they are applied and for the environmental
conditions in each area.
3. EXPOSED METALWORK
All exposed metalwork shall be wire-brushed and iron cleaned from rust,
scale, dirt and grease, and shall then be given one priming coat, one
undercoat and one approved color finishing coat of full gloss enamel.
4. CONCEALED METALWORK
All galvanized iron surface concealed in roof spaces, false ceilings, building
ducts etc. shall not be painted.
Pipe work and metal sheeting shall be painted as for exposed or metalwork
as applicable.
6. PIPEWORK IDENTIFICATION
Supplementary colors shall be displayed as bands not less than 25mm wide
in the centre of the ground color bands.
7. LABELLING
The following refers to specific items (but not by way of limitation) requiring
labeling
The valve schedule shall clearly relate to the various system schematics to
enable the entire operating sequence and circuitry to be followed.
8. APPLICATION OF PAINTING
When the surfaces to be painted are clean and dry, one coat of an approved
primer shall be evenly applied over the entire area. After surfaces have
been primed, the sub-contractor shall notify the engineers so that an
inspection of the primed surfaces can be made prior to the application of the
undercoat and the finishing coats.
When the priming coat has been approve, one coat of an approved paint flat
undercoat shall be applied. Before applying the finishing coats, the sub-
contractor shall ensure that the under coated surface is rubbed flat and
smooth. Finally, two coast of an approved high gloss finishing paint shall be
when all dust has been removed.
1. GENERAL
The contractor shall ensure to the satisfaction of the Engineer that the
installation complies with all requirements including the following clauses.
a. The contractor shall the entire installation including all sanitary fitments
and pipe work, etc. After installation and keep them in a new condition.
b. All pipes, etc, shall be flushed through with water, ridded when
necessary to ensure clearance of debris.
a. The Contractor shall carry out hydraulic test on the completed fire
fighting systems to show that it is functioning satisfactorily within the
requirements of this specification and local regulations.
b. The Contractor shall provide suitable tests pumps and arrange for a
supply of water required in connection with testing of pipe work, the test
pump shall be fitted with pressure gauges which shall be fitted with
pressure Gauges which shall be of suitable range for the pressure being
applied.
c. Hydraulic tests shall be carried out as the pipe work is installed and
shall be completed before cases in walls. Also tests shall be carried out
prior to false ceilings and other finished are installed.
d. All water services pipe work shall be hydraulically tested for a period of
not less than 24 hours to a pressure of not less than one and half times
the working pressure. The Contractor must record all test figures
together with schedules of pipe lengths and should note that testing
f. The Contractor must carry out any additional tests if required by the
local authorities, without any additional cost.
Blow air through the tube and reconnect at the manometer gauge to
obtain a reading of 38mm w.g. the level should remain for a period of
not less than five minutes without falling and without further air being
following
- That the plant and apparatus is of robust construction and of capacity
for the duty specified.
- That all valves, switches, controls, etc, are properly regulated and
capable of proper operation and in the case of valves that are
capable of tight shut-off.
- That all apparatus is silent.
- That all instruments are correctly calibrated and read accurately.
- That all services are tested in accordance with the details of the
relevant clauses of this specification.
- That the alignments for all pumps are proper.
h. Should the results of these test shown that the pumps, etc or any other
items of equipment fail to perform to the efficiencies or others
performance figures as given in this specification, and as replace the
equipment without additional cost to the contract in order that the
required performance is obtained. Should it be necessary for the
Contractor to attend to item of plant as described he will be responsible
for cast for any damage or deterioration to the building or any other
services consequent on such attendance.
I, The Contractor shall perform all tests and demonstrations as called for
by the local authorities.
a. The Contractor shall provide all tools, pressure pumps, instruments and
recorders required to carry out the tests given in this section.
b. All water and electricity required for testing purpose wUl be supplied by
others.
5. PRETREAMENT
1. GENERAL
After handover of the work, the contractor shall carry out regular preventive
maintenance at interval not exceeding three calendar month, or other wise
as directed by the £ngineer and shall provide a fast, efficient and
comprehensive breakdown services as required during the defects liability
period.
All materials supplied and installed by the Contractor shall be new and
such material must be suitable for incorporation in the tropics.
Materials must be of good quality products from the latest production. For
the materials mentioned below are the Owner must guarantee that the
goods are
good and new by producing delivery of mail order dealers / agents / factory.
The Contractor must be willing to replace the material that is not
approved due to deviating from the specifications or other matters, where
such replacement is no extra cost.
2. LIST OF MATERIALS
For all the materials offered the Contractor must complete list of
materials that mention the brand, type, class complete with a brochure /
catalog that are also attached at the time of submitting their tender.
The table of the list of these materials gives priority to the components
in the form of factory-manufactured goods.
If later during the course of the project it happens that the materials listed
on thet tabel of materials cannot be made available by the Contractor
PT. PRAPANCA ENGINEERING TS - 77
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
a. A cover giving
• The same of the development
• The title of the document
• The same and address of the installation contractor.
b. Inside page giving similar information to the cover but including contact
telephone numbers for normal and emergency use.
c. Content page.
d. Description of the installation.
e. Scheduled details of all equipment and plant.
f. Operating instruction including details of any automatic control system.
g. Maintenance and fault finding instructions including composite schedule
of routine maintenance.
h. Tests reports and commission records.
i. Recommended spare parts and lubricants.
j. List of equipment and plant with manufacturer’s name and address and
local agent, if applicable.
k. Manufacturer’s literatures suitable indexed to include shop drawings,
wiring diagrams, performance curves, etc.
I. A complete valve schedule as described in the “painting, labeling and
finishing” section.
m. List of as-installed drawings.
5. SERVICE
6. PREVENTIVE MAINTENANCE
The Contractor shall carry out regular inspections periods not exceeding
three calendar month, and shall fully service all plant installed under this
specification for the term of the defects liability period, and shall maintain all
such plant in perfect operation during that period.
The contractor shall attend all tests and inspections carried out by statutory
authorities, and shall forthwith executive any variation work as a result of his
failure to comply with the statutory requirements.
A. SCOPE OF WORK
The scope of works for the fire Hydrant System shall include the following :
a) External Pillar Fire Hydrants
b) Standpipe and hose system
c) Automatic fire Alarm System
d) Portable Fire extinguisher
The design and installation of the Fire Hydrant System shall comply with the
following codes : -
a) Fire Fighting System
b) Public Work Ministry Regulation No. 02/ KPTS /1985
c) Regulation of DKI Jakarta/ Makasar Government
d) National Fire Protection Association (NFPA)
- NFPA 10 Portable Fire Extinguisher
- NFPA 14 Installation of standpipe and Hose System
- NFPA 20 Installation of Centrifugal Fire Pumps
The material / equipment and the Fire Fighting system installation and
sub-system that become part of work scope in this chapter, should meet
and in compliance with few references, standard material and works,
including the relevant Regional Regulation but not limited to the matters
specified hereuinder:
- Indonesian National Standard / SNI 03-1745-2000 pertaining to the
Planning Procedures and Installation System of Vertical and Slang
Pipe for the Prevention of Fire Danger In Building Construction.
- Indonesian National Standard / SNI 03-0000-2001 pertaining to
Pump Installation Permanently Installed for the Fire Protection
- Indonesian National Standard / SNI 03-6481-2000 pertaining to
Plumbing System -2000
- Indonesian National Standard / SNI 03-0255-2000 or General
Requirement Electrical Installation (PUIL-2000) specifically for the
electrical works in sub-work plumbing system
- Certain International/other country Standard which are not in
contradictory with the related SNI such as: NFPA, National Plumbing
Codes, etc.
- Indonesian Plumbing Regulation Guidance published by the
Directorate of Sanitation Engineering of Directorate General of
Creative Works of Public Works Department.
- General Examination for building material NI-3 (PUBB) 1956 NI-3
1963. PUBB 1969
- Indonesian Concrete Regulation PBI-NI-2 / 1971
- Indonesian Labor Regulation pertaining to the daily, weekly, monthly
and labor contract usage.
- DKI Regional Regulation-Greater-Jakarta No. 8 Year 2008 pertaining
to the Procedure of Fire Anticipation in the territory of Special
Region of Capital City of Jakarta that can be used in the other
Districts.
- Ministerial Decree of Public Works No. 28 year 2000.
2. GENERAL
The Hydrant system shall be supplied and installed in .accordance with the
drawings, the requirements of the local regulations and NFPA 14 as
appropriate.
3. SYSTEM
a The Hydrant pipe material shall be black steel pipe conforming to ASTM
A53 BSP Sch 40.
b Pipe joints shall be as described in the suction on the pipe work.
5. EXTERNAL PILLAR HYDRANT
Hose station shall be properly grouped with each group proceeded with
pressure reducing device to be able to limit flowing pressures at any hose
valve at a maximum of 6.5 bars (100 psi).
Pipe work for the wet riser system shall be galvanized mild steel pipe to BS
1387 :1967 heavy grade (Class C ).
7. SIAMESE CONNECTIONS
The water supply system shall consist of two electric fire pumps, each pump
is provided with emergency generator power supply, and a jockey pump.
from the floor. The hinge should be located adjusted with the condition so
that it is easily-opened.
• The entire boxes and door should be in red paint Duco ex
Danapaints and engraved with Hydrant writing in white color.
• The length of the fire hose should be not less than 30 m, and easy
to be equipped with hose rack pressure proof and use the coupling
system as the connection. Nozzle variable (set spray) φ 1 ½” and
landing valve φ 2 ½” should be in new condition and fabricated, with
minimum class of 200 psi, bronze material.
24 PIPELINING SYSTEM
a Pipe Connecting System
Fire Fighting Pipe
The use of fitting
Pipe below φ 40mm” malleable iron ANSI B. 163 class 300lb, Screwed
and pipe above φ 50mm”, wrought steel Butt weld fitting ANSI B 16.9 SCH
40 Flange: Diameter above 50mm”, Forged Steel RF Class 300lb, welding
joint.
To strengthening from the leak, the pipe connecting using thread should
be firstly layered with Primatone EPOXY ADHESIVE & SEALANTS.
While the flanged connection should be equipped with Ring Pack ujs /
gasket rubber made homogenously.
1) All fixtures should be properly installed and free from any dirt that
might interfere the flow or cleanliness of the water, and should be
rigidly installed at its place with a rigid foundation.
2) All fixtures, fittings, water pipes should be in tidy condition and does
not disturb the installation process / porcelain wall and etc. The
fixtures component should be synchronic and well-installed, and also
installed in strong foundation to hold up the components, such as
fixtures, fitting and etc. The Contractor should be responsible in
completing the said component on the installation networks as
abovementioned.
3) For the pipes with high pressure water / main pipe, a concrete block
with strong mixtures should be installed and it is installed in every
connection of pie, tee, elbow, valve and etc.
d. Valves
1) Water valve with φ 2” is “screwed bronze body type with external
spindle” Type Gate Valve
2) Water valve with φ 2½” - φ 3” is of “bronze flanged body type with
internal screwed spindle” Type Butterfly Valve
3) Water valve bigger than φ 3” is of “flanged steel body type with
external spindle yoke”. Type Butterfly Valve
4) Work pressure from valves should be adjusted with its function, for the
water work of fire fighting, valve with work pressure 300 psi, with cast
iron material must be used.
e. Underground Pipes
PT. PRAPANCA ENGINEERING TS - 89
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
f. Painting
All underground irons / steel pipes should be layered with Tar (Tor Corted)
or coating to prevent from corrosive. While for the exposed pipes should
be marked with color or paint where the color of which will be determined
later by MK. In the purpose of being easily-recognized the entire pipes on
the ceiling should be marked in color / paint for a distance of ± 4 m long
on each main pipe as well as the pipe in the shaft where the examination
door is located. Standard paint colors that will be used are as follows;
- For Hydrant Pipe and Sprinkler will use red color
- For pipe direction will use white color.
b. Material
The Contractor should warrant that the entire unit of equipment are in new
condition and free from any defective material, improper material, and
also warrant that the quality of the equipments are in accordance with the
PT. PRAPANCA ENGINEERING TS - 90
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
e. Shop Drawings
Shop drawings for the entire works should be available on the site at all
times. Including the changes or suggestion and etc, during the installation,
Contractor should mark the drawing sets with a pencil or red ink for any
changes made, erasing or any additional to the said installation, shop
drawings should be made in 1 (one) set of calques papers 3 (three) sets
of blue print by the Contractor.
f. As Built Drawing
g. Model of Goods
The Contractor is obliged to send the model of material that will be used in
the implementation or brochures from the said equipment to MK and
awaiting for the approval from MK prior to the installation.
Should the said material be declared improper/unusable by MK, therefore,
the Contractor should remove the material out from the site within 3
(three) days, the said material should be no longer be in the site area
anymore.
h. Executants
The entire works should be implemented properly by the skilled labor so
that it is able to precisely produce best quality work.
For the particular implementation, the Contractor should provide statement
letter that verify the labor is capable in terms of experience and skill in
doing such work.
i. Security
The Contractor is responsible for the prevention of the material /
equipments of the installation from the damage or thievery. The lost or
damaged materials / equipments should be replaced by the Contractor
without any additional cost.
j. Coordination
During the work implementation, the Contractor is obliged to hold
coordination among the other Contractors that engage the structural,
electrical and interior works and etc, in order to minimize any error and
mistakes happening in the installation.
k. License
1) Permits and other necessary requirements to implement the
installation should be performed by the Contractor at its own cost.
2) All the examinations, utilization worthiness testing from the Fire
Fighting Agency (DPK) and others as well as the official notes that are
necessary for the installation works should be performed by the
Contractor at its own cost.
3) The Contractor should be responsible for the usage of copyrighted
equipment, the possibility of indemnity claims and other necessary
costs for such works. The Contractor is obliged to handover the
statement letter pertaining to this matter.
4) The Contractor should handover the permits or official notes obtained
from the authorities pertaining to this installation project to MK,
Consultant or to the appointed party.
l. Work Correlations
1) The Contractor should provide data, measurements and drawings
pertaining to the excavation and piling works that are performed by the
other parties if any.
2) All machine pedestal manufacturing should be performed by the
Contractor. The Contractor should provide necessary data,
measurements, drawings and equipments to the other parties that
require such data.
3) All electrical cable withdrawals up to the equipment panel can be
performed by the other party. The Contractor is obliged to provide
necessary data and drawings to the other executing parties.
4) All the water pipe withdrawals including clean water pipe, hydrant pipe
and sprinkler pipe which are not listed in the drawings and
specifications performed by the other party, the Contractor should
coordinate and provide data, measurements and drawings to the other
executing party.
5) All electrical facilities, water, emergency sanitary should be done by
the Contractor. The Contractor should coordinate with the other parties
to anticipate this matter.
m Sub Contractor
1) Should there be any requirement particularly in the skilled labor as the
result of incapability of the existing labor to implement the installation,
adjustment, testing and other works; therefore the Contractor is able to
PT. PRAPANCA ENGINEERING TS - 93
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
n Site Supervisor
1) The entire works covered in such installation should be supervised by
qualified person. He / She is fully responsible for the work installations
in this project.
2) Name, detail work experience, organizational structure of Site
Supervisors should be provided by the Contractor to MK in order to
obtain an approval.
3) When, in fact, that the appointed Consultant or other authorized party of
Site Supervisor is consider incapable by MK, therefore the Contractor
should substitute them by another person.
o. Installation Report
1) The contractor should provide samples of all materials that will be used
to MK, consultant or other appointed party to request a written
installation approval thereof.
2) By listing a complete brand, type and specification from all models of
material proposed.
3) The Contractor should create a schedule of detail time for every work
and give it to MK, Consultant or other appointed parties to obtain an
approval.
The contractor should provide:
1. Daily Report Book
2. Weekly Report Book
3. Monthly Report Book completed with a Picture
4. Overtime / holiday works permit
5. The Contractor should report the work progress in each week along
with the comparison as per schedule having been arranged.
6. When there is any discrepancy, then the reasons thereof together
with the way how to overcome such discrepancy should be given.
7. For each completed installation work, the Contractor should obtain a
written statement from MK, Consultant and other appointed party
q. Operational Instruction
1) By the time of the initial handover, the Contractor should provide
drawings, operational instruction equipment data and maintenance
method of installed machinery under this Contract in Indonesian
Language.
2) The said data should be handed over to the Owner in 3 (three) sets
and 1 (one) set to the Consultant.
3) By the time of the initial handover the Contractor should provide as
follows; Instruction Manual, Installation Manual, Maintenance Guide,
Operating Instruction, Trouble Shooting Instruction and Original
Brochure.
4) The Contractor should provide 2 (two) sets of abbreviation operational
instruction and maintenance to the Owner that should be placed in
glass framed and attach it to the wall in the main machine room or in
the other locations appointed by MK.
5) The Contractor should provide practical education at no cost pertaining
to the operational and maintenance to technical engineering officers
appointed by Owner / MK until the aforesaid officer is qualified enough
to perform the task.
6) The Contractor should provide a warranty letter toward the main
equipment to the Taskmaster.
r. Certificate
The contractor should provide Certificate / Recommendation from the
regional Fire Fighting Agency (DPK) for the evidence of the said unit is
eligible to be used particularly in works of fire fighting system installation.
26 TESTING
a. Exhaust System Testing
1) The entire water pipe systems should have pluggable hole so that the
said systems can be filled with water up to the highest “Vent” hole.
