Professional Documents
Culture Documents
I. INTRODUCTION
Wind power is currently the most promising renewable
technology and is expected to contribute significantly to
achieving the “20-20-20” target set by EU - 20% reduction
of greenhouse gases and 20% share of renewables by 2020
[1].
The development potential of wind power, especially
offshore, is huge. According to the latest estimations,
offshore wind power could reach an installed capacity of 40- Figure 1. Proposed sites for future offshore wind farms in Denmark [3]
55 GW by 2020 in North Europe [2].
In Denmark, a commission under the Danish Energy In addition to these Danish sites, Germany and the
Authority has issued “Future Offshore Wind Farm Sites – Netherlands also plan to continue their offshore wind power
2025” [3], appointing a number of potential sites for large development in the North Sea close to the Danish wind farms.
offshore wind farms, taking into account water depth, wind Therefore, under critical weather conditions, the wind power
resources, grid connection and other important issues. variability is becoming critical.
The proposed Danish offshore wind power sites are This issue is addressed in a very large European project.
indicated in Fig. 1. Each circle corresponds to a 200 MW The TWENTIES project (www.twenties-project.eu) aims at
wind farm, which means that approximately 2.4 GW wind “demonstrating by early 2014 through real life, large scale
farms including the existing ones could be concentrated in an demonstrations, the benefits and impacts of several critical
area of approximately 50 km × 100 km west to the Danish technologies required to improve the pan-European
The works and developments required for the elaboration of this transmission network, thus giving Europe a capability of
paper/article have been carried out partially within TWENTIES project responding to the increasing share of renewable in its energy
(www.twenties-project.eu) which belongs to the Seventh Framework mix by 2020 and beyond while keeping its present level of
Program funded by European Commission under project no.
ENER/FP7EN/249812/”TWENTIES”.
24
Speed [m/s]
22
20
18
16
19:00 20:00 21:00 22:00 23:00 00:00 01:00 02:00
7/8 Feb 2011
Figure 3. 1-min measured vs forecasted wind speed Figure 5. Offshore wind farms in Denmark in 2020 scenario
0.8
provide the mean wind flow over a large region, and then 0.7
adds a stochastic contribution using an adapted version of the
0.6
PARKSIMU approach that allows the mean flow to vary in
Power [pu]
time and space. 0.5
The meteorological data come from a climate simulation 0.4 Increasing period
gridded fields used in the nudging are taken from the NCEP
reanalysis [13] at 2.5° × 2.5° resolution. The sea surface Figure 7. Duration curves of reserves for different time windows
temperatures are obtained from the dataset of Reynolds et al
[14] at 0.25° horizontal resolution and temporal resolution of
1 day. The simulation covers the period from 1 January 1999 2500
to 31 December 2011 with hourly outputs. The model is run 1st percentile
5th percentile
value that are dealt with as ramping. Since the reserves must
be allocated in advance, the positive reserve requirement is
defined as the difference between the initial mean value and 0
10 20 30 40 50
Period [min]
60 70 80 90
Pramp (n) = Pmean (n) − Pmin (n + 1) Nevertheless, the part that is of most interest is the “worst-
(1)
case” scenario, namely the part close to the tail of the
Note that with this definition, positive reserves means distribution, the 1% in this case. The 1st percentile, together
decreasing wind power that requires positive reserves from with the 5th and 10th, are shown in Figure 8. One can notice
other power plants. that, in the worst case, around 1500 MW can be lost in 30
minutes, with this number going up to 2000 MW lost in one
The duration curves of the reserves requirements, hour.
calculated for different time windows.,from 10 to 90 minutes,
in 5 minute steps, are given in Fig. 7. V. HIGH WIND RIDE THROUGH™ CONTROLLER
During the project, Siemens Wind Power has developed,
tested, implemented and certified a new storm controller,
called High Wind Ride Though (HRWT). Today, the HWRT VI. CONCLUSIONS
controller is implemented in all wind turbines in the large Wind power variability under critical weather conditions
offshore wind farm of Horns Rev 2, in Denmark. The is raising concerns regarding the stability of the power
controller ensures that the turbines are slowly ramped down systems, especially when deployment of large scale offshore
when wind speed reaches or goes above 25 m/s, so a sudden wind power is considered. The analysis presented in this
shutdown of an entire park is avoided. The controller ramps paper shows that forecasting EWP is not very reliable and,
the actual power and generator speed down relative to the with the present way of dealing with EWP’s, the Danish
wind speed with a full cut-out at 31 m/s. The controller has as power system could face a loss of 1500 MW of offshore wind
inputs the rotor speed and the pitch reference. A more power in 30 minutes, or even up to 2000 MW in one hour.
detailed description of it can be found in [16]. Such an extreme event could therefore pose serious
For the upscaling part, a parameterization of the HWRT challenges to the secure and stable operation of the power
controller has resulted in the power curve shown in Figure 9. system. The new HWRT controller, presented by Siemens in
Until a new EWP is recorded in Horns Rev 2 wind farm, the TWENTIES project seems to have at least partially solved
after the implementation of the new HWRT controller, the problems. Preliminary simulations show that the impact
simulations for the old EWP, recorded with the old storm of EWP is greatly reduced.
controller, were performed.
