New Shedule
New Shedule
LAY-OUT Mr.Babu
On-site line installation
KBI Mr.Tamil Maint/Prodn 3 Weeks
Ensure existing machine wise programming Mando 3 days
Mr.Babu
Line T/O Mr.Shiva
Mando/KBI Mr.Tamil Maint/Prodn 2 days
Initial operator recruitment of 20 people,
including 2 staff KBI Mr.Dheena HR/IR 2 month
Man power
Recruitment of 85 people including 4
management staff in KBI KBI Mr.Dheena HR/IR 2 month
20 people, including 2 management staff,
Mr.Shiva
training in MAIL
Mando/KBI Mr.Tamil QA/Prodn 1 month
Training Mr.Babu
Mass production training (production, quality, Mr.Shiva
maintenance) Mr.Tamil Maint/QA/Prod
Mando/KBI 1 month
Mr.Shiva
Jig/Fixture Take over of jigs, tools, checkers, spares
Mando/KBI Mr.Tamil QA/Prodn 1 Week
Mr.Tamil Prodn/Purch
WIP And process bins
Logistics KBI Mr.Naresh ase 1 month
Dispatch Trolley KBI Mr.Naresh Sales TBC