2) The said system should be able to hold the water filled as
abovementioned and if the observer would like to have another testing
other than the test above, the Contractor should allocate an additional
cost and borne by the Contractor.
The test should comply with the procedure of NFPA 20 in the condition
that Valve is plugged by pump Head 101-140% in the capacity of 150%
of normal capacity, Head pump 65% of the normal pump Head.
Utilities:
• Pump is equipped with diesel engine couple on the top of the base
plat, completed with the radiator, muffler, and flexible pipe; unloose
plat, fuel tank, electrical panel and etc.
• Battery charger
• Fuel tank for 2 hours capacity (cap 1 Gal / 1 HP plus 10%)
• Operation system, automatic start and manual stop
up to the time limit, the Main Pump will automatically start, and will be
manually stopped by the operator if the testing or the fighting test is
completely accomplished.
b. Maintenance Period
Maintenance period should be determined for 180 (one hundred eighty)
calendar days since the date of initial work delivery along with the Official
Notes. The Contractor should repair all the damage or the improper
functions of the equipment due to imperfectness of the implementation or
the material used. The repair should be performed immediately by the
Contractor on the first warning time from Board of Directors. The
Contractor should immediately repair the damage resulting from the
implementation of the work.
c. Work Delivery
The said work should be fully accomplished and delivered for the first
period as mentioned above. The notice of the work delivery should be in
writing prepared by the Contractor and mentioning the desired date of the
handover to the Construction Management within 1 week prior to the
desired performance of handover. Should the works be considered
eligible, then the Construction Management will accept the said work for
the first time, declared in writing in the First Official Notes.
1. GENERAL
The contractor shall supply and install all electric wiring electrical and
control panel and level control etc. for the complete, safe and satisfactory
operation of the plant covered by the specification.
3. ELECTRICITY SUPPLY
The electricity supply will be 220 Vt phase/50 Hz and 380 V/3 phase / 50Hz,
4 wire. All equipment shall be designed to operate with ± 10% voltage
tolerance without a loss of rated output.
The Contractor shall be responsible for extending the supply from the above
mentioned isolator/distribution board and shall include all electrical works
including control panels. starter, conduits and wirings etc. Necessary
operation of their equipment offered.
Before commencing any work whatsoever on the pump control cubicle, the
contractor shall submit drawings of the proposed layout showing all
dimensions, the total weight, fixing details, cable sizes and cable termination
details of both incoming and outgoing cable to the Engineer for approval.
Approval of drawings will be given I principle only, without abrogation of the
Contractor’s responsibilities in respect associated details.
Cubicle shall be wall mounted and provided with hinged lockable access
doors with mechanically retained gaskets and hinged top panels containing
control switches, supervisory instruments and pilot light. All exterior door
fitting shall be chrome plated.
Pump control cubicle shall contain a main fused switch, bus work, Brach
switch, bus work, branch switch fuses or molded case circuit breakers,
motor starters, auxiliary relays, control fuses, on/off push buttons,
manual/auto power ‘on’ lights, pump running and overload lights, ammeters,
terminal blocks, wiring and accessories for the full operation and control of
the associated pumps. All electrical equipment shall comply with the
relevant section of this specifications.
The Plumbing and drainage Contractor shall provide voltage free dry
contacts in from of terminal block inside the pump indication panel for each
respective alarm of the pumps and water tank status. The following points
for each pump/water tank/sump pit are required to be monitored; Pump
Running, Pump Trip
5 CABLES
All wiring shall be carried out using PVC insulated stranded single core
copper conductor cable to B.S. 6004,6231,5345 or 6500 as appropriate.
The Contractor shall confirm loads and sizes of cable prior to placing orders.
All PVC insulated wiring including earth wires shall be enclosed in conduit or
approved trucking.
To eliminate the possibility of damage to cable due to thermal expansion,
allowance for movement shall be made by the introduction of bend or set in
each cable/core adjacent to the terminal.
Cables shall, at alt times, be handled with care and every effort made to
shall be exercised when breaking the rotation of the drums and under no
circumstances shall babble be dragged over loose earth of concrete
Approved type of cable rollers shall be used.
After installation, all cables shall be tested for continuity and insulation
resistance and records of test submitted to the Engineer for approval. Single
core cable shall be pulled into conduit only after the whole network, or a
complete section of conduit has been installed, tested for continuity and
swabbed through.
6. ELECTRIC MOTORS
The power factor of all motors shall not be less than 0.85 lagging under all
conditions.
Motors shall be mounted on a common bed plate with the driven machine
wherever possible.
7. ELECTRICAL TESTS.
The precise method of carrying out the following test shall be agreed with
the Engineer prior to Commencement.
1. MATERIALS
All parts of the work installed under this specification shall be painted with
approved first quality enamel paints, except those items specified as being
painted by others or otherwise exempted from painting in this section of the
specification.
All paints used shall be of one approved manufacturer, and finishes shall e
full gloss unless otherwise specified.
Before ordering any primer, undercoat and finishing paint, the Contractor
shall submit the color scheme to the engineer for approval.
The sub-contractor shall select all finishing and painting materials from type
suitable for the surfaces to which they are applied and for the environmental
conditions in each area.
3. EXPOSED METALWORK
All exposed metalwork shall he wire-brushed and iron cleaned from rust,
scale, dirt and grease, and shall then be given one priming coat, one
undercoat and one approved color finishing coat of full gloss enamel
The priming coat for exposed galvanized iron shall be an approved
galvanized iron primer.
All galvanized iron surface concealed in roof spaces, false ceilings~ building
ducts etc. shall not be painted.
6. PIPEWORK IDENTIFICATION
All pipe etc. shall be identified in accordance with British Standards 1710:
1984.
high for pipes up to 50mm nominal diameter, and in block letter not less
than 40mm high for larger pipes.
7. LABELLING
The following refers to specific items (but not by way of limitation) requiring
labeling
acceptable.
The valve schedule shall clearly relate to the various system schematics
to enable the entire operating sequence and circuitry to be followed.
8 APPLICATION OF PAINTING
When the priming coat has been approve, one coat of an approved paint flat
undercoat shall be applied. Before applying the finishing coats, the sub-
contractor shall ensure that the under coated surface is rubbed flat and
smooth. Finally, two coast of an approved high gloss finishing paint shall be
when all dust has been removed.
1. GENERAL
The contractor shall ensure to the satisfaction of the Engineer that the
installation complies with all requirements including the following clauses
a. The contractor shall the entire installation including all sanitary fitments
and pipe work, etc. After installation and keep them in a new condition
b. All pipes etc, shall be flushed through with water, ridded when
necessary to ensure clearance of debris.
a. The Contractor shall carry out hydraulic test on the completed fire
fighting systems to show that it is functioning satisfactorily within the
requirements of this specification and local regulations.
b. The Contractor shall provide suitable tests pumps and arrange for a
supply of water required in connection with testing of pipe work. The test
pu mp shall be fitted with pressure gauges which shall be fitted with
pressure Gauges which shall be of suitable range for the pressure being
applied.
c. Hydraulic tests shall be carried out as the pipe work is installed and
shall be completed before cases in walls. Also tests shall be carried out
prior to false ceilings and other finished are installed
d. All water services pipe work shall be hydraulically tested for a period of
not less than 24 hours to a pressure of not less than one and half times
the working pressure. The Contractor must record all test figures
together with schedules of pipe lengths and should note that testing
shall be witnessed by the Engineer. No pressure drop shall be allowed
during the tests.
f. The Contractor must carry out any additional tests if required by the
local authorities, without any additional cost.
At the base of each stack, a drain bag drain plug is inserted and small
quantity of water allowed to settle above it so as to form a seal that can
easily be inspected if it leaks.
Blow air through the tube and reconnect at the manometer gauge to
obtain a reading of 38mm w.g. the level should remain for a period of
not less than five minutes without falling and without further air being
following
h. Should the results of these test shown that the pumps, etc or any other
items of equipment fail to perform to the efficiencies or others
performance figures as given in this specification, and as replace the
equipment without additional cost to the contract in order that the
required performance is obtained. Should it be necessary for the
Contractor to attend to item of plant as described he will be responsible
for cast for any damage or deterioration to the building or any other
services consequent on such attendance.
i. The Contractor shall perform all tests and demonstrations as called for
by the local authorities.
a. The Contractor shall provide all tools, pressure pumps, instruments and
recorders required to carry out the tests given in this section
b. All water and electricity required for testing purpose will be supplied by
others.
5. PRE TREATMENT
1. GENERAL
After handover of the work, the contractor shall carry out regular preventive
maintenance at interval not exceeding three calendar month, or other wise
as directed by the Engineer and shall provide a fast, efficient and
comprehensive breakdown services as required during the defects liability
period.
a. A cover giving
b Inside page giving similar information to the cover but including contact
telephone numbers for normal and emergency use.
c. Content page.
j. List of equipment and plant with manufacturer’s name and address and
local agent, if applicable.
3 SERVICE
4 PREVENTIVE MAINTENANCE
The Contractor shall carry out regular inspections periods not exceeding
three calendar month, and shall fully service all plant installed under this
specification for the term of the defects liability period, and shall maintain
all such plant in perfect operation during that period.
The contractor shall attend all tests and inspections carried out by statutory
authorities, and shall forthwith execute any variation work as a result of his
failure to comply with the statutory requirements.
IV. ELECTRICAL
A. SCOPE OF SPECIFICATION
1. EXPLANATION
The works included in the field of this expertise include:
a) Provide all electrical systems works so that it can operate perfectly.
b) The drawings, specifications and bills of quantity are
complementary parts of and something that is contained in the
drawings and specifications which shall be binding.
c) All electrical installation works undertaken should be done by the
installer Contractor who can be trusted, has a good reputation and
has skilled and experienced workers in their fields, and the
company is registered as a PLN official installer by holding the
highest class installers fitting (D) which are still valid for a current
last year or has a valid technique responsible person determination
(SP-PST) and Certificate of Expertise / SKA from AKLI.
d) All installation works must be done according to "General
Requirements for Electrical Installation in Indonesia last edition in
2000 (PUIL) and PLN Rules (SPLN)" as a guide and also prevailing
regulations on the local area and other recognized standards/codes
such as IEC, VDE/DIN, AS, BS and others.
e) The Contractor shall place a scholar or who is deemed an expert as
a representative of the company and can make decisions if at any
time necessary. MK may request another supervisor turnover when
considered incapable.
2. DRAWING
PT. PRAPANCA ENGINEERING TS - 116
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
a. The plan drawings that include the scope of electrical installation work
in this Tender Document are the drawings with the drawing code
number EE.
b. The Contractor shall check the design against the possibility of
errors/lack of match in terms of electrical quantities as well as
installation and others. The matters above shall be submitted in writing
or drawing on the explanation of the tender/aanwijzing.
c. Before the work is submitted in whole or in stages, the contractor shall
submit to MK of 3 (three) sets of drawings called "as-built drawings"
that are drawings of all materials, equipments and installations of
electrical systems, (1 set tracing 3 sets of blueprints)
d. The electricity drawing shows the overall magnitudes and numbers
and terms of the purposes of installation, the installation must conform
to local conditions on the project.
e. The drawings of architecture and structure must be related to the
construction and final details of the project, while other drawings must
be related to the details construction with regard to each work. The
contractor must complete all further purposes such as "shop drawings"
and detailed drawings.
f. Meaning that if there is technical or physical incompatibility then this
matter must be submitted in writing 4 days prior to the performance of
work, to be reported to MK/ the Planner in the field as a step of
execution, where the costs are already covered in the unit price of the
item.
4. GENERAL REQUIREMENTS
b.Referenced Clause
If there are matters that are mentioned again in other
section/chapter/drawing then this shall be interpreted not to eliminate one
another but instead to further confirm the matter. If there occurred any
contradictory matters between drawings or to technical specifications as
well as BQ, then a benchmark which shall be taken is having technical
weights and or having the highest cost weight.
c. Coordination Of Work
To smooth this work must be held coordination of all parts involved in this
project activity. All activities involving in the project must be coordinated in
advance for any disruption and conflict with one another can be avoided.
Localizing/itemizing each work until the details for approval by MK/the
Planner.
All equipments, materials used in this work must be new and the material
must be resistant to the tropical climate. All works must be carried out in
the right way and every worker must have a satisfying skill. Where special
training for workers is necessary and the Contractor must perform it. The
Contractor must complete the valid certificate for any expert personal,
stating that the personnel has participated special trainings or has special
experiences in their respective areas of expertise.
e. List Of Material
At the time of bid, the Contractor must include/ attach "List of Materials"
which is firstly specified from all materials to be installed on the project and
must be mentioned factory, brand, manufacturer, type, complete with a
brochure/catalog. This shall be binding and must be filed complete, not be
a partial.
g. Shop Drawing
After the approval, in this case before the list of material specification, the
Contractor is required to submit shop drawings for approval of the Planner.
The shop drawings must be given the records of the Contractor, stating
that what is recommended is in conformity with the specifications and the
conditions of the space provided.
The data for each system must show the complete installation of all
component coordination to review the overall of the actual from the entire
system, the partial delivery will not be considered. The drawing of shop
drawings must be made in 4 (four) sets.
Shop drawings to be submitted are:
1. HVDP and LVMDP Panel
2. Power and lighting panels, outlet boxes and others.
3. Transformer, distributions wire layout and other.
4. The details of the installation of lamps.
5. Plan of lighting installation, socket every floor.
6. And others as requested by the Planner/MK.
Shop drawings are inserted for review / approval of the planner/MK at
least 14 (fourteen) working days after the issuance of Offer Letter
(SPK).
h. Subtitution
1) Product mentioned name of manufacturer
Materials, equipments, furnishings, accessories mentioned the name
of the manufacturer in the specification, the Contractor must complete
the products mentioned in the specification, or may propose an
equivalent substitution product, with complete data for approval of the
Planner/MK before order.
i. Sample
The Contractor shall submit samples of all materials to obtain prior
approval from the Planner/MK. All costs shall be borne by the Contractor.
These samples (mock-up) are included at least 14 (fourteen) working days
after the issuance of Offer Letter (SPK).
j. Protection
All materials and equipments must be in truth and adequately protected by
the Contractor, prior to during the construction and after the completion of
installation (under warranty period). Which materials and equipment were
damaged as a result of a sloppy installation and the inadequate protection
cannot be accepted for the installation of project.
k. Acces Opening
The Contractor shall provide an access opening (openings) for the
installation and maintenance of electrical installations. The openings
(access opening) contained in building construction such as walls, ceilings,
and so on upon the opening shall be equipped with proper closing facilities
for equipment surface, the cover must be released and transferred without
causing damage to the adjacent surface.
l. Painting
If the equipments have been painted from the manufacture and the
additional painting in the field is not specified then the entire defect surface
PT. PRAPANCA ENGINEERING TS - 122
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
n. Testing
The Contractor shall perform all testing as described and must perform an
experiment as properly real operation of the entire system. The
equipments, materials and how to work the damaged / defective / wrong
equipments must be placed/corrected and the repeated experiment. All of
the cablings, installations of "keur" the Contractor shall be responsible to
gain approval of PLN for the installation of electricity network system and
all the costs shall be borne by the Contractor. The period of the electrical
PT. PRAPANCA ENGINEERING TS - 123
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
equipment testing is 1x24 hour non-stop, the testing costs shall be borne
by the Contractor.
q. Cleaness
The Contractor shall clean all dirt/trash and the unused waste materials as
the result of his work and must finish each part of the regularly and orderly
installation.
t. Installation Completeness
In this technical specification and in the drawing for a system or a device
of electrical equipment is intended as a system that can operate well in
such a way so that if any part or component of the installation system that
is not mentioned in this technical specification as well as in the drawings,
then this means the Contractor must establish and ensure the system /
installation will work well.
u. Training
Educating the operator or persons designated by the owner to run, operate
the necessary testing and maintenance of installations. All these costs are
borne by the Contractor
5. EXTENT OF WORK
a. Electrical
Incoming electricity supply from the PLN substation to 20 KV
switchboard, power transformers, L.V. main switchboard, including
supply and installation of incoming cables to 20 KV switch board to PLN
requirement 20 KV main switchboards, 20 KV I 400 V power
transformers, LV. main switchboards.
Small power installation, including all devices, isolating switches and the
like. Detection, control circuit and wiring for automatic operation of the
system.
- Boiler room
- Storage and Maintenance Building
- Pump room
- Weigh Bridge
- Guard house
- WWTP
b. Electrical
Source Power Supply shall be taken from PLN substation at Ground
Floor Site Plan. The Sub-contractor shall supply and install a 20 KV/630A
MV switchboard with load break switch SF-6 inside the Owner’s
transformer room to receive power from PLN substation Totally filled
transformer DYN5 2OKV/400V power transformers shall also be supplied
and installed by the Sub-contractor to distribute power to air conditioning
equipment, pumps etc.
Transformer Room The room shall house the 24 KV main switch board
cubicle and power transformers to receive power from PLN substation,
All installation works inside the room shall comply with PLN and all
relevant government Rule & Regulation
The location of all plant equipment shall be verified by the contractor on
site.
Power from the transformers shall be delivered to the main switch room
cubicle via bus way/Tray & Ladder Power shall be distributed at
380v/3phase /50Hz to the entire building Cubicle switchboards complete
with switchgears, protective relays and instrument/metering facilities as
detailed in the Drawing/Specification shall be supplied and installed by
the Contractor Sub-switch rooms are located on each floor of area for the
distribution of power supply to the electrical equipment of the entire
building.