1.2 REFERENCES
[1] 20 20 by 2020. Europe's climate change opportunity COMMISSION
1 OF THE EUROPEAN COMMUNITIES. Brussels,.
Power [p.u.]
0.8 [2] EWEA, Pure Power, Wind Energt Targets for 2020 and 2030, Brussels,
2011 [Online] Available:
0.6 http://www.ewea.org/fileadmin/ewea_documents/documents/publicatio
ns/reports/Pure_Power_III.pdf
0.4 [3] Future offshore wind power sites – 2025 (in Danish). Danish Energy
0.2 Agency, Ministry of Climate and Energy, April 2007.
[4] www.twenties-project.eu
0 [5] Horns Rev 2 Wind farm [Online] Available:
0 10 20 30 40 http://www.dongenergy.com/Hornsrev2/EN/Pages/Index.aspx
[6] NA. Cutululis, A. Hahmann, MH. Bjerge, A. Gøttig, LH. Hansen, N.
Wind speed [m/s] Detlefsen, P. Sørensen, ”Assessment of storm forecasting”, D6.1,
TWENTIES project, www.twenties-project.eu, June 2011
[7] NA. Cutululis, M. Litong-Palima, L. Zeni, A. Gøttig, N. Detlefsen, P.
Figure 9. HWRT controller power curve parameterization Sørensen, “Offshore Wind Power Data”, D16.2, TWENTIES project,
www.twenties-project.eu, April 2012.
November 11 2010 [8] P. Sørensen, NA Cutululis, A. Vigueras-Rodríguez, LE Jensen, J.
1.2 Hjerrild, MH. Donovan, H. Madsen, ”Power fluctuations from large
wind farms”, IEEE Trans. On Power Systems, 22(3), pp. 958-965,
1 August 2007.
[9] P. Sørensen, A. D. Hansen, P. A. C. Rosas, ”Wind models for
0.8 simulation of power fluctuations from wind farms”, J. Wind Eng. Ind.
Aerodyn. (2002) (no.90) , 1381-1402
0.6 [10] P. Sørensen, N.A. Cutululis, A. Vigueras-Rodriguez, H. Madsen, P.
Pinson, L.E. Jensen, J. Hjerrild, M.H. Donovan. Modelling of Power
0.4 Fluctuations from Large Offshore Wind Farms. Wind Energy (2008)
11, 29-43
0.2 [11] A. Vigueras-Rodriguez, P. Sørensen, NA. Cutululis, A. Viedma, MH.
Donovan, “Wind model for low frequency power fluctuations in
0
measured power offshore wind farms”, Wind Energy, 13(5), pp: 471-482, July 2010.
HWRT simulated power [12] Hahmann, A. N., D. Rostkier-Edelstein, T. T. Warner, Y. Liu, F.
12:00 18:00 00:00 Vandenberghe, Y. Liu, R. Babarsky, and S. P. Swerdlin, 2010: A
reanalysis system for the generation of mesoscale climatographies. J.
Appl. Meteor. Climatol., 49, 954-972.
Figure 10. Measured vs HWRT simulated power [13] Kanamitsu, M., W. Ebisuzaki, J. Woollen, S.-K. Yang, J. J. Hnilo, M.
Fiorino, and G. L. Potter, 2002: NCEP–DOE AMIP-II Reanalysis (R-
For example, for the EWP that was recorded on 2). Bull. Amer. Meteor. Soc., 83, 1631–1643.
[14] Reynolds, R. W., N. A. Rayner, T. M. Smith, D. C. Stokes, and W. Q.
November 11, 2010, the total wind farm output power was Wang, 2002: An improved in situ and satellite SST analysis for climate.
simulated using the individual wind speeds, as recorded in the J. Climate, 15, 1609–1625.
wind turbine nacelles, and the new HRWT power curve. The [15] Parson, M. Milligan, B. Zavadil, D. Brooks, B. Kirby, K. Dragoon, J.
result is presented in Figure 10. It is easily observed that, with Caldwell, “Grid Impacts of Wind Power: A summary of recent studies
in the United States,” Wind Energy , vol. 7, Apr./Jun. 2004, pp 87-108.
the HWRT the wind farm would not shut down at all, but [16] PM Christiansen, MS Jensen, “Test and verification of Storm Control”,
actually continue producing almost as nothing had happened. D12.1, TWENTIES project, www.twenties-project.eu, January 2013.