By Bruce A. Suprenant reused or removed. Grease the
ometimes contractors S must place new concrete walls against existing concrete part of the tie or bolt that will be embedded in the fresh concrete. If this step is walls, earth banks, and steel or skipped, the accessories can’t timber shoring that protects be reused. property lines. These situa- tions often require the use of Prefabricated form one-sided forms, and the form components installation may have to be When specifications or site done without conventional conditions prohibit the use of form ties to help resist lateral ties, contractors can avoid us- concrete pressures. To avoid ing a lot of lumber bracing by bulges, blowouts, and out-of- selecting prefabricated form tolerance walls, contractors can components. Attach vertical use bracing, specialty acces- wales or strongbacks to a sories, or prefabricated form- form panel. Then add a hori- work components. zontal and diagonal wale to Even very short walls will the vertical wale to form tri- bulge if not adequately braced angular waler frames that re- or tied. On the project shown sist the pressure of fresh con- in Figure 1, workers felt the crete (Figure 2). This type of bracing was sufficient, but it one-sided form can be readily wasn’t and the wall bulged. To ganged and moved by crane. correct the bulge, they re- Securely attach the triangu- moved concrete from the lar frame to the footing or forms, added more braces, slab to resist the force gener- then shoveled the concrete ated by the lateral pressure of back into the forms. This was the concrete. Drill in anchors expensive, time-consuming, and place anchor bolts to se- and messy. On another one-sid- cure the waler frame to the ed forming project, vibrating concrete. Even with strong the concrete during place- panel forms and 5- to 8-inch Figure 1. Without ties, one-sided wall forming can lead to ment caused the wall to move. bulges and blow-outs. Even on this short wall, the concrete steel wales, don’t space the The workers stopped vibrating pressure was sufficient to move the form. Here workers are triangular wale braces more and used a rebar to consolidate removing concrete and adding braces to stop the form from than 3 to 4 feet apart. the concrete. But the 1-inch moving. Manufacturers provide specialty form accessories bulge at the bottom of the wall to make the job easier and prevent bulging walls. Blind-side forming remained. Even when braces When forming against an are sufficient, the stakes hold- use these specialty items to anchor ties existing foundation wall, it’s some- ing the braces may be too weak, per- to existing concrete walls, rock cliffs, times possible to use two-sided forms mitting form movement. Anchoring steel soldier piles or sheet piling, if space allows. The back-side form, stakes to a concrete deadman may be wood lagging, rebar, and other ties. or blind-side, between the old and necessary. Ties are connected to these members new wall can be formed with specialty by welds, screws, and couplers (see devices similar to those used for one- Specialty accessories box). These accessories allow the ties sided forming. The trick to using ties To avoid the problems associated to resist the lateral pressures of the with blind-side forming is to get them with making timber bracing strong fresh concrete. Then lateral bracing into place and anchored. Figure 3 enough to support the lateral pressure only needs to resist wind or other lat- shows three different methods of of fresh concrete, contractors can eral loads created during concrete blind-side forming that require 1 to 4 choose from a number of specialty ac- placement. inches of clearance. Because there cessories that allow the use of ties A waterproof grease should be used usually isn’t adequate work space, the with most one-sided forms. They can on embedded items that are to be SPECIALTY ACCESSORIES MAKE TIES WORK Accessory Application
A. Coil tie attached to steel channel. A. B.
The tie can hold as much as 3,750 pounds with a safety factor of 2. Ac- tual working load depends on the strength of the field weld.
B. Weld channel to steel or drill hole
through steel, slip channel through, pull back tie to use channel as a bearing anchor.
A. Expansion anchors are available in A. B.
varied sizes and allowable working loads. The actual anchorage capacity is usually governed by the strength of the rock or concrete to which it’s anchored.
B. Drill a hole perpendicular to the
concrete or rock surface. Insert and set anchor, screw in coil rod, and at- tach coil tie to the threaded rod. Typi- cal hole length is 6 to 10 inches. Hole diameters vary from 1 to 2 inches.
A. Use a lag bolt with a tapped end to A. B.
accept a threaded rod. Typical lag bolt size is 5 inches long and 3⁄4 inch in di- ameter. Ends are tapped to accept 1⁄2- inch threaded rod. Safe working load of the bolt varies from 1,000 to 3,000 pounds but the quality of the wood could lower the working load.
B. Drill a pilot hole in the wood, screw
in lag bolt, and install threaded rod and waler assembly.
A. The coil tie can safely support loads A. B.
from 3,750 to 13,500 pounds. The quality of the weld governs the allow- able loading. This tie, ranging from 3 to 5 inches long, is available to fit #6, #9, or #11 rebar.
B. Weld the modified coil tie to rebar
(or other firmly anchored steel item). Minimum field weld size varies from 1 to 2 inches.
A. Steel couplers vary in size from 2 to A. B.
4 inches long and 3⁄4 to 11⁄2 inches in di- ameter. They come in sizes to fit 1⁄2-, 3⁄4-, and 1-inch-diameter threaded rods. Both ends can accept threaded rod.
B. Place coupler into cavity left by a she-
bolt, screwing it onto the threaded rod. Screw new tie into coupler. Concrete may need to be chipped from the cavity to make the connection. Make sure both rods screw full-depth into coupler. Figure 2. One-sided forming can be blind-side form in place, slide the ta- successful without ties. Form panels are braced with a triangular wale system pered tie through both forms, then that is anchored to hardened concrete, screw the tie into the washer on the keeping the wall vertical. This system blind side. This system requires about can be ganged for crane handling. 3 inches of clearance. For smaller clearances, don’t use vertical studs. blind-side form is typically left in After placing concrete, unscrew the place. taper tie from the washer and slide the One method of blind-side forming tie out of the wall. The blind-side can uses ties hooked around the form then be removed. Because of the tight sheathing. The sheathing and tie can clearance, however, it’s difficult to use be as thin as 1 inch. But the tie spac- a bar to pry the forms from the con- ing is fairly close and the allowable tie crete. load is low (about 1,500 pounds). To stiffen the form sheathing, use flat 1x Be creative and 2x material. Then the allowable Learning how to use specialty tie load controls tie spacing. Another accessories for one-sided and blind-sid- method uses a loop tie that is slipped ed forming can make the job easier and through holes drilled in plywood, then prevent bulges. Some contractors de- hooked around rebar or rods. velop their own forms using metal stay- The blind-side form for both of in-place forms with ties welded to these systems must be left in place. them or ties slipped through holes then For blind-side forms that need to be hooked on rods behind the metal stripped, use taper ties and a back- forms. But whatever system is used, side form of plywood sheeting with make sure the ties are adequately an- flat vertical studs attached. Drill a chored. If using one-sided forms with- hole for the tie through the plywood out ties, use plenty of bracing. and vertical stud. Nail a nut or plate washer over the tie hole. Set the