All light fittings as shown on light fitting schedule shall be supplied and
installed by the Contractor c/w conduit and wirings.
Staircase lights shall be switched on all at times. Lighting for exit’ signs
shall not be controlled by any switch other than the MOB.
• Earthing system
• 20 KV systems
• LV system
• Transformer neutral
• Electronic (telephone, fire alarm, sound system etc).
• Lightning protection system
Application of Meters
The sub-contractor shall fill in all details, submit the forms to the power
compan~,’ and arrange for subsequent testing and meter connection.
a All concrete equipment plinths and concrete piers in plant rooms, keyed
to the floor slabs and graded where required. Plinths and concrete
supports shall have shapes and dimension as indicated on detailed
drawings to be provided by the Electrical Contractor.
b The building in off all sleeves and equipment holding down bolts, where
required to be built in during construction. The Electrical Contractor shall
supply all bolts and sleeves, and detailed Drawings accurately
positioning such items
c All cutting, patching framing up, furring in, chasing and making good
associated with the building construction for the passage of ductworks,
pipes, conduits etc.
Detailed and drawings shall be provided by this Electrical Contractor
h Provision of earth pits and PVC ducting for earthing and lightning
protection system etc. as indicating on the tender.
8. REGULATIONS
9. ELECTRICAL EQUIPMENT
a. MEDIUM VOLTAGE MAIN PANEL (20kV)
1)General
Medium Voltage Main Panel (PUTM) or medium voltage switchgear is a
partner in and placed in the building. The switchgear must be metal
enclosed, prefabricated.
The switchgears that strung which will be called Panel
2) Standard
Switchgear shall be designed and fabricated according to the
requirements set forth in the last edition IEC’s recommendation and the
corresponding added with the possible application of the following
standards:
• NFC Standard
• VDE/DIN Standard
• British Standard
• NEMA Standard
And the edition mentioned in this specification. The equipment that meets
the other regulatory standards, which guarantees the same quality or
better than the standards in this specification, will also be accepted.
3) Climate Conditions
Geography: equator
Height: less than 1000 meters above sea level
Atmosphere: humidity 80% - 100%
Temperature:
- Browse temperature: 16OC - 40oC
- The average temperature in 1 year: 270C
- The average temperature in 1 day: 350C
b. Degree of Protection
c. Access to Compartments
1) Switchgear Compartment
This compartments meet the connection of cables, isolators, load
break switch (LBS), power breaker switch (CB), earthing switch, fuses
switch, measuring transformer and relays. Access to equipment
installed in this compartments is by way of opening the door or lid.
Access partially or completely into the switchgear compartment by the
operator shall be possible only if all the equipments that is connected
to the circuit outside the compartment.
Type of mechanical interlock must prohibit access to the switchgear
compartment if the conditions are not fulfilled:
• Switches (LBS, DS, etc.) on open positions/out
• grounding switch in the closed/in position
• Any conductive parts that are beyond the compartment is in the
event of grounding
Closing the door or cover is not possible to be done except grounding
switch in the entry/closed position.
However, the grounding switch must allow to be opened while the
door in an open condition.
2) Busbar Compartment
Closing and sealing of this compartment is securely installed and
cannot be opened unless the use of equipment (for example
tightening with hexagon-headed screw).
e. Control levers
The control lever for separator switch/ circuit breaker will be preferred
if on the top position when the switch is in position "closed" and the
low position when the switch is in a position to "open".
Energy required by the operator to operate the lever must not exceed
250N.
The direction of rotation of the crank shall be such a way as to not
stuck to the wall or to the opened door of the adjacent compartment.
The position of all the separation equipments/breaker shall be clearly
and automatically shown in the mimic diagram which must be
contained on the face of cubicles.
f. Control Mechanism
Control mechanism to separator switch/breaker, must be independent
manual operations type.
The operation of the separator switch/breaker must be done without
entering the switchgear compartment.
g. Information Label
Information plate indicating the function of the equipment contained in
the various compartments is installed in front of switchgear panels.
Information that indicates the open / close position and direction of
rotation for the CB, LBS, DS open/close operation and earthing
switches must be placed adjacent to the respective switches
concerned so that it is easily known by the operator.
h. Dimension
Minimum overall dimensions of a unit load breaker switch (LBS) are:
• High (Height) : 1600 mm
• Depth (Depth) : 1,000 mm
• Width (Width) : 500 mm
"Lifting lugs" that can be removed for cubicles following facility, must
be provided and installed on top of each cubicle.
6) 20 KV Cubicle Specifications
a. Incoming Unit Load Break Switches
1 set of 630 A busbar
1 LBS three-pole 24 KV with manual control:
1. Identifier flow 630 A
- Endurance flow of a short time of 1 second ≥ 14.5kA
- Capacity of Entry 31.5 kA
- The main active load breaking capacity 630 A
(Power factor = 0.7)
3 voltage Transformers
Ratio 15.000-20.000/100 V
S3 S3
Identifier burden 30-50 VA
Class of accuracy 0.5 (IEC 186)
3 TR Fuses for the phase and one link for secondary circuit
neutral. The fuse is placed in a cover
c. Unit Outgoing Load Break Switches
1 set 630A busbars
1 LBS three-pole 24 KV with manual control:
- Identifier flow... ... ... 630A
- Endurance flow short circuit time of 1 second... ≥ 14.5 kA
- Capacity of Entry ... . 31.5 kA
- The main active load breaking capacity ... ... 630A
(Power factor = 0.7)
- The breaking capacity of the cable charging 25A
7) Shop drawing
The Contractor is required to submit shop drawings as listed below for
approval before the panel in the fabrication:
a) Drawing of layout and elevation
b) Bill of Material
c) Wiring diagram
d) Details layout of the components within the panel
e) electrical characteristics of components
The Contractor is required to provide and install the rubber mat with
a size of 1000mm (width) and 6mm (thick). The length is adjusted to
the length of medium voltage panels.
b) Diagram of One Electric Systems Line
The contractor must provide drawings of Diagram of One Electric
Systems Line installed on glass frame and hang on the walls of the
room. The drawing of the diagram must be sized approximately
1000mm x 800mm.
c) Danger Signs
The Contractor is required to provide a "Hazard Sign" TM panels
room and the room entrance.
B. DISTRIBUTION TRANSFORMER
1. GENERAL
a) The scope of work of the contractor is a procurement,
manufacturer, factory testing, delivery, installation, testing on site
and commissioning for 20/0.4kV distribution transformers with
capacities as shown in the drawing .
b) The distribution transformer is to use copper windings (copper), oil
immersed type with Class A isolation system with natural cooling.
c) The transformer is used for this type of partner indoor.
2 SHOP DRAWING
Before fabrication, the Contractor is required to submit shopdrawing for
approval of MK / the Planner Consultant. The working drawings or shop
drawings to be submitted shall include detailed drawings such as:
layout,
elevations,
sections,
PT. PRAPANCA ENGINEERING TS - 141
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
detailed
schematic wiring diagrams.
3 CABINET
All cabinets must be made of steel plate with minimum thickness of 2
mm, or made of other materials such as polyester or Bakelite. The
Cabinet to "panel board" has the proportional size as required for the
panel board, which the amount is in accordance with the size of the the
planner drawing or by requirements so that for the number and size of
wire used is not too full / solid. The frame / framework of the panel
must grounded to the cabinet must be any good ways to install, support
and set the "panel board" and the lid. The cabinet with wires of "trough
feeders" must be arranged in such a way so that there is a channel
with a width of not less than 10 cm for branch circuit panel board. Each
cabinet shall be equipped with keys. For one cabinet shall be provided
2 (two) pieces of keys, with master key systems.
The high of panels must not exceed 2200mm.
4 BUSBAR / RAIL
Busbar must be of copper material which its outside layer is coated
with a layer of tin (tin plated) with a size in accordance with flow
capability of 150% of load flow installed which its size is adjusted to the
PUIL rules (list no. 630-DI-D4/PUIL-2000). All busbars / rails must be
painted and held by a strong and well isolator material into the
framework of the panel. All busbar / rails must be painted with colors
that match mentioned in PUIL. Paints must be resistant to a
temperature of 75 °C.
Busbar is prepared and held by insulator very well to system 3 , 4
wires as indicated in the drawing. Each panel must have an isolated
neutral bus to ground and a bare grounding bus clamped firmly on the
5. PANEL COMPONENTS
a) Air Circuit Breaker Motor Operated
- Current Rating : in accordance with planner’s
drawings
- Insulation Rating : 750 V AC, Voltage rating: 380
V, 50 Hz, 4 P
- Rated Breaking Capacity : in accordance with the
planner’s drawings
-Relay Thermic and magnetic over
current release, under voltage
releases, Auxiliary contact block
(2 NO +1 NC).
-Drive : Motor, 220 V, 50 Hz.
c) Current Transformer
- Insulation Rating : 600 Volt
-Class : 1.5
- I Therm : 60 x In
- Rated secondary current :5A
PT. PRAPANCA ENGINEERING TS - 143
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
• Frequency
• THD (per-phase, current and voltage)
ii) Energy Consumption Readings
• Accumulated Energy (kWh actual power, kVarh
reactive power, kVAh apparent power)
h) kWH - Meters
- Rated voltage : 3 x 380 Volt
-Ratedcurrent transformers output : 5 A
- Ocuracy class : 2.0
-Baseplate of moulded
plastic
- The register : 6 (six) cipher rollers
measurement double
i) Indicator Lights
Tubular lamp, 5-watt incandescent, 54 mm diameter
Color: Red, yellow, blue
j) Push Button
Panel mounting, double on-1, off-0. All push buttons are equipped
with indicator lamps to indicate system in the on or off.
k) Relays
l) Selector Switch
From the type of rotary switches, for switching. Rated voltage 380
Volt AC insulation 660 V.
6. DISTRIBUTION PANEL
a) Panel Construction
• Power and lighting Panels completed with all the components
that must exist as shown in the drawing . The panels intended
to operate on 220/380V, 3 phase, 4 wire, 50 Hz and direct
grounding and must be made to follow PUIL, IEC, VDE / DIN,
BS, NEMA standard and so forth.
• The panels shall be constructed of 2 mm thick iron plate with
iron frame and must be entirely in zinchromate and in duco 2
times and must be painted with fuels paint, color and the paint
will be determined later by the Owner or MK / Planner. Door
panels shall be equipped with a master key.
• The construction in the panels and the location of the
components and so on must be arranged in such a way so that
improvements, switching on the component can easily be
implemented without disturbing the other components.
• The size of each panel unit must be adapted to circumstances
and needs and has been approved by MK / Planners.
• Body of panels must be properly grounded
b) Panel components:
1. Accessories
2. Busbar
Each panel must have 5 busbar copper consisting of 3 busbar
of RST phase, 1 neutral busbar and 1 busbar for grounding.
The amount of busbar must be reckoned with large current
flowing in the busbar without causing the increase in
temperature greater than 70 °C.
Each copper busbar must be colored according to the rules of
PLN, where the busbar color layer must be resistant to heat
that arise.
Busbar is pure copper rod with a minimum of 98%
conductivities. Ampere rating is based on the drawing .
Busbar shall be painted in accordance with color code in PUIL
as follows:
• Phase : Red, Yellow and Black
• Neutral : Blue
• Ground : Green / Yellow
3. Circuit breakers
• Circuit breakers for lighting and outlet may use the
MCB with a breaking capacity of at least 6 kA symmetrical.
• others Circuit breaker must be of MCCB type, in
accordance with given the plan drawing in the breaking
capacity of at least 10 kA symmetrical.
• Circuit breaker shall be of automatic trip type with a
combination of thermal and magnetic instantaneous unit
D. CABLE
1) 20 kV Cables
a) General
Medium voltage cable that is used is single-core and multi-core
cables with isolation of "Cross Polythylen" from the outside copper
protective with PVC coating on the outside.
The working voltage is 12/20 kV.
The cable will be planted directly in the ground at a minimum depth
of 0.8 m or according to the requirements in PUIL 1987 and in the
pipe at the building entrance, or held in the trench cable provided.
The ability to do this cable current at ground temperatures is about
300C cm/w, at least:
Cross-section (m²) Ability (A)
95 260
c) Marking/Color
The surface cable color as signs for each wire are:
Phase: Red
Yellow
Black
Neutral: Blue
e) Fire proof layer thickness is minimum 0.14 mm, where the fire-
proof layer coating is wrapped with longitudinal system along the
cable, not with overlapping systems for at the time of the fire the
fire did not spread fast.
f) The flow conductivity power of FRC cable is based on the ambient
temperatures of 40ºC.
g) For the multi-core cable then between the cables must have filler
(filler) that are not spreading fire.
2) TECHNICAL SPECIFICATIONS
Fire Stop Materials are used to protect cables or prevent the spread of
fire through electrical cables and pipelines in the area of shaft and
aperture wall.
Fire Stop Material Systems planned has the following material
requirements:
- be flexible and easily disassembled at the time of the addition or
replacement of the new cable.
- No material properties which will remove dust.
- Resistant to vibration and not easily cracked.
- Non-toxic and odorless.
- Heat resistant up to 10000C
- No action or absorb water.
- Installation can be used in damp areas.
- Equipped with ROCK WOOL panels, raw density 140 kg/m 3 and
meets BS 476 Part: 4-1970, Temperature Fire max. 750 0C, the
resilience of fiber melting point is 10000C.
- Equipped with HISEAL.
PT. PRAPANCA ENGINEERING TS - 153
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
Covered and must be installed within the scope of work of Fire Stop
System of these materials, including:
a. Procurement and installation of fire stop materials, among others:
spaces of shafts and holes of Electrical sparing that exist at each
floor.
b. Installation and supervision are carried out by skilled personnel or
experienced experts from the factory.
c. Installation of Fire Stop Materials in Electrical shaft is made as
much as possible 2 (two) layers used in the Electrical shaft, the
thickness of the first layer is minimum 2 mm and so on.
F. CABLE TRAY
1) Hot dipped galvanized is accordance with BS 729 or colors powder
coating
2) Cable tray is perforated and is made from 2mm thick steel plate
(mild steel sheet)
3) Support / buffer of cacle tray must be installed every 1200mm and
150mm from each corner, a fork or riser
4) Cable trays must be grounded
G. CABLE LADDER
1) Factory standard, heavy duty type
2) Hot dipped galvanized
3) All components and auxiliary equipments must be manufacturer
standard and from the same manufacturer
4) Installation of cable ladder including cable clamps must be able to
sustain minimum of two times the weight of the cable attached
5) Cable ladder must be grounded
6) Cable Trays (hot dipped galvanized + colors powder coating)
H. INSTALLATION MATERIAL
1) The installation equipment in question is the materials to complete
the installation in order to obtain results that meet the requirements,
reliability and easy maintenance.
2) All cable clamps used must be made of manufacturer.
3) All cable connections must be made in the junction box / doos, the
cable must be the same color.
4) Juction boxes / doos that are used must be large enough and
equipped with a safety cap.
5) Boxes and switches to be installed on the wall of a brick wall is the
type of installation of entry / inbow (flush mounting).
6) Regular sockets (inbow) installed has 10A and 16A rating and follow
the VDE, 2Pin + E standards, while special sockets for indoor AC
split has 13A rating, 3 Pin standard BS.
7) Flush-box (inbow doos) to place switch, wall socket and push button
must be used of the type of blakely or metal material.
8) Wall boxes installed are 300 mm from the surface of the floor unless
otherwise determined by the Interior and the wet/damp spaces must
be water tight type (WP) while for the switch it is installed 1.500 mm
from the surface of the floor or in accordance with the drawing
9) The installation conduit of lighting and socket used is of the type of
PVC High Impact where the diameter in of the conduit is minimum
of 1.5 times of the diameter in (19 mm) or stated otherwise in the
drawing.
I. CAPACITOR BANK
1) The capacitor must follow the IEC 60831 standards, tests type is
carried out in accordance with the temperature of the D category
(maximum 55 ºC).
up to I49.
b) Parameter : - Manual programming on PF, c/k,
programming switching delay time, operating
sequence, number of output
- Automatic programming on C/K,
current transformer connection &
automatic adaptation to phase
rotation
c) Operating : - Circular
sequence - Selectable sequence 1:1:1: ..., 1:2:2:
..., 1:2:4: ... and any other customer
programmable sequence
d) Safety protection : - Automatic disconnection of all
capacitor when power outage
- Automatic disconnection of all
capacitor when high temperature
- Automatic disconnection of all
capacitor when over voltage and
under voltage
- Automatic disconnection of all
capacitor when over THDV%.
e) Alarm : - Alarm contacts and LED when not
achieving targets PF when all
capacitors are switched on in a
period of time
- Alarm contacts and LED when over
temperature
f) Switching delay time : - Switching delay time programmable
g) Saving function : - All programs and parameters saving
when power outage and insensitive
to harmonics
h) Mounting position : - Vertical mounting panel
i) Communication : - Modbus
3) TL LAMP COMPONENTS
a) Ballast
Non-dimmable electronic ballasts
Dimmable electronic ballasts.
Must be leak proof, has a lower working temperature, less
noise, low loss. For 2 (two) lamps it is arranged/used "twin-
lamp ballasts" 2 (two) ballast (anti stroboscopic).
Ballast shall be equipped with terminals connection.
b) Lamp Holder and Starter Holder
Lamp holders and starter holders are of white plastic material,
unobtrusive and touchproof. Lamp holders and starter holders of
contact vibration queue. Rating lock lamp holder type, with or
without starter socket adapted to home used.
c) Starter
Starter for fluorescent lamp has reliability. It is made from high
quality white polycarbonate. Rating starter is adjusted with
fluorescent lights rating.
d) Capacitor
As compensation for losses on the lights and get cos 0.95.
e) In all lighting fixtures must be made nuts and bolts as a grounding
terminal place (grounding)
Lamp house consists of 0.7 mm thick steel plate with the lid of a heat
resistant Acrylic material and has not changed the color of the light edge
using rubber to ensure impermeable.
Power : 20 Watt / 220 V, 50 Hz
Type : Square Round TL
5) WASHTAFEL LIGHTS
Grounding system implemented must be based on prevailing standards
and codes, among others:
Power : 1 x 20 Watt, 220 V
Type : complete square of heat-resistant acrylic cover and
do not change color. Its housing is fitted the rubber,
impervious to outside air and solid.
6) DOWN LIGHT
Housing aluminum cylinder, brown polycarbonate inside is equipped with
black bayonet fitting diaphragm and reflector. Lamp: PL-C 13 W and
PLC18 W.
lamp is still burning and otherwise for the emergency exit lamp or is taken
from a series of socket.
Technical Specifications:
Type : Maintained
Length : 2 hours
Lamps Power : TL 10 Watt Exit Lamp
Input Voltage : 220 V, 50 Hz
Power Consumption : 20 VA
Body : Epoxy coated zintec sheet steel.
Equipped with monitor charging current and battery can work for ± 5
years and given a minimum 2-year warranty.
8) STREETLIGHT
Housing made of fiber glass material
High quality methacrylic bowl
Aluminum Reflector
Light rays distribution diagram of CIE recommendations
Installation of glass Reflector is fastened with klips
Component (ballast, capacitor, etc.) can be easily installed and
removed
Lamp High Pressure Sodium (SON) 150 Watt
Forms / model are defined landscape
9) SPOTLIGHT
Housing is made of cast Aluminum
It is not easy rusty
High quality Aluminum Reflector
the heat-resistant tempered glass Cover will not crack
Gaskets rubber to hold the water jets and the IP 55dust enter
HPIT Lamp 1000 Watt, 2000 Watt
K. MOTOR STARTER
1) All electric motors shall be in accordance with DIN classification, both
in terms of protection, safety isolation, manner of operation,
installation and others.
2) For motors with a rating of:
• Up to 1.5 kW - 1 phase / 3 phases
• 1.5 kW and above - 3 phase
Except as otherwise provided by the manufacturer.
3) Selection of starter-motor is as follows:
• Direct starter for motor of 3.75 kW (5 HP)
• Star-delta open transition starter 5.5 kW (7.5 HP) up to 37.5 kW
(50 HP)
• Motor above 37.5 kW, start-delta closed transition, auto-
transformers or rotor resistance starter
• Starter variable speed drives (VSD) must be used for all ACMV
work pumps, plumbing or other works mentioned in the
specification.
L. GROUNDING SYSTEM
1) SCOPE OF WORK
a. Procurement and installation of body grounding system (touch
voltage) on all electrical appliances made of metal, namely: TM
panels, transformers, lighting panels, power and others.
b. Connection of the neutral grounding of the transformer terminal to
the grounding electrode.
c. Grounding system a maximum of 3 .
d. Connection of grounding system of Mesh/Loop with Bare
Standard
e. 70 mm ² copper conductors inside the conduit pipe leading to the
Rod electrodes in the control basin.
3) GROUNDING SYSTEMS
• The Contractor shall carry out this grounding work in
accordance the planning drawings.
• Grounding system uses multiple Electrodes Rods / Earth
Rod and interconnected with one another to form a relationship in
Mash.
• The Contractor must consider the condition of the existing
ground type resistivity in order to have a good grounding system.
M. INSTALLATION TECHNIQUES
a General
All cable used for electrical installations must meet the SNI
requirements. All cables / wiring must be new and must be clearly
marked on the size, type of cables, the number and type of its spun. All
cables with cross section more than 6 mm² must be made a twisted
(stranded). This installation can not use a cable with a cross section
smaller than 2.5 mm² except for the use of remote control.
Unless other requirements, the conductor used is of type:
• For the installations of lighting are NYM, all the installation of
lighting and socket using the 3 cores system where the third cores
are the grounding network. Its grounding is incorporated in the
panel.
• For the distribution cables and garden lighting by using NYFGbY
or NYY cable.
• For the installation of garden lighting / outdoor lighting cutting
the road must be in GIP conduit.
All installation cables in buildings must be in super high impact PVC
conduit adapted to its size, cable tray, cable trench, rack cable and
must be clamped.
It is used flexible conduit with the same material for connecting the
installation to each light fixture.
b. "Splice" / branching
It is not allowed the "splice" or the connections in both the feeder and
the branches except on the installation cable of lighting and socket.
Connections of the cable is made mechanically and must firmly be
electric by the ways of "solderless connector." Voltage cable types, the
type of "compression or soldered." In making the connectors "splice"
c. Insulation materials
All insulation materials for the splice, connection and others such as
rubber, PVC, asbestos, glass, synthetic tape, resin, splice cases,
compostion and certain others must be installed using an approved
manner according to the recommendation of government
representatives and/or manufacturer.
• End of the pipe cable included in the panels and junction boxes
must be equipped with "Socket/lock nut", so that the pipe is not
easily removed from the panel. If not otherwise specified, then any
cables that are at the height of the floor surface up to 2 m must be
included in the pipe. And the pipe must be clamped to the building
at each distance of 50 cm.
a. Switches
The switches must be of type of mechanism rocker with a rating of 10
A/ 250 V, the switch is generally installed inbow unless stated
otherwise in the drawings. If not otherwise specified, the switches
frame must be installed flush on the wall at a height of 150 cm above
the finished floor unless otherwise determined by MK. Switches must
be installed in the boxes and rings (standard). Connections are only
allowed between adjacent boxes.
b. Socket
Socket must be the type which uses earthing contact (2P + E) with a
rating of 10 A, 16 A, 25 A, 250 V AC.
All couples socket with a voltage of 220 V must be given a channel to
the ground (grounding). Sockets shall be installed flush with the
surface of the wall with a height of 30 cm from the top of the finished
floor or wall duct outlet according to the drawings of plans or the MK
instructions.
a. General
c. Lights
All fixtures must be equipped with lights and installed in accordance
with the terms and drawing s. For incandescent lamps uses lamp
holders and base type edison screw, for lamp holder types edison
screw should not be connected to a control center, unless required by
another. Fluorescent lamps must be of the type of cool white or
according to the planning.
All fluorescent lamps or other lights that need repair power factor must
be equipped with capacitor. In this specification the size of "microfarad"
of the capacitor for each light is not too stressed because of what is
needed is the end result of power factor to at least 0.95.
a. Cabinet
All cabinets must be made of steel plate with minimum thickness of 2
mm, or made of other materials such as polyester or bakelite. The
cabinet for "panel board" has the proportional size as required for the
panel board, which the amount is in accordance with the size of the
planning drawings according to the needs so that the number and size
of cable used is not too full /solid. Frame/framework of the panel must
be grounded in the cabinet it must be any good ways to install, support
and set the "panel board" and the lid. The cabinet with cables of
"trough feeders" must be arranged in such a way so that there is a
channel with a width of not less than 10 cm for branch circuit panel
board. Each cabinet shall be equipped with keys. For one cabinet shall
be provided 2 (two) pieces of keys, master key systems.
b. Finishing
All cabinets shall be painted with the color specified by the Planner/MK.
All the cabinets of the doors for electrical panels, shall be made
corrosion resistant by the way of "galvanized cadmium plating" or with
"zinc chromatic primer." In addition to the above, it shall be coated with
anti-rust coating that is as follows:
• The inside of the box and door.
c. Panel Installation
The installation of panels in such a way so that each equipment in the
panel can still be easily reached, depending on the kind/type of panel.
Then if it takes the base/foundation/leverage/hanger then the
contractor shall provide and install though it is not shown in the
drawings.
e. Name Board
PT. PRAPANCA ENGINEERING TS - 171
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
i. Measuring Tools
Each panel must be equipped with measuring tools such as in the
drawings. Meters are of the type of "moving iron vane type" specific for
the panel, with circular scale, flush or semi-flush, in a vibration-resistant
box, measuring 144 x 144 mm or 96 x 96 mm, with linear scale and
thoroughness of 1.5 %. Position of rotary switch for voltmeter
(Voltmeter Selector Switch) must be clearly marked.
j. Current Transformer
Current transformer is of the dry type, in the window type space with an
appropriate comparison with the precision of 0.3 with the burden in
accordance with IEC standards. The installation must be strong and
can withstand styles and mechanical when there occurred short
connection of 100 kA. The current transformer for Ampere-meter can
also be used in conjunction with kWH meter provided the accuracy is
still good. If it is not better then it must be used the special current
transformer.
k. Control Cables
Control cable from the panels must be installed at the factory /
workshop completely and bundled and protected against mechanical
damage. The minimum size is 1.5 mm2 of 600 Volts type.
l. Factory Brand
All safety equipments must be arranged one factory-made, similar
equipments must be moved to each other and exchanged its place on
the frame.
n. Pilot lamp
All of the surface lid of panel is equipped with:
Pilot lamp to declare the existence of R, S and T voltage.
Provision of the Pilot lamp mentioned above is a must, even in the
drawing s is not printed.
The colors for the pilot lamp:
• For R phase: red
• For S phase: yellow
• For Q phase: blue
1. GENERAL
The sub-contractor shall supply, install, commission, test and maintain the
20 kv switchgears, cables and transformers as herein specified and shown
on the drawings. Any item not mentioned but required for a complete system
operation shall be provided as part of the contract.
The supply will be obtained from the PLN / 20kv substation at ground floor.
The feeder cables between the consumer’s 20 kv switch room and the PLN
substation shall from part of the Contract.
The Contractor shall arrange for a,M.V. Licensing engineer to turn on the
consumer M.V. switchboards. All application and submission for supply of
electricity including any testing fees shall be paid by the Contractor, and
shall be deemed to be included in the contract price.
All work shall conform to this section of the specification and to the best
principles of modem engineering practice and be carried out by fully
competent tradesmen of appropriate grades.
All electrical equipment shall be of first grade quality with regard to design,
manufacture, installation and shall be completed for satisfactory operation,
control, maintenance and safety under all conditions of services.
2. QUALITY ASSURANCE
3. MAINS
The Contractor shall supply and install 20kv cables from PLN substation to
consumer’s 20 kv switch room. The cables shall be of the types and sizes
indicated on the Drawings.
4. MAIN EARTHING
The contractor shall supply and install main earthing conductor from the 20
KV switchboards and transformers to the main earthing system as
described in section Earthing System’.
The contractor shall supply and install all 20 KV main switchboards and
2Okv/400V transformers as shown on the drawing and in the positions
indicated.
6. 20 KV CABLES
The contractor shall supply, install and connect all 20 KV cables as shown
on the drawing, together with all manholes, trenches, cable ladders,
saddles, glands, etc, as necessary for the complete and satisfactory
installation. All 20KV cables shall be installed in accordance with drawings
Cables shall be of the types and sizes as indicated on the Drawings.
7. TESTING
Labelling shall be carried out to the satisfaction of the Engineer and to the
requirements of the supply Authorities.
1. H.V.SWITCHGEAR
All high voltage switchgear shall be of the indoor type rated at 20KV with a
short circuit interrupting capacity of not less than 500 MVA for 3sec. They
shall be manufactured to suit tropical atmospheric conditions with
temperature range of 24°C and humidity range of 65% to 95%.
2. CONSTRUCTION
All switchgear cubicles shall be of sheet steel construction with folded edges
bolted together, modular type, totally enclosed and be of factory standard
design, Each cubicle shall be capable of fixing onto another cubicle without
any major alteration, Each cubicle shall be partitioned into compartments to
accommodate individually the following :
3. SAFETY SHUTTERS
automatic shutters which covers the exposed fixed contacts as soon as the
breaker track is withdrawn shall be provided. The operation of the shutters
for the upper and lower fixed contact shall be independent of each other so
that each individual set can be manually opened.
Tee busbar shutter shall be painted ‘SIGNAL RED” and labeled with
“BUSBARS” in large white letters. Circuit shutters shall be painted “LEMON”
COLOUR.
4. EARTHING
5. BUS-BARS
The high voltage bus-bar shall be of minimum rating 630A at 20KV. The
bus-bar shall be constructed to withstand any electro-mechanical stress
under normal condition or under fault condition of up to a maximum of
55OMVA for 3 seconds. All bus-bars that that penetrate into the wall
partition of adjacent cubicle shall be insulated by cast resin wall bushing
isolators mounted on the opening of the partition walls.
The high voltage circuit breaker shall be of SF-6 type and fuse bad break
switch for transform protection.
service, position — in this position the breaker is ready for operation test
position — in this position, the breaker can be operated and tested
engaging the live contacts.
isolation position — in this position, the breaker cannot he engaged at
all.
Positive interlock facilities shall include but not be limited to the following
The breaker cannot be withdrawn when it is in the ‘closed’ position. The
breaker cannot be pushed into the serve position when the breaker is
engaged in the closed position or if safety shutters are not un locked.
All high voltage circuits shall be protected for over current and earth fault
Current transformers shall be of the cast encapsulated type capable of with
standing the voltage level and short-circuit currents
One set of metering CTs shall be provided to PLN under this Sub-contract
Metering CTs shall be of class 0.5 and 15 VA.
Over current and earth fault relays shall be solid state electronic type They
shall be mounted with a switchgear cubicle and have a glass window door
panel for observation. The relay casing shall be dust proof and relay
removable from the front for easy replacement. The relay cover shall
incorporate a reset button so that re-setting is carried out without opening
the cover. Light emitting diode indicators shall be provided to indicate the
type of fault and the phases at fault. All indicators shall be visible without
opening the switchgear cubicle door panel. The tripping contacts shall be of
approved material and capable of repeated operation without deterioration.
The relay shall conform to BS 142.
8. PROTECTION SYSTEM
The 20KV panel shall have the following protection 4 nos. Over current
protection and I no. earth fault relays. Over current protection relays shall be
9. SUBMITALS
Submit for the approval the engineer the following drawings before
manufacture of the equipment
Reports of all the tests in accordance with BS 5311 and any other tests
required by PLN shall be provided prior to shipment to site for review by the
Construction Management and PLN.
(d) Tapping - +5% at step of 2.5% on HT side with of toad, tap changer.
Tap-changer shall be by external hand well and padlocked. A tap
position indicator shall be provided.
(f) Total iron and copper losses at full load shall be less than 1 %
(h) BIL-95KV
2. TRANSFORMERS ACCESSORIES
Special Accessories
- N2 Filling Valve
- Pressure Relief Valve.
- Pressure Vacuum Gauge.
- Pressure Relive Device c/w Contact.
- Radiator Fans.
- Radiator Valves.
- Winding Thermometer.
- Terminal Box.
(b) Billboard.
Data to be published on the billboard are
- Transformer type.
- Factory Name
- Serial number.
- Year of production.
- Nominal price voltage, frequency, current.
- Market diagram.
- Short circuit voltage on nominal current.
- Cooling type.
- Total weight.
- Oil Weight.
- Certificate.
3. CONSTRUCTION
The transformer shall be of totally filled or oil immerced type and shall be
self cooking and indoor use type. The transformer shall be equipped with a
truck with plain wheels for travel length ways or side ways.
4. MAGNETIC CORE
5 WINDINGS
6. MECHANICAL VENTILATION
(a) HV Side
3-pole cable box suitable for the reception of a 3-core 150 mm sq.
XLPE/SW A/PVC 20 KV cable descending vertically from cable
ladder. Termination shall be insulated by head-shrunk rubber. All
exposed termination shall be insulated or shrowded to the
satisfaction of the Engineer.
(b) LV side
4-pole cable box suitable for the reception of copper cable.
1. 20KV CABLES
All high voltage cables shall have a minimum rated voltage 20KV, X-linked
polyethylene insulated, single wire armored and PVC sheathed, suitable
for installation in cable tray, manufactured to BS 5467, All cables runs shall
be straight through without joints and where cables are subject to bending,
a minimum bending radius of 18 times the cable diameters shall be used.
All cables when cut shall have the ends sealed immediately unless
plumbing follows subsequently. After installation of the whole system, the
cables shall be subjected to the pressure tests of 76KV
The contractor shall carry out a short circuit calculation and prove to the
Engineer that the Contractor’s choice of cables is correct.
(a) CONDUCTORS
The conductor shall consist of compacted circular (class 2) stranded
annealed plain copper wires in accordance with lEO Pub 228.
(c) INSULATION
The insulation shall consist of extruded cross linked polyethylene
(XLPE).
The average thickness shall be not less than the specified nominal
value.
The minimum thickness or any point shall not fall below the nominal
value by more than 0.1 mm plus 10% of the nominal value.
(f) LAYING-UP
The screened cores shall be assembled together with non-
(h) Armour
The armour shall consist of one layer of galvanized steel wires. The
nominal diameter of each wire shall be 3.15mm. A suitable binder
binder tape may be applied over the armour at manufacturers
discretion, if necessary.
3. TEST
4. PACKING
The cable shall be wound onto non-returnable strong and seaworthy reel
lagged with wooden or steel battens.
1. GENERAL
All work shall conform to the specification and to the best principles of
modem engineering practice and be carried out by fully competent
2 SUPPLY
3. MAINS
The contractor shall supply and install 380 V mains from the secondary
terminals of the transformers to the LV. switchboards. The main shall be of
the types sizes indicated on the Drawings.
Supply and install main earthing conductor from the L..V. switchboards to
the main earth system as described in section ‘Earthing System.
Supply and install all L.V. main switchboards (380V and 220 V) as shown on
the drawings and in the position indicated.
The construction of the switchboard shall be in accordance with section L.V.
switchboard & Distribution Boards. Equipment shall be of the manufacture
and ratings specified on the drawings.
Supply 5% spare H.R.C. fuse cartridges of the type and rating installed.
8. EARTHING
All L.V. equipment and exposed metal parts shall be effectively earthed in
accordance with section ‘Earthing System”.
All light fittings shall be earthed. All metal clad switches shall be earthed.
Wire and connect all light fittings as shown on the drawings. Switches shall
be shown on the Drawings and/or as specified in “Light Fittings Installation”.
The Contractor shall be responsible for checking the lighting layouts against
structural plans and other services prior to the installation of trunking,
conduits, and lighting fixtures so that conflict of light fittings with structural
members and other services can be avoided.
Balance the loads throughout the installation to the satisfaction of the supply
Authority and the Engineer. Phase balancing shall be carried out in stages,
when the building is partially occupied and when fully occupied.
Calculate and check the maximum demands for all submains and cables,
etc., from the information given about equipment to be connected and check
the rating of all cables, circuit breakers, switches, etc., accordingly notify the
engineer immediately of any discrepancy. Check that the voltage that drop
shall not exceed the limit of 5% for final circuits from the main switchboards.
Minimum size of cables shall be 2.5mm2 copper conductor for lighting, 2.5
mm2 for general purpose socket outlet, 2.5 mm2 earth continuity cable, 1.5
mm2 copper conductor for control wiring, matering and indicating lights.
Each lighting circuit shall be served by a separate neutral wire.
13. TESTING
The Contractor shall carry out such tests on the installation as may be
required by the supply Authorities or the Engineer and shall provide all
instruments, labour and materials necessary for such tests.
Each switch, power outlet and equipment shall be fitted with a circuit
identification disc, numbered to indicate the distribution board and circuit.
1. SCOPE
This section of the specification covers the general requirements for the
switchboard cubicle when called for else where in this specification or in the
drawings.
2 GENERAL REQUIREMENT
3 SWITCHBOARD CONSTRUCTION
(d) The L.V. switchboard shall comply with BS 5486 Part 1 class 3 with type
test certificates issued by an independent and approved test authority.
(e) The sheet metal for constructing the switchboard shall be specially
selected, dead flat mild steel not lessthan 2mm thick. The panel shall be
built up on substantial framing with all necessary stiffeners and supports
with no cross struts. The entire panel shall be vermin proof.
(g) Front access doors shall be provided and back of the panel shall be
provided with hinges and lockable handles to facilitate inspection and
maintenance. Removable gland plates shall be provided at the top and
at the bottom of the switchboard with knockouts or blanked off openings
for incoming and outgoing circuits cables.
(h) All doors shall have concealed hinges and where necessary, shall be
interlocked with the switch mechanism. All doors shall be provided with
dust excluding gasket of neoprene or equal and approved material.
(k) The LV. switch board shall be supplied with an integral channel iron
plinth of not less than 100 mm in black.
4. BUSBARS
(e) For rectangular section busbar, connections shall be made with double
split cast brass clamps. Drilling of the bars will not be permitted unless
approved by the Engineer.
(g) Notwithstanding the above, all conductors between the busbars, circuit
brakers and fuse switches shall be high conductivity copper bar,
having a current rating of not less than that of the fuse switches to
which they are connected. The conductors shall be coloured to BS
colour code for phase identification.
(i) Atinned copper earthing strip of dimension not les than 150 mm2 shall
be provided for the full length of the switchboards and sufficient
provisions shall be made for earthing connections of all electrical
circuits. It shall be effectively connected to all metal parts other than
current carrying conductors.
(a) Air circuit breakers to be provided shall be of triple pole or four pole as
specified on the drawings. The circuit breakers shall be rated at 41 5V
and certified by type tests by ASTA to 50 KA short circuit breaking
capacity and the rated short time withstand of 5OKA for 3 second for
ACB or MCCB of above 1600A and 4OKA for 1 second for ACB or
MCCB for 1600 and below.
(b) The circuit breakers shall be of metal clad, flush mounted, air break,
horizontal drawout type and comply with B.S. 4752: Part 1.
(c) The circuit breakers shall have a sufficient short circuit performance.
(d) The design shall be such that the main contact pressure increases
with heavy through-fault currents. Auxiliary arcing contacts shall be
provided to protect the main contacts from burning during the
switching operations. All contact parts shall be readily replaceable.
(f) With hand charged spring mechanism, the springs shall not be
discharged until the spring has been fully charged and the means of
charging has been removed or disconnected.
(i) All air circuit breaker shall be equipped with the following as shown on
the drawings:
One single element I.D.M.T,L. type relay for unrestricted earth fault
protection with 10% - 40% plug settings to B>S> 142 (for the incoming
ACB and where shown on the drawings).
(j) The tripping mechanism shall be stable and its operation shall not be
influenced by shock or vibration. The design of the trip plunger shall be
such that its action is instantaneous once the trip circuit is operated.
Shunt trip coils operated by power supply from the mains shall not be
used. A separate D.C. power pack c/w 30 V nikel cadmium cells
batteries and booster trickle charger unit shall be used for shunt trip
coils. The batteries under fully charged condition shall be able to
maintain a minimum of 20 times consecutive tripping.
(k) Individual are chutes shall be provided on each pole of the breaker.
They shall be so designed that any are caused by the opening of the
breaker under maximum fault condition shall be contained in the are
chute the
6. CURRENT TRANSFORMERS
(a) current transformers shall comply with B.S. 3938 of the ‘straight
through’ type and shall be rated for Class B temperature rise and a
primary voltage of 600V.
(f) Current transformers provided in polastic casings and of the split core
type will not be accepted.
(h) Current transformer shall have an accuracy not less than Class I for
measuring and metering and Class lOP 15 for protection.
with open circuited secondary and full load current flowing in the
primary.
7. PROTECTIVE RELAYS
(a) Except where otherwise specified, protective relays shall comply with
BS. 142.
(b) Plug selection design shall be such hat the 50% to 200% plug setting
can be changed on load without open-circuiting the current transformer
and the highest current taping point will automatically be selected
when the plug is removed.
(c) Draw-out cases finished in phenolic black shall be provided for flush
mounting of the relays. A contact shall be fitted which shall short circuit
the associated current transformer on withdrawal of the relay.
(d) For I.D.M.T, overload protection relays, three single phase units shall
be arrange in one horizontal plane in accommodated in a common
casing. Earth fault relay shall be separately accommodated.
(f) I.D.M.L. earth fault protection relay shall have adjustable current
setting of 0-1.3 seconds at 10 times current setting. The relay shall be
of GEC CDG, Reyrolle TJM or equivalent.
(h) Relays shall be housed in dust and vermin-proof accessible cases with
viewing glass.
(I) Operation indicators shall be provided for each protective element and
installed within the same relay. The relay shall have a common hand-
reset devise openable without opening the relay case.
(j) The relay contacts shall be capable of making and breaking the
maximum current which my occur under fault conditions in the circuit in
which they are connected.
8. AMMETER
(a) Ammeters shall be of moving iron type class 1.5 accurancy to B.S. 89
industrial and be capable of carrying their full load current without
undue heating and shall not be damaged by the maximum fault levels
of the switchgear.
(c) Mechanical zero adjustment shall be provided and accessible from the
front without dismantling.
(d) The ammeters shall give direct readings without application of any
multiplication factors.
9. VOLTMETER
(a) Volt meter shall be of accuracy class 1.5 and have expanded scales.
The arrangement, scale deflections shall be approved prior to
assembly of the associated switchboard.
(c) Other requirements shall be as per the applicable clauses specified for
ammeter.
(a) The voltmeter selector switch shall be mounted on the front of the
panel and shall be of the rotary type with break-before-make contacts
for selection to measure red-yellow, yellow-blue, blue-red and red,
yellow and blue phase voltages with RY, YB, BR, R-N, Y-N, B-N
marked clearly on the switch.
13. BATTERY
14. FUSES
(a) HRC cartridge fuses to BS 88: Part 2, Class Qi shall be supplied, ASIA
certified.
(b) The voltage rating shall be 415V 50Hz. The rated breaking capacity of
fuses shall be 89 KA at 415V 50Hz.
(c) All live terminals and contacts shall be effectively shrouded and it shall
be possible to change fuses with the circuit alive, without danger of
contact with live part.
(a) The automatic transfer switch shall comprise a pair of circuit breakers.
Air circuit breakers shall be used for automatic transfer switch. The
pair of circuit breakers shall be the mechanically held type,
mechanically and electrically interlocked to exclude any possibility to
paralleling the normal and standby sources. Operations of circuit
breakers shall be by individual momentarily energized solenoid
mounted on each breaker. The solenoids shall be operated at D.C.
supply.
(b) To ensure continuity of service both circuit breakers shall have two
stable positions, closed and open. It shall be possible to manually
operate the circuit breakers in the event of the absence of control
voltage.
(c) The circuit breakers shall have a neutral position with both breakers in
the open position. It shall be possible to lock each breaker in this
position.
(d) The front panel of the equipment shall be provided with indicating
lights to indicate closed and opened status of each breaker.
switches.
(f) The three phase sensing circuits shall be provide on the main busbar
of switchboards. Failure of one or more phases of the incoming supply,
or a reduction in voltage to less than 60% of normal, shall initiate a
timing device adjustable in the range 0 to 15 seconds. If the failure
persists at the expiry of this pre-set time delay, a signal shall be
initiated to start the engine of the standby generator. When power
becomes available from the generator, the changeover contractor shall
operate with an adjustable time delay between 0 to 15 seconds to
transfer the essential load to 9 the generator supply.
Control and auxiliary relay shall be to BS 142 and shall be plugin type,
rack-mounted, provided with cable connection sockets and anchored by
quick fastening vibration-proof devices as required where deemed
necessary for proper operation of the Circuit Breaker or starting
equipment. The switches of the relays shall be double break, easily
accessible for maintenance and have adequate current rating to carry the
connected load.
(a) “Volt-free” contact shall be provided as required for the use of other
trades for external control, alarm or indication circuits.
(a) All instruments and equipment shall be securely mounted and all
internal wiring runs shall be so positioned as to insure complete
accessibility for servicing purposes.
(b) All internal wiring shall be PVC insulated, neatly bunched, run on
supporting cleats or insulators and shall be coloured and adequately
labeled or sleeved for identification. All control wiring shall be 1.5 mm
mm. Copper cable and shall terminate on the ‘Klippon” or similar
approved system and shall incorporate loops to permit the opening of
doors and removal of components for inspection without disconnecting
the cables.
(c) Where control necessitates the use for a battery supply, DC wiring
shall be totally segregated from the mains system.
(d) All terminals shall be shrouded and adequately labeled with cautionary
signs. All circuits shall be provided with removable links/fuses to
facilities isolation, checking and maintenance.
(a) Capacitor bank shall be used as the power factor correction equipment
and shall be connected to the public supply section of the switchboard
as shown on the drawing.
(b) The capacitor shall be dry type.
(a) All drawing covering the design and construction shall be prepared to
the satisfaction of the engineer.
(b) During the construction of the switchboard, a factory engineer from the
licence’s work shall be required to visit the local plant on at least two
different occasions and to inspect the quality and workmanship of the
locally made equipment. Upon completion, a final insfection will be
made by the factory engineer to certify that the completed control
panel is in accordance with the approved drawings, and that the
standard of materials and manufacture fully comply with type tests
requirements.
21. DISCRIMINATION
(c) Where circuit protection devices are not provided with earth leakage
detection they shall be arranged to trip on earth leakage by means of
the over current protection by ensuring a low earth fault loop
impedance in accordance with the PEE Wiring Regulations.
The tenderer shall provide sufficient dry contacts and terminals, etc. in the
switchboard for interfacing with the remote control System as detailed on
the Drawings or as specified.
23. TESTING
(a) The following tests shall be included, but not be limited to, at the
manufacturer’s workshop during the course of assembly and on
completion immediately prior to transport to site.
(b) After the transport and erection of the switchboard on site, the
following test, but not be limited to, shall be also be carried out
(c) The following commissioning inspections and tests, but not limited to,
shall be carried out before the switchboard is put into normal services.
Voltage tests between any two combination of each phase, neutral and
earth.
• Phase sequence tests on each outgoing units.
Function checks, specially on the controlling devices.
1. GENERAL
All work shall conform to this specification and to the best principles of
modern engineering practice and be carried out by full competent
tradesmen of appropriate grades.
All electrical equipment shall be of first grade quality with regard to design,
All work performed under this contract shall comply in every respect with
15 th Edition of lEE Regulations, Rules and Regulations of all Local
Authorities having jurisdiction over the installation.
The LV. distribution system originates at the main L.V. switchboards as
shown in the drawings.
2. SCOPE OF WORK
This section sets out the requirements, methods, materials and standards
of workmanship in connection with the L.V. electrical distribution system of
the work defined below and as indicated on the drawings.
3. CABLE INSTALLATION
this section of the specification covers the general requirements for the
supply, installation, testing and commissioning of all cables that are
required for the complete installation of the electrical system.
All the main power cables involved in this sub-contract are shown on
the drawings and the Contractor shall provide all the necessary trays,
ladders. conduits, supports and cables trunking, glands, shrouds, and
boxes, clamps, compounds, specialist tools, etc., necessary to install,
terminate and connect the cables in accordance with good engineering
practice.
All cables shall be provided with identification labels at each and at all
positions where cables change direction. In cases where cables are of
multiple runs, labels shall be provided at 10 m intervals. Labels shall
be copper disc engraved to show the size of the cable and the fed
equipment.
Not with standing the above the Sub-contractor shall install the cables
in accordance with the lEE. Wiring Regulation.
The Sub-contractor shall keep all cables entirely separate from pipe
work associated with other services. No direct contact shall not be
permitted between the cables and such pipes.
The Sub-contractor shall satisfy the Engineer that all labour employed
in the installation of the cables shall be competent and have been
properly trained in the methods of installations as recommended by
the cable manufacturers. Final cable termination to the motor
equipment shall be coiled in ordered to avoid excessive vibration being
transmitted to the cable termination.
PVC insulated PVC sheathed copper cables (PVC & PVC) shall be of
single core or multi-core with full neutral and shall be 600 V/I 000 V
grade complying to B.S. 6364:1969.
PVC insulated steel wire armoured cable (PVC/SWA and PVC) shall
be 600V11000 V grade complying to B.S. 6346 :1969 multi-core with
full neutral. The cores of these cables shall be high annealed copper
conductors complying with B.S. 6360 :1969.
The minimum bending radius shall be not less than eight times the
overall cable diameter.
All wiring shall be carried out by the loop-in system and the wiring shall
For copper cables sizes 6mm and above, compression type cable
connect~r/7Ugs shall be used for all cable terminations. Where
apparatus is fitted with tunnel type terminals, stranded cable
conductors shall be tinned solid for direct connection to such terminal.
If for any practical reason different termination method is used, prior
endorsement must be obtained from the representative of Engineer.
Connections to electric fixed equipment shall be by means of PVC
cables in conduits, with the final connection being made by PVC
covered pliable conduit, and suitable adaptor. A separate earth
continuity copper earth in accordance with lEE. Regulations and B.S.
6004 of not less than 2.5 mm shall be provided outside the flexible
tube and solidly connected at each tube termination.
(a) All fused switchgears and isolators shall be heavy duty type
conforming to the requirements of B.S. 5419. All contact are to fully
shrouded and are to have a breaking capacity of 35 KA.
(b) The fuse links for fuse-switches and switch fuses are to high
interrupting capacity, cartridge type conforming to B.S. 88, or B.S.
1361.
(d) The enclosure shall be of totally enclosed type, made of heavy gauge
sheet metal, adequately rust protected and finished in ename. An
earthing terminal shall be provided. The enclosure shall be suitable for
conduit, trunking and armored cable entries and also for connection to
busbar chamber from top or bottom. Frames sizes for the range of
switchgear shall be kept to a minimum.
(e) The switchgear shall be of quick-made and quick break type and the
switching operation shall independent of the speed of the manual
operation. An interlocking device shall be provided such that the front
cover of the switchgear cannot be opened when it is at the ‘ON’
position.
Similarly it shall not be possible to close the switch with the door open,
except that provision shall be made for authorized persons to defeat
the mechanical interlock for test purposes, and close the switch with
the door in the open position.
(g) The ‘ON’ and ‘OFF’ position of all switches and isolators shall be
clearly indicated by a mechanical flag indicator or similar device.
(h) Switch and isolator operating handles shall be retractable into the unit
when the switch is either the ‘ON’ or ‘OFF’ position.
(I) In T.P. & N. fused switches or switch fuses units bolted neutral links
are to be fitted. For single pole and neutral switch fuses and isolators,
the neutral conductor is to be taken through a bolted link. Breaking the
neutral conductor is to be taken through a bolted link. Breaking the
neutral conductor, either with linked or non-linked switch will not be
permitted.
5. BUSBAR CHAMBER
(a) The busbar chamber shall be constructed incompliance with B.S. 5486
Part 1, 1977 with full neutral consisting of electro-tinned, hard drawn
copper busbar of appropriate size insulated by porcelain supports or
other approved insulation material spaced at 600 mm intervals. The
enclosure shall be made of 2 mm thick mild steel and, epoxy powder
paint finish to B.S. 4800.
(c) The front cover and end plates of the enclosure shall be removable
and normally held in position by captive, non-metallic screws.
(e) Busbars shall be so arranged that all conductors can be brought onto
the bus without undue bending. Each busbar shall be coloured in one
position or labeled to indicate the phase to which it is connected.
(g) Conductors between the bus bars and switchgear shall be copper
cable with cross sectional area not less than that of the outgoing cable
from the switchgear.
and shall be fully type tested by ASTA for with stand capacity of 50 KA
for 3 second. Locally made busbar chambers are acceptable provided
ASTA certificate is available.
(c) Tray supports shall be spaced according to the number and size of
cables being carried on the tray, but nowhere shall they be at greater
than 1.3 m intervals.
(d) Cables mounted on the trays shall be laid after installation of the tray
and spaced in accordance with the LEE. Regulations to avoid derating
of the cables, Cables shall be grooped in circuits and individually
clipped, cleated or tied at intervals of not less than 2 m lengths on
horizontal runs and 1 m lengths on vertical runs, using insulated type
or equal and approved fixing.
(f) Cables leaving cable trays shall be installed properly without damage
to cables by cutting edges of trays and rubbers pads shall be inserted
to underside of cables,
(g) Trays shall not be bent for change in direction of run. Proper bends or
straight trays meeting at angle shall be emplyed at change of direction.
Cable trays shall be supported at either sides of junction.
(h) Where trays are exposed to the weather, they shall be coated with
epoxy resin before painting, PVC coating is not acceptable.
(i) Cable lader shall be fabricated from formed good quality hot dip
galvanized mild sheet steel of not less than 1 .60mm for sizes up to
150mm by 150 mm and not less than 2.00 mm thickness for larger
(j) All bends, crosses are to be purpose made, length of cable ladder
shell be jointed together by means of suitable fixing plate complete
with copper earth bonding terminal.
7. CONDUIT SYSTEM
(a) Conduit
The contractor shall supply and install under neath slab all PVC
copper cables into conduit, unless otherwise specified herein or shown
on the Drawings.
All conduits and fittings used in the installation, flexible conduits, shall
be PVC high impact class, screwed.
All conduit and conduit fittings shall be erected complete and swabbed
through with approved drawtapes and absorbent cloths before any
cables are installed. The swabbing operation shall be carried out to the
satisfaction of the engineer or his authorized representative.
MOB distribution boards shall be of two types. Viz. type 1 and type II.
Type I MOB distribution boards shall be suitable for accommodating
single-pole MOB Sonly while type Il MOB distribution boards shall be
suitable for accommodating, in any combination, single-pole and multi-
pole MCBs.
All type Il MOB distribution boards shall each be provided with mould-
case, triple-pole and neutral incoming switch disconnector having
rating not less than that of the supply side protection device.
The metal front plate assembly shall be of sheet steel and shall be
finished to the same colour as the distribution board enclosure. The
front plate shall be screwed on the enclosure, making the assembly
suitable for both surface and flush mounting. The front plate shall be
affixed with labels for circuit identification.
The single pole and neutral busbars for type I MOB distribution boards
shall have current ratings of not less than 100A while type II MOB
distribution boards shall have triple-pole and neutral busbars rated at
not less than 200A. The configuration of the busbars, busbar supports
and mounting arrangements shall be type tested and certified for a
short time withstanding current of not not less than 6 KA for 0.2
second at a Voltage of not less than 380V.
The configuration of the bus bars, busbar support and the busbar
mounting arrangement shall be type tested and certified to a short-time
withstanding current of not less than 14 KA in the case of boards with
busbar rating 225A or above, or the prospective short circuit current
which can occur at the point of installation whichever is the largest for
0.2 second at a voltage of not less than 380 volts.
Each distribution boards shall be provided with spare ways for future
expansions. Each spare way shall be blanked off with a suitable
blanking plate having a finish comparable to that of the distribution
board.
9. SWITCHGEAR
(a) Switchgear shall include all metal clad switches and circuit breakers
Switch Fuse
Switches
Changeover switch
Automatic transfer switch
(b) The switchgear shall be Triple Pole with neutral (TPN), Single Pole
with Neutral (SPN), Double Pole (DP) or Triple Pole with Switched
Neutral (TPSN).
For DP and TPSN, the neutral pole shall make first and break last, and
shall only be used when specified. Switchgear shall be of surface
mounting or flush mounting type suitable for switchboard installation as
per specified:
(c) All switchgear shall have ratings as specified and carry continuosly,
make and break the rated current without any overheat or damages.
(d) Switchgear shall be dust and vermin-proof. For outdoor application the
switchgear shall be inlockable weather proof enclosures complete with
3 sets of keys. For applications in damp, wet or humid area such as
pump room, chiller plant room etc., damp-proof and flash-proof type
shall be used.
(f) All switchgears shall have a quick-make and break action suitable for
both AC and DC application. With the exception of MCCB, MCB and
ELCB which are totall~r erctc~ed~ switchgear shall be completed with
removable phase barrier contact shrouds, and arcquenching devices.
All switchgear shall equipped with spring accelerating mechanism to
ensure positive ‘on’ and ‘off’ and ‘trip’ shall be perrnantely provided.
The front operating handles of switchgear (except circuit breaker) Shall
be chrome palted, extensible and not protruding more than 75mm from
the cover.
Externally the switchgear shall be finished with gloss grey paint and
internally in matt white paint. All paint shall be synthetic enamel and air
drying type. For plush mounting type, the finishes shall be same and
uniform as the cubicle and other components.
(h) Earth terminal shall be provided for all metal clad switchgear. All
hinged or removable doors shall be earthed by flexible earth tape to
the earth terminal.
(b) The body and base of the units are to be moulded bakelite, or similar
material, and the units are to be sealed after assembly.
(c) The load handling contacts are to be silver/tungsten and the contacts
and operating mechanism so designed as to give a wiping action both
at make and break.
(f) Miniature circuit breakers shall comply and be type tested to B.C.
3871. The followings is the minimum requirements for short circuit
duties:
- Single pole breaker 5KA
- Triple pole breaker 8KA
(g) MCB with current carrying contacts of plug-in type shall not be
acceptable
(h) Cable terminals of the MCBs shall be at top and bottom of the unit with
access from the front and suitable for terminating the size of solid or
stand conductor in accordance with table 6 of BS 3871:Part1.
(i) Positions of the breaker operating dolly are to be clearly indicated for
‘ON’ and ‘OFF’.
(J) All cable and busbar terminations shall be sweated and tinned prior to
connection to M.C.B. terminals.
(a) General
MCCBs shall be four-pole, triple pole or double pole, independent
manual closing air brake type they shall be totally enclosed in moulded
casing formed from an insulating material. The construction of the
MCCBs shall comply with and the type tested to BS 4752: Part 1.
Rated short circuit braking capacity not less than 5OKA for use in main
switchboard or indicating in drawing and 22 KA for lateral sub main
installation or the prospective fault current at the point of installation
switch ever is greater. MCCB short circuit performance shall be
minimum category P-i.
(a) Fuse switch shall be metal clad and type-tested in accordance with
Table VI of B.S. 5419:1977 The rated fused short-circuit current shall
be 50 KA.
(b) Fuse switch shall be of continous duty and shall be capable of closing
onto and remained closed on a fault without overheating and damage.
(C) Fuse link shall be high rupturing capacity cartridge type to BS 88.
(d) Live contact shall be shielded from the front so that fuses can be
replaced without damage.
13. SWITCHFUSE
(a) Switch shall be metal clad and type-tested in accordance with table VI
of B.S. 5419: 1977. The rated fused short-circuit current shall be
5OKA.
(b) Switch fuse shall be of continuous duty and shall be able to be closed
onto and remained closed on a fault without overheating or damages.
(c) Fuse link shall be high rupturing capacity cartridge type to BS 88.
rewirable fuse is not permitted to be used.
(d) Live part shall be shielded from the front so that fuse can be replaced
safely.
14. SWITCHES
15. CONTRACTORS
(c) The rated operational voltage shall be 380 + 6% volt, 3 phase. 50 hz,
or 220 + 6% volt, single phase, 50 Hz. The rated power and quantities
of the contactors shall be as indicated on the drawings.
(d) Both the mm and auxiliary contacts shall be rated for uninterrupted
and intermittent duty. The main contacts of the contactors shall be
silver or silver-faced.
(e) Two spare sets of NC and NO contacts shall be provided in addition to
the contacts used.
(a) The automatic transfer switch shall be a twin unit consisting of two 4-
pole contractors (1 NC & I NO) in compliance with BS, 5424 :1977 or
lEO 15-1 2 nd Edition 1970.
(b) Automatic transfer switch for load transfer between normal and
generator supply shall be with double relay control. On detection of the
failure of the mains supply by the rated voltage from the emergency
generator by the voltage sensing relay, the contractor shall be
automatically changed over.
(c) All contactors shall be enclosed and ventilated metal casing; arcing
shield or suitable are quenching device shall be provided to minimize
and confine arcing; contact surface shall be of sintered alloy or other
suitable metal.
(e) The solenoid coil shall be rated at continuos rating complying with B.S.
764: 1954 and suitable for 220 V single phase 50Hz system.
(f) The twin unit shall be both electrically and mechanically interlocked to
prevent the normal and emergency sources prom parallel operation.
(g) Indicating light showing to with source the switch is connected shall be
provided.
(h) Spare voltage free auxiliary contact shall be provided, minimum 2NC
and 2N0 for each contractor unit.
(a) Bus bar chambers with rated operational currents above 400 A shall
be type tested to a short time current capacity equivalent at last to that
of the incoming switchgear and type tested to the rated operational
current.
(b) A bus bar chamber shall contain 4 sets of fully sized, hard drawn
copper bus bars electro-tinned and supported on epoxy resin or other
approved insulators. The bus bar chamber shall be totally enclosed
and manufactured from sheet steel suitable rust proved and painted or
hot dip galvanized. The front cover and end plates shall be removable
and normally held in position by non ferrous metal screws.
(c) Each bus bar shall be colored to indicate the phase to which it is
connected. Coloring shall comprise a band of paint in one position on
the shall not be painted throughout its length.
All wiring shall be arranged in a regular manner with bends set at 90o and
securely held in position with suitable clips and where convenient shall be
installed in the up right and/or backstays.
Meter wiring for the switchboard shall be carried out in PVC insulated
cable of not less than 1.5mm2. All meters wiring shall be of similar colour
to those of respect ~ vebusbars to which connections are made. The cable
terminations shall be made with approval lugs.
1. SCOPE OF WORK
This section out the requirement, standards, workmanship and the extent
of work in relation to the supply, installation of electrical accessories, light
fitting, wiring and switching etc.
2. WIRING SYSTEM
3. LIGHTING
(a)General
carrosin.
All ballasts shall be naturally cooled polyester filled type with class a
insulation complying with BS 2818: 1981.
All starters shall comply fully with BS 3772 :1981. The canister shall be
made of electrically safe and non-corrosive material capable of
withstanding high temperatures. A ceramic disc type radio interference
suppression capacitor shall be fitted internally to each canister, waxed
paper and foil type capacitors will not be accepted. All capacitors shall
comply fully with BS 4017 : 1979 and shall be suitable to correct power
factor to not less than 0.85 lagging.
All fluorescent lamps except those under dimmer control will be the
energy saver (high efficiency) type with the following minimum
maintained lumen output (after 2000 hours operation).
Special for all l44 (lobby, colour corrected lamps refer to incandescent
fluorescent lamps similar to Philips colour 54)
The adjustment nuts and bolts of the luminaires that wifl be mounted
high on buildings or coloumns shall be captive to prevent luminaire
mounted at high position dropping. The luminaires installed in such
locations that are within hand reach shall bestrongly contructed, fitted
with an impact resistant transparent or diffusing cover, an shall have
secret key fixings for the cover to the body of the luminaires. Where
necessary, wire quards shall be fitted over the cover to give extra
protection.
Metal parts such as cover plates for adaptable boxes, blanking plate
for any boxes and conduit pendants, etc. Shall be painted white or a
suitable colour to match the interior finish of a particular location.
5. ELECTRICAL ACCESSORIES
(a) General
Fuse connection unit shall comply with BS 1363 and provided with 2A
to 13A cartridge fuse link having earthing facilities for connections to
the metal work of current appliances being fed.
The cable connection unit shall be flush mounted type with terminal
blocks suitables for fixing onto the BS 4662 box. PVC insulated and
sheathed cable with circuit protective conductor shall be used from the
unit to the appliance served.
B.S.3676 and rated at 10 apms. AC. circuit load shall not exceed 8
amps. For tungsten type lighting fittings and 6 amps. For fluorescent
type lighting fittings.
(g) Switches
Engineer.
The time control unit shall be plug-in type and shall permit instant
removal and replacement without disturbing the wiring. The unit shall
be supplied complete with a socket block which shall be permanently
secured and wired into position.
The time switch shall be off spring reserved type to maintain the clock
mechanis to continue to function of power supply, the motor shall
restart and quickly charge the spring to fully charged condition.
The time switch shall have a viewing window in the front cover for
visual checking of the moving mechanism.
(a) The Electrical Contractor shall supply and install a complete final sub-
circuit wiring system including commissioning and testing of the work
as shown on drawing and stipulated in this specification.
- Transformer rooms
- Switch rooms
- Pump rooms
- All areas where there are false ceiling in office areas. Cable shall be
attached to messenger Wires.
- All area with the expection of the areas as specified in items above
(surface conduit wirings)
- All public area, staircase.
- All toilets
- Security alarm and remote control system.
(c) The position of each light fittings as shown on the Drawings are for
guidance only, the Electrical Contractor shall check the Architectural
Drawings (or Reflected Ceiling Plan) for the exact location off each
light fittings before the conduit wirings.
(d) The Electrical Contractor shall also supply and install a complete final
sub-circuit wiring system throughout each office floor as indicated on
the layout plan. This include all the lighting points, power socket
points, connection points and spare unit etc. as shown drawings.
(e) Provision of TPN MCB distribution board shall be provided for each
office floor. Sample of distribution board should be submitted for
approval prior to ordering.
1. EARTHING INSTALLATION
All metal work associated with the electrical installation but not forming fart
of a live conductor, including exposed conductive parts, shall be solidly and
effectively bonded and earthed in accordance with the latest edition of the
LEE. Wiring Regulations and the British standard codes of practive CP
1013.
Earth electrodes shall be in rods of mild steel inner core with a bonded hard
drawn copper selve of an approved type. The overall diameter of the rod
shall not be less than 12.7 mm and the thickness of the copper sleeve shall
not be less than 1 ohm. The minimum length shall be 2.4 m. Additional
lengths, whenever required, shall each be of I .2m, connected together by a
coupling. The penertrating end of the rod electrode shall be a hardened
steel point.
In case the earthing resistance achieved by bone rod is not sufficienctly low
for the purpose required, additional length or additional rods shall be driven
into the ground outside the resistance area of the other rods. A mutual
separation of 3,5m is required.
Earth resistance ~ 10 must be achieved.
For wiring system using PVC insulated, PVC sheated cables, the circuit
protective conductor of every ring final circuit shall also be run in the form of
a ring having both ends connected to the earth terminal ar the origin of the
circuit.
5. LABELLING
The size of lettering shall be 6mm and the laminations shall be green white
green.
(a) The sub contractor shall supply, install, test, commission and set to
work an ear-thing system as shown on the drawings and specified
herein.
(b) Earth pits shall be provided by Main Contractor. The contractor shall
liaise with the main Contractor in determing the exact locations of the
earth pits on site.
(c) All switchboard shall be fitted with tinned copper earth bar over its entire
length to which the building main earth network shall be connected.
(d) All distribution boards shall be fitted with tinned copper earth bar over its
entire length to which the building main earth network shall be
connected.
1. GENERAL
2. SCOPE OF WORK
This section includes supply & install lighting head, down conductor,
earthing control, testing and repair during maintenance period of the
complete lighting system according to this specification and also the
arrangement of the permit from the~ authoritative body (safety department).
3. AIR TERMINATION
The mast shall be adequately supported on the Antenna of the building and
shall be sized to withstand wind velocities of up to 120km hour. Support by
4. DOWN CONDUCTORS
The sub-contractor shall supply and install down conductors in the location
shown on the Drawings.
The down cable shall be coaxial with one conductor placed coaxially with a
second conductor, each conductor placed conductor of 50mm of copper. I
The insulation medium between inner and outer conductor shall have a 1/50
microsecond impulse withstand not less than 209 KV.
The coaxial cables shall be located at least 600mm away from any other
cables. Manufacturer’s instruction shall be strictly adhered to during
installation.
5. TEST LINES
The sub-contractor supply and install test links in the down conductor. The
test links be of phosphor bronze and shall be located in an easily accessible
position for testing.
No joints and bonds in the systems, except at test links, air termination shall
be allowed.
7. EARTH TERMINATION
8. TESTING
All tests all shall be carried out in accordance with the British Standard
Code of Practice OP 362 :1013.
All tests shall be carried out in presence of and to the satisfaction of the
Engineer.
9. TRENCHING
Trenching where required for running the lighting earth connection leads
shall be excavated to a depth of 1 meter.
The trench shall be back filled and compacted with earth to its original level.
1. GENERAL
The equipment shall comply with B.S. 1850, IEC 60831-1 (1996), IEC
60831-2 (1995) and the admissible ambient temperature shall be ranged
from 0°C to 45°C.
2. SCOPE OF WORK.
On the whole the scope of work will cover supply, install capacitor bank
complete with accessories material and testing commissioning.
3 CAPACITOR SPECIFICATION
The capacitor shall be dry type metal film capacitor and provided with and
adequate discharge circuit. The residual voltage shall be reduced to 50V or
less within one minute after the capacitor is disconnected from the source.
1. GENERAL
2. SCOPE OF WORK
(a) Installation inside internal conditioned space, the external surfaces of all
equipment, fitting and services including supports, hangers and
brackets shall be painted.
(b) All sheet metal control cabinets, switchboards and contribution board
enclosures and similar shall be painted internally and externally.
(d) The requirement for painting of all pipework, conduits etc, is in addition
to the colour coding or banding specified in this Specification.
(f) Galvanized metal work installed in false ceilings, bulk head and vertical
ducts.
(h) Bearing surfaces, slides, adjusting screws and any surface that is
required to be unpainted for the correct operation or adjustment of the
equipment.
3. PAINT MATERIAL
Before ordering any primer, under coat and finishing paint, the Sub-
contractor shall propose the color scheme to the satisfaction of the
Engineer.
The Sub-contractor shall select all finishing and painting materials from
types suitable for the surfaces to which they are applied and for the
environmental conditions in each area.
Steel plate and all rooled steel sections including brackets and support not
galvanized, shall be given an application of cold phosphating compound
before being prime coated with red zinc chromated primer. Steel pipes and
conduits delivered to the site unpainted shall be prime coated as specified
for steel plate.
All galvanized or zing coated steel surfaces and all non-ferrous surfaces
shall be given and application of PVB/Zinc chromate self-etching primer
before being prime coated as specified above.
5. FINISHES
Each finishing coat shall be of a different shade. The final coat shall be left
smooth, even and free from the visible brush marks and other defects.
For surfaces which shall operate below 9°C, the finishing coat shall be high
grade alkyd enamel.
The entire ‘ength of piping, cable enclosures and conduit installed in the
following locations shall be painted :
Plant rooms.
Piping in trenches.
Piping in the underground floors and in vertical ducts.
• Wherever exposed to the weather or to view.
All piping, cable enclosure and conduits installed in ceilings and similar
concealed spaces have the identification colour applied in bands spaced at
6 metre centres except that ground colour bands shall be provided adjacent
to branches, junctions, valves, floors and walls (both sides).
All supports, hangers and brackets, where associated piping or duct work is
to be finish painted shall be painted to gloss finish of colour black.
6. LABELS
The front plate of each switch socker or socket or control switch feeding an
essential circuit ao a fixed electrical appliance, such as water heater,
cooker, wall-mounted fan, exhaust fan, room cooler, etc., shall be engraved
according to the appliance being controlled. Detail of the inscription shall be
submitted to the Engineer for endorsement.
7. SCHEDULE OF COLOURS
Pipe works:
a. Identification - B.S. 1710 :1984
b. Color coding - B.S. 4800 1981
pipes up to 50mm nominal diameter, and in block letter not less than 40mm
high for larger pipes.
Identification bands shall be located where they ere clearly visible in each
room or compartment through which the pipe runs, and shall be placed at
centers not exceeding 6m.
Prevention and installation of Fire stop System complete with material, such
as fire seal and supporter/complementary which must be procured, will have
a function to protect the cable or to prevent the fire spread through the
electric cable.
Places where the cable will pass through on every floor are electric and
telecommunication at office.
The requirements for the raw material/material of the fire stop system are
- Heat-resistant up to 1000 degree of Celsius within 2 hours,
- No Flame point.
- Flexible and there is no difficulty when changing or adding new
cable.
- All the materials have no characteristic to be dusty.
- Shock/tremble-proof/not cracked.
- Not consist of asbestos.
A. GENERAL REQUIREMENTS
1) Commissioning of the equipment must be carried out by the
Contractor together with experts from the relevant manufacturer or
supplier. Commissioning must also be coordinated with other work
disciplines.
2) Commissioning experts from the relevant Contractor must be
experienced and trained in their field. Qualifications of
commissioning experts must be submitted to MK / the Planner for
approval.
3) Testing of all installations must be carried out either in per-
area/part as well as a whole to indicate that the Contractor's work
has been carried out in accordance with the requirements in
technical specifications.
4) All equipments, including supervision personnel and other
personnel for commissioning must be prepared by the Contractor.
All equipments must be calibrated the accuracy and must be
approved by MK / the Planner prior to the commencement of
commissioning.
5) All the commissioning results must be recorded in test record
format. The Contractor shall submit testing procedures and test
records format to MK / the Planner for approval. At the completion
of commissioning and prior to final inspection and handover, the
commissioning results must be submitted in a form that has been
recorded (bounding) to MK / the Planner who have the authority to
witness the execution and commissioning procedures as required.
PT. PRAPANCA ENGINEERING TS - 255
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
6) Testing shall follow the related PUIL, ISO or other standards, such
as the British Standard (BS) and the Australian Standard (AS).
7) All testings must be witnessed by MK / the Planner and, in the
circumstances to do routine / type test at the manufacturer, the
Contractor shall inform a minimum of 14 days in advance for that
purpose.
8) All equipment testing results must be bundled in a format
approved by MK / the Planner and submitted in triplicate (3).
The Contractor shall include in the tender all the costs associated
with commissioning and testing work including all works of repair
of damages that may occur when the testing is required and if
necessary re-testing. Such costs must also include the cost of
equipment for commissioning and testing.
C. FACTORY TEST
1) MK / the Planner has the right to review and examine the electrical
equipment which is in fabrication to ensure that the equipment is in
accordance with the standards and requirements as specified in
technical specifications. The electrical equipment requires tests to
be performed in the presence of MK / the Planner to prove that the
equipment meets the requirements of this specification. All costs
incurred in carrying out tests at the manufacturer must be included
in the cost of the Contractor.
2) The contractor is required to submit immediately to MK / the
Planner in writing, in 3 (three) triplicate, a list of all equipments both
local and imported which need to be inspected and tested are
witnessed by MK / the Planner prior to the equipment will be sent
to the project site.
3) Upon completion of manufacture, or prior to delivery to the project,
all intended device materials and equipments must be inspected
and tested before MK/the Planner. Tests are conducted in
accordance with the needs and requirements of MK / the Planner.
4) The Contractor shall be responsible and ensure that MK/the
Planner has been notified in writing at least a week before the date of
the test.
D. FIELD TEST
way reduce the contractor from the obligations to carry out tests
assigned to submit a test certificate.
8) If there are errors or defects that arise during the maintenance
period in one plantroom, its equipment or installation, MK / the
Planner has the right to ask the contractor to carry out further tests
to isolate errors or defects that are occurred and then prove that
the errors or defect has been repaired.
I. POLARITY TEST
It is implemented in accordance with the directions on PUIL 2000 or AS
NZS 3017
A. GENERAL
1) All materials, equipments and safe and reliable lightning protection
system components shall refer to the BS EN 50 164standard
2) All lightning rod and grounding work must be carried out by
specialist subcontractors who have expertise in their field and
minimum of 10 years experience.
B. SCOPE OF WORK
The scope of work of the contractor is the design, procurement,
installation and testing of protection systems / lightning rod and
grounding as set out in the drawings and technical specifications.
D. MATERIAL
The main components of lightning protection system are:
• Termination water
• Down Conductor
• Clamps, Clips and Furseweld Exothermic connections Test Joints
• Earth Termination c/w earthing loops
E. INSTALLATION
1) The installation of all the conductors and components must be
correct, so that the work that has been already done does not
damage the appearance of the buildings, while still considering the
necessary checks and maintenance for such buildings stand.
2) All components must have adequate mechanical and electrical
characteristics and was chosen to achieve a minimum lifetime of 20
years. All materials must be prepared to obtain approval from
MK/the Planner.
3) Planning of lightning protection can not only ensure the protection
of buildings from the downward stroke only, but also flashes upward
into consideration the height position of the building. The design
must have the principle of a Faraday cage to protect humans and
equipments in the building, as well as flashes from the side is not
allowed.
F. TECHNICAL REQUIREMENTS
1) Termination Water (Terminal Trunk)
2) Down Conductor
The number of conductors conductivity connecting the conductors
conductivity shall be installed as shown in the planning drawings.
Each delivery down to the room or the roof of the building using
coppers having the high productivity with the size of 25mm x 3mm,
in accordance with BSEN 13601 or can also use aluminum tape in
accordance with the BS 2898-1350 standard, drawn from the roof of
the building to fall into any grounding termination on the ground
floor, with connections in parallel so as to avoid pressure from large
electrical currents during the process of lightning current delivery.
Each conductor conductivity must be securely installed with a
distance of 1m, and is connected with the termination of grounding,
and shall be able to withstand the mechanical pressure during
channeling the lightning. The copper ribbon or aluminum used as a
conductor conductivity must have the same size as the conductor
on the roof. The conductors conductivity shall be installed on a
regular basis around the column structure of the building.
PT. PRAPANCA ENGINEERING TS - 263
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
The precise method and requirement of carrying out tests on the installation
shall be agreed with the engineer and shall meet with supply company’s
requirement. The following are minimum tests that shall be carried out by
the Contractor after the installation has been completely erected and
connected up (except for those equipment which tests have to be carried
out before connection is made) on site.
sample tests records to the Engineer for approval within I month of award of
contract. The Contractor shall notify the representative of the Engineer a
minimum of 7 days in advance of tests to be carried out so that witness of
the tests can arranges properly.
All instruments, tools, materials and labours required to perform these shall
be provided by Electrical Contractor.
All control circuit, automatic change over operations and interlocks shall
be tested for correct operation. Checks for ease of rack-in and rack-out
all with drawable equipment to be carried out.
• All power cables and risers shall be tested at 2KV for one minute.
All power cables and risers shall be tested for insulation with a 1000
Volt megger. Insulation values shall be obtaines between conductors
and ground and between phase; and before and after the pressure
tests.
The resistance to earth of the main, and any auxiliary earthing systems
shall be measured, both at the earthing electrode position, and at the
main switch/switchboard.
Insulation Resistance/tests of Completed Installation (lEE Reg. 613-5 to
8)
Tests required are show in the able below-
Minimum
Insulation
Tests Conditions of Tests Resistance
The contractor shaD carry out any other tests that may be required by
the Engineer or the local supply company. All the costs for these tests
shall be deemed to be included in the sub-contract prices.
Test reports of site test shall be submitted to the Engineer within 7 days
from the date of testing carried out.
(1) A cover giving the name of the development the title of the
document the name and address of the installation contractor
(2) Inside page giving similar information to the cover but including
contact telephone numbers for normal and emergency use
D. SERVICE
The contractor shall undertake to provide a comprehensive breakdown
service whereby a qualified electrician attends to breakdowns as soon as
practicable after a breakdown is reported and carries out immediate
remedial work during the defect liability period.
Where the contractor fails to attent the plant, with six (6) normal working
hours of notification of a break down and where remedial work is
interrupted during normal working hours for purposes other than obtaining
replacement parts prom the nearest source, the representatives of the
Engineer reserves the righ to order such action as may reasonably
expedite completion of remedial work at the contractor expense without
abrogation of the contractor’s responsibilities.
E. PREVENTIVE MAINTENANCE
The Contractor Shall carry out regular inspections at periods not exceeding
one calendar month, and shall fully service all plat installed under this
specification within the Defects Liability Period, and during that period.
(3) Check all phase loading and phase balance the circuit if required.
(4) Service all circuit breaker, switches, socket outlets, swith panels
starters, motors, transformerts etc. and check their proper
operation.
(6) Check the proper functioning of all control circuits, sensing and
1. SAFETY REQUIREMENTS
The contractor shall allow for the following items related to safety in switch
rooms.
The contractor shall provided in the main L.V. switch room- ‘as installed’
single line diagram framed behind glass.
The diagram shall be not smaller 1000 x 800.
2. SPARE PART
(a) The Contractor shall include in his tender an itemized priced list for the
supply and delivery of spare part recommended by him for the
continuous operation of the plant for a period of two years, The spare
parts listed in spare parts schedule may be ordered in part or not at all.
The contractor shall undertake that in the event of a contract being
placed with him the itemized list of prices will remain valid for a period of
12 months from the date of acceptance of tender.
(b) All spare part supplied shall be new, unused interchangeable with the
The entire ‘ength of piping, cable enclosures and conduit installed in the
following locations shall be painted:
(c) All cases, containers or other packages are liable to be opened for such
examination as Engineer may require and packings shall be designed to
facilities opening and subsequent repacking/
3 TOOLS
(a) A complete set of all necessary tools shall be specified by the Contract
to enable any action, dismantling or testing to be carried out any part of
the plant by the purchaser after the work have been take over, whether
of an electrical, mechanical or any other nature. The contractor shall
ender take that in the event of a contract months from the date of
acceptance.
(c) Any tools ordered together with the contract shall be dispatched at the
same time as the plant.
(d) The shall not be used for the erection of the equipment being supplied
and must be handed over the purchaser in a completely new and
unused condition, should the contractor require any such tools at site for
erection, he should provide his own.
(e) The tools provide shall included special tools and auxiliary equipment
required for to the operation and maintenance of the switchboard and
generator. All tools shall be supplied in suitable tool boxes complete
with a list of parts contained in each box.
1. GENERAL
b) Operator Consoles;
c) Power Source;
f) The types and nos. of telephone sets specified below and shown on the
Drawing
2. SCOPE OF WORK
d. Conducting the entire system test so that the said telephone system can
function exactly and rightly.
e. Arranging the license for testing and the connection of the said
telephone system with Telecommunication Company.
h. Holding the maintenance for the system including the supply of spare
parts for minimal of 3 (three) years.
Conducting training to the personnel who will use the telephone system.
v) Automatic attendance.
vi) The system support paging (pager) and local GSM — expandable.
4 OPERATOR CONSOLE
5 POWER SOURCE
The equipment required for power source shall include batteries, rectifier
and enclosure. The batteries shall be of the Nicad in a transparent
polystyrene case with clad positive plates and paste negative plates for a
total of 48V and with a capacity of 100 AH or minimum 6 hours operation.
The rectifier shall have a capacity of 70 A and be of full wave bridged
metallic silicon operated type with a rated input of 380V AC, 50 Hz, three
phase and having rated output of 48V DC. Both batteries and rectifier shall
be mounted in the same cabinet.
6 MDF
The MDF shall be of floor mounted, metal (2 mm mild sheet steel) enclosure
type and be same dimension as Supply cabinet. Test and arrester springs
shall be provided
7 SYSTEM REQUIREMENTS
a) System Capacity
b) Numbering Schema
c) Operator Console
e) Telephone Sets:
Both of desk and wall type DTMF push button telephone sets fl Testers
Connecting from the Perumtel junction box to main distribution frame and
also TBT (Terminal Box Telephone) and to the final outlets, etc. shall be by
this contractor.
All cables shall be labeled at each end showing where the cables are
connected at the other end.
Multi-pair cables connecting junction box, main distribution frames and TBT
shall be labeled with sandwich type plastic sheets with letters engraved on
the first layer. The plastic sheets shall be tied to the cables nearby the end
by releasable cable tie (type RELIOO by Heller Mann Insulin). The words
engraved shall indicate the type of the cable (number of pairs), to which
terminal boxes it is connected (at both side) and the number of terminations.
Empty conduit with draw wires shall be provided by this Contractor panel
from the TBT’s to the outlet points as shown on drawings.
10 CONTRACTOR REQUIREMENTS
(c) Provide a letter from the telephone company confirming acceptance and
compability of the proposed system, prior to contract award
(e) Submit proposal for total system maintenance for a two-year period
which is to commence as soon as the one year period of maintenance
expires.
(f) Guarantee system and all components for a period of one year which
shall begin at date of substantial completion.
(a) Carry out additional service work required to ensure the correct
operation, performance and function of the telephone system.
(b) Check and ensure that the whole system is working properly.
The Contractor must provide, at its own expense, all equipments and
personnel which is necessary to conduct the trial. The installation work is
considered as finish if it has been tested by the Telecommunication
Company (Perum Telkom)
and is acknowledged as good.
13. WARRANTY
All work, material and equipment must be guaranteed within 360 (three
hundred and sixty) days. All equipments, material and work, which is not
good must be quickly replaced or repaired by the Contractor, without
additional expense and must of the same brand name/type of material.
The Contractor must enclose in the proposal about the list of the address of
PT. PRAPANCA ENGINEERING TS - 285
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
1. GENERAL
c. Contract is to ensure that the system installation completed with the local
authorities requirement.
.
2. STANDARD / REGULATION
All materials and installations should meet the requirement / standard from
NFPA (National Fire Protection Association) UL listed (USA) and
requirements of Fire Extinguishers from local Government.
3LIST OF MATERIAL
4. MANUFACTURER
5. SAMPLE MATERIAL
For all materials and equipment the Contractor is required to obtain the
Construction Management approval.
6. COORDINATION
8. SCOPE OF WORK
The scope of works include all items for the system to function as specified
including but not limited to the below item :
a. GENERAL Requirements
b. Drawings
In the Tender Documents, the drawings in the planning which include the
work scope of fire alarm installation work are drawings coded with EF.
Contractor shall check the design against the possibility of errors /
incompatibility in terms of electrical quantities as well as installation and
the like. The above matter must be in writing or the drawings submitted at
the time of tender bidding orientation / aanwaijzing. Before the work is
submitted entirely or in stages, Contractor shall submit to MK 3 (three) sets
of drawings to be called "as built drawings" which are drawings of all
materials and Fire Alarm 3 installation.
d. Standards / Regulations
All materials and installations in this work must meet the General
Requirements for Electrical Installation (PUIL) 2000 SPLN and
international standards for Fire Alarms Systems, applicable in the Republic
of Indonesia.
e. Material List
At the time of bidding, Contractor must include / attach the "Material List”
which should be more detailed, listing all the material that will be installed
later in this project and all according to the requirements in the
specification.
In the Material List, name of manufacturer of brand and type must be
mentioned, complete with brochures/ catalogs or any other information on
specifications regarding technical working voltage, power frequency,
physical dimensions, etc.
g. Material Samples
Pertaining to the materials mentioned below, prior to installation,
Contractor must show the material samples to MK / Planner for approval.
If deemed necessary by MK / Planner, and it may be possible, Contractor
is obliged to show the samples to MK / Planners. If the samples are
rejected by MK / Planner, Contractor shall then, for approval, replace and
show that it is in accordance with the specifications.
Technical quality / power, brand / manufacturer, physical characteristics of
work, and aesthetic quality of work of the material samples as well as
installations that have been approved, is binding.
Procurement cost of material samples are the responsibility of and for the
account of Contractor. Material samples must be submitted to MK /
Planner at not more than 14 (fourteen) calendar days after issuance of the
SPK.
If there are clauses in the Tender Documents mentioning the items / other
paragraphs it does not mean eliminating these items but more so to
emphasize the matter.
If there is a contradiction between the drawings or to specifications, then
as a benchmark, technical or highest cost consideration should be taken.
i. Claim Waiver
Project Owner is exempted from all patents and the like for all kinds of
material procurement and setup. Owner is free from any claims or charges
against special rights such as patents and the like.
j. Coordination
Planner give directions in order to get results in line with the installation
requirements.
l. Built-in Insert
Contractor shall provide all "insert" and other additional equipment which
are needed to be immersed in concrete and other installations.
m. Grounding
n. Finishing
All materials installed must already be in a good finished state as required;
finishing after installation is a requirement and this includes all
improvements the said materials and other works, resulting from
installation works which include: repairing, repainting, cleaning and the
like.
All equipment of the fire alarm which are visible such as a conduit pipe
which are not implanted, manual call, bell, signal / location lamp, fire-
fighting units and the like, must be finished in red paint, or another paint
color according to MK’s approval.
o. Warranty
All installation work and the relevant equipment must be guaranteed
working perfectly. All works are included in the scope of this job should be
given free maintenance for a period of 1 (one) year.
After the period of free maintenance, Contractor may submit a proposal to
have a maintenance contract to Owner, unless otherwise specified by
Owner.
p. Training
a. Scope of Work
Encompassed within the scope of work and fire alarm and fire extinguisher
installation is to provide, fix, test / trial-run, all the fire alarm installationand
fire-fighting; as specified in the job description below and shown in the
drawings planning.
The scope of work here means that the unit must work well for each part
as well as the entire installation that is attached as a whole unit.
• Procurement and installation of the Master Control Fire Alarm, Fire
Detector, Manual Call, Alarm Bell, Signal / Location Lamp, Siren and
wiring installation.
• Procurement and installation of Addressable Module Box (AmB) and
accessories Procurement and installation of fire extinguisher units.
• Conducting trial-runs and testing all installation as well as
demonstrating how fighting units are used.
• Board will indicate the availability of manual push button fire-fighting
units, the place / direction of escape hatch / ladder hazards (fire
escape).
• Making of cabinets / panels for fire extinguishers, alarm calls, and
buttons at the places specified.
• Contractor must assure task giver that the work is carried out by
experienced staff who will follow standards determined.
• During installation, Contractor must deploy an expert who always
supervise the job execution.
• Contractor must replace damaged material to meet physical and
technical requirements.
• Contractor shall ensure cleanliness of work area i.e. free of any pieces
of wood, wire, metal resulting from boring into walls / concrete or the
like.
• Contractor shall conduct testing, start-up and demonstration if need
d. Power Supply
Voltage that may be applied is the DC voltage of not more than 100 V
voltage generated by the rectifier. In an emergency or PLN power supply
loss, batteries which can serve system for 4 (four) hours should be used.
The batteries must be Nickel Cadmium (NiCad). Battery capacity and
rectifier system must be according to performance and fire alarm
installation as a whole.
Supply must be not more than 100 V. DC, indoor type. Bell is fitted into the
building and must have enough frequency to overpower the noise level at
medium level. Installation of alarm bell is placed according to the location
approved by MK.
Indoor type, mounted on either a wall or door. Supply should not be more
than 100 volt DC.
Installed outdoor, in open areas, parking or the like, complete with poles.
Have sufficient frequency to be heard clearly either in buildings or other
place.
Addressable Control Panel and Module Box (AmB) is in the wire rack /
cable tray.
• Each floor inside the building is served by an Amb located in the panel
space. To connect each AmB at each floor with Fire Equipment
Master Control, 3 TP 2 cores cable 18 AWG is used, placed in the wire
rack / cable tray, clamped on the shaft wall.
• For installation system of AmB into manual call box fire detector or
bell, HIS cable size 1.5 mm ² is used and placed into the PVC pipe
conduit, installed above the ceiling.
• For installing the wiring in series, tap point each fixture at the end of
the installation, using the End Of Line Resistor.
• Each deflection / bifurcation / continuation must use junction box,
strongly mounted on each holder, clamped onto a wooden frame or
the like.
• For pipe conduit, junction box is embedded in the concrete, walls or on
the floor.
• Contractor shall coordinate with Field Supervisor / MK to place it
before casting.
• For fire extinguisher, the fixed type unit is hung on hanging holder,
mounted onto the wall anchor, or placed in the provided and specified
fire hydrant closet. Or placed as specified by MK and adjusted to field
condition.
• The signboards must be made of iron plate, 0.8 mm thick plate size,
adjusted according to number of alphabets in yellow, red primary color,
legible from a minimum distance of 10 m for normal eyesight.
• Contractor shall conduct testing on all installations and fire alarm
equipment, to be witnessed by Project Owner / his representative,
Planner, MK.
In the testing process, Contractor must guarantee all results of his
work with a report / warranty stating that the work done is according to
tender offer and additional attachments and that all installations are
working properly and perfectly.
Hence, the Licence on Use Worthiness from the Fire Department
(DPK) is the responsibility of Contractor.
General
PT. PRAPANCA ENGINEERING TS - 295
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
Indicating LED”s shall be provided in twin pairs , the other shall still be
able to indicate the alarm at reduced illuminated.
The ilimuninated light on the panel must be capable of being turned off
until the alarm inititing points have been restored to normal.
The panel shall be provided with a buzzer which shall sound when any
alarm is received ,A buzzer isolating key witch shall be provided on the
panel for acknow ledgement purpose.
A buzzer shall be provided at the status panel which shall sound when
any alarm is actuated.
A buzzer isolation key switch shall be provided on the panel to enable
the operating staff to isolate the buzzer at his sole discretion.
“Power Supply ON” indicator, green.
“System On” indicator, green.
“Battery On” indicator green.
A push button I key switch for lamp testing.
The charger shall have facility for manually operated boost charger,
capable of re-charging the batteries from fully discharged to fully
charger condition in not more than eight (8) hour.
The unit shall be suitable for use on a 220V A.C. 50 Hz single phase
supply and shall automatically maintain the 24 V nickel cadmium
batteries in a stat approximate to full charger and at the same time to
compensate for the standing load.
The batteries shall be capable of maintaining the system for not less
than 24hours and then be able to operate in the “alarm” condition for all
bells for not less than 2 hours.
Fault indication shall be given in the status panel when any one of the
battery charger is faulty or when the D.C. voltage is low.
The heat detectors shall have a status indicating LED for visual
supervision. When the detector is actiated, the LED shall lacth on
steady and at full
brilliance. The detector shall have auxiliary relay and connections for a
remote LED alarm indicator.
Where the detector is fixed inside hidden places such as false ceiling
voids, remote indication lamps with decorative base plate shall be
provided and mounted at ceiling level or high level directly under the
hidden detector.
The smoke detector shall have a status indicating LED for visual
supervision. When the detector is actuated, the LED shall latch on
steady and at full brilliance. The detector shall be resettable after being
cleared of products of combustion. The detector base shall have
auxiliary relay and connections for a remote LED alarm indicator.
The detector shall be capable of operating satisfactorily under a
reasonable variation in supply voltage, such as normally occur in
service due to charge and discharge of the alarm system battery.
Where the detector is fixed inside hidden places such as false ceiling
voids, remote indication lamps with decorative base plate shall be
provided and mounted at ceiling level or high level directly under the
hidden detector.
In situations where the same lamps or LED’s are required both for fire
alarm/status indication and fault alarm indication, they shall be of twin-
color type, of suitable colors to B.S. 4099:1976 and B.S. 5378: 1976
and of the type approved by the Engineer.
Fire alarm break glass units conform to B.S. 5346: Part 1:1977 and shall
be suitable for 24 V D.C. operation. They shall have open circuit
contacts arranged for surface fixing with the front cover finished in red.
The contact shall close immediately after the glass is smashed.
The work “In Case of Fire Break Glass” shall be engraved both in
English and Indonesia.
The unit shall be of flush mounted and is generally adjacent to the hose
reel cabinet or positioned as shown on the drawings and to the approval
of the Engineer.
This detector consist 2 part, first part generate infra red signal, and the
other part for receiving the infra red signal, this equipment used for long
range area such as ware house, and will detected the smoke.
(b). Grounding
(c). Finishing
(a). the type which is used conforms to standard for fire fighting telephone
complete jack ,hand set battery back up, and other
(b). At floor is divided into several zone and the number of fire telephone
jack, hand set units will be conformed to the square meter of the room.
(c) Main control is located adjacent to the master control fire alarm in the
control room.
(d). Telephone Jacks are installed inside the fire hose cabinet.
(a) All materials supplied and installed by the Contractor, must be new and
is specially for installation in the tropical area, and must get the written
of Construction Management approval.
1. GENERAL
3. ILLUSTRATIONS
a. The pictures for the installation work of CCTV to be included in the Tender
Documents are the pictures with code numbers of the CCTV.
PT. PRAPANCA ENGINEERING TS - 302
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
4. STANDARDS/ REGULATIONS
All materials and installation in this work must comply to the General
Electrical Installation (PUIL 2000), SPLN / SNI No. 04-0225-2000,
Indonesia’s National Standard and other international standards.
6. MATERIAL SAMPLES
8. COORDINATION
Project owner is exempted from patents and the like on all kinds of
material procurement and installation. Owner is exempted from any
claims or charges against special rights such as patents and the like.
12. SPECIAL TECHNICAL REQUIREMENTS
The CCTV system is planned to support the security system of the building
by continually monitoring movements displayed on the screen around the
area where the IP CCTV camera is installed. The placement plan of the
CCTV cameras should be according to the drawings; cameras to be
placed in specific areas are required to use outdoor / indoor housing
adjustments in line with the drawing plan.
b. Scope of Work
- Sensitivity : 2 lux
- Resolution : 460 TV lines
- Image Device : 1/3 inch interline transfer CCD
- Ambient Temperature : -10 ºC ± 50 ºC
- Power Consumption : 12 V DC/ 24 AC /220 V AC
- Sync System : Internal
- Video Output : 1V p-p / 75 ohm
• Fixed Standard
- Focal Length (mm) : 8mm
- Maximum Aperture : F1.2
- Nearest Distance : 0.3 m
- Horizontal Field Angle : 34.8 º
• Motorized Zoom
.- Focal Length (mm) : 5.7 – 34.2 mm
.- Maximum Aperture : F1.2
- Nearest Distance : 0.3 m
- Horizontal Field Angle: 45.9 - 8.1º
2. Housing
Housing is used to protect the camera from around especially if placed in
areas disturbance and dirt potential.
Housing specifications:
• Outdoor Housing
- Window : 80.5 ( W ) x 72 ( H )m thick glass
- Construction : Aluminium
- Mounting : From Bottom
- Active Cap : Available to adjustable camera angle
• Indoor Housing
PT. PRAPANCA ENGINEERING TS - 307
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
3 Monitor
The monitor to be used is SVGA, size 19”; technical data as follows:
-Screen size : 19”W 10%
-Ambient Temperature : 0 C - 40 C
- Resolution :1280 x 1024 pixel
- Input Impedance :75 ohm / high-Z,(switchable)
- Humidity : max.80%
- Power Consumption : 80 W
Monitor size 15” (15 inch)
- Multi stereo system
- Melody on – off
- Equalizer
- Zoom & wide
- Plug & Play
- Turbo sound
- Absent power off
- Graphic DSD
DVR Specifications
- CPU : I7
- RAM : Min 8 GB
- HDD : 1000 GB ( Expandable )
- VGA Card : AGP 126 Mbyte – ATI
- O/S : Windows 7 or 8
- Camera input :16 Port ( RJ 45)
- Sensor Input :16Port
- Controller Output :16 Port
- Display Speed : 480 FPS
- Recording Speed : 360 x 288 : Max 480 FPS
- Recording Resolution :360 x 288,720 x 576
- Image Compression Size : - MPEG 4+ 360 x 288 : about 1~5 KB
- JPEG 360 x 288 : about 3 ~ 10 KB
- Voice Recording : 16 Chanel
- Compression Mode : MPEG 4+ / JPEG
- Motion Detection :10 Area by each channel ( Pre-even recording)
- Networking : Modem, ISDN ,LAN, TCP/IP
- Backup Device (Option) : 3.5”FDD,HDD, DVD-RAM,CD-RW,ZIP- Drive
- Pan/Tilt/Zoom Control : RS-422/485 Interface
- Size (WHD) : 480 x 178 x 450 (mm),19” x 7” x 18” ( inch )
- Weight : 16 Kg ( 35 lbs )
d. Wiring
15. MONITOR
This NVR (multiplexer) work not only as multiplexer, but is already completed
with facility which connected to alarm contractor ( remote switch) If the alarm
signal ( contactor) is received then automatically will display the picture of
PT. PRAPANCA ENGINEERING TS - 311
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
location on the monitor screen, and will interrupt (stop ) the observation
sequence on the programmed multiplexer
18. SCANNER
c. ZOOM LENSES : V 6 – 60
- Focal Length range : 6 – 60mm
- Effective aperture range : 1.2 – 360
PT. PRAPANCA ENGINEERING TS - 312
Mechanical & Electrical Works
PT. Barry Callebaut Comextra Indonesia
Makassar – Indonesia
d. ZOOM LENSES : V 5 – 50
- Focal Length range : 4,5mm
- Effective aperture range : 1.0 – 360
- Minimum focusing distance: 3.9 (1,2) ft (m)
Using LAN Cable UTP Cat 6 or and for control purpose and use NYA 0.5
mm.
HVAC
1. K'Flex Alu AA
12 Almunium Tape China
130
2. Idenden Japan
3. AB Foli Malaysia
ELECTRICAL SYSTEM
9 Lamp Component :
a Tube Lampu TL, PLC, PLS, Osram, Philips UK, Deutch
Nedherland,
b Ballast type Low Loss West Aust/WA, Australia,
May + Christy England
c Fitting Vosloh Sweden
Aid
d Capacitor
Electronic,Philips
e Emergency Lighting 1. Interlite Indonesia
2. Visilite Indonesia
3. Industira Indonesia
2. FG Wilson-
Perkin England
19 Alternator 1.Stamford
2.Marathon
3.Leroy Somer
4.Peerless USA
3. Socla Japan
3. Kitazawa(SinarMas
A) Japan
2. ABB England
3. Moeller Germany
ELECTRONIC SYSTEM
N
O MATERIAL / COMPONENT PRODUCT Original
1 TELEPHONE
IP PABX (IP Telephone) 1. Siemens German
Including (Telephone Set), 2. AT&T USA
Billing System 3. Philips Belanda
N
O MATERIAL / COMPONENT PRODUCT ORIGINAL
1 FIRE ALARM :
MCFA (semi Addressable) 1. Siemens Germany
Announciator 2. GE-Vigilant USA
Sirine 3. Esser Germany
Detector 4. Simplex USA
Manual Break Glass
Bell
General Alarm
Indicator Lamp
PLUMBING SYSTEM
N
O MATERIAL / COMPONENT PRODUCT Original
Clean Water Pipe / Pipa Air
1 Bersih Galvanized 1. Bakrie Indonesia
Medium Class 2. PPI Indonesia
Alat Sambung Pipa / Fitting
2
Fixture 1. FKK Japan
2. SNP Japan
3. TG Japan
4. HE Japan