Daily Inspection Schedule
Daily Inspection Schedule
Sr. No. Description of item for Inspection Time NOI No. Reference Drawing No. Reference specification Remarks
Date
RAWAD
Survey Inspection as built Box 25 Phase 02 1st
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
1 Strip Filter Area after Structural backfill of 3rd 22-Feb-24 8:30 AM PE_ZULUF_DRA-0020-01 Re-Scheduled
A00-0555 0001
layer. Elev-6.10 M
Field Density test for box 25 Phase 02 1st strip of
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
2 Filter area after structural backfill of 3rd layer. 22-Feb-24 8:45 AM Re-Scheduled
A00-0556 171-230004-DC 0001
Number of test 01.
Survey Inspection as built Box 25 Phase 02 2nd
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
3 Strip Filter Area after Structural backfill of 2nd 22-Feb-24 9:00 AM PE_ZULUF_DRA-0020-01 Re-Scheduled
A00-0557 0001
layer. Elev-5.90 M
Field Density test for box 25 Phase 02 2nd strip
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
4 of Filter area after structural backfill of 2nd 22-Feb-24 9:15 AM Re-Scheduled
A00-0558 171-230004-DC 0001
layer. Number of test 01.
Survey Inspection as built Box 25 Phase 02 2nd
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
5 Strip Filter Area after Structural backfill of 3rd 22-Feb-24 9:30 AM PE_ZULUF_DRA-0020-02 Re-Scheduled
A00-0559 0001
layer. Elev-6.10 M
Field Density test for box 25 Phase 02 2nd strip
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
6 of Filter area after structural backfill of 3rd layer. 22-Feb-24 9:45 AM Re-Scheduled
A00-0560 171-230004-DC 0001
Number of test 01.
Rapid dynamic compaction_ Field Density Test
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
7 for Box 24 Phase 02 Side 2nd strip after RDC. 22-Feb-24 7:45 AM Re-Scheduled
A00-0563 171-230004-DC 0001
Number of test 01.
Rapid dynamic compaction_ Plate Load Test for PE_ZULUF_DRA-0020-01,
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
8 Box 24 Phase 02 2nd strip after RDC. Number of 22-Feb-24 10:00 AM 171-230004-DC, As per Re-Scheduled
A00-0564 0001
test 01. attached points of PLT
Survey Inspection as built Box 24 Phase 02 1st
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
9 Strip Filter Area after Structural backfill of 1st 22-Feb-24 9:30 AM PE_ZULUF_DRA-0020-01 Re-Scheduled
A00-0565 0001
layer. Elev-5.50 M
Field Density test for box 24 Phase 02 1st strip of
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
10 Filter area after structural backfill of 1st layer. 22-Feb-24 9:45 AM Re-Scheduled
A00-0566 171-230004-DC 0001
Number of test 01.
Survey Inspection as built Box 24 Phase 02 2nd
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
11 Strip Filter Area after Structural backfill of 1st 22-Feb-24 9:45 AM PE_ZULUF_DRA-0020-01 Re-Scheduled
A00-0567 0001
layer. Elev-5.50 M
Field Density test for Box 24 Phase 02 2nd strip
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
12 of Filter area after structural backfill of 1st layer. 22-Feb-24 10:00 AM Re-Scheduled
A00-0568 171-230004-DC 0001
Number of test 01.
Survey Inspection as built Box 24 Phase 02 1st
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
13 Strip Filter Area after Structural backfill of 2nd 22-Feb-24 10:30 AM PE_ZULUF_DRA-0020-01 Re-Scheduled
A00-0569 0001
layer. Elev-5.70 M
Field Density test for Box 24 Phase 02 1st strip of
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
14 Filter area after structural backfill of 2nd layer. 22-Feb-24 10:45 AM Re-Scheduled
A00-0570 171-230004-DC 0001
Number of test 01.
Survey Inspection as built Box 24 Phase 02 2nd
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
15 Strip Filter Area after Structural backfill of 2nd 22-Feb-24 11:30 AM PE_ZULUF_DRA-0020-01 Re-Scheduled
A00-0571 0001
layer. Elev-5.70 M
Field Density test for Box 24 Phase 02 2nd strip
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
16 of Filter area after structural backfill of 2nd 22-Feb-24 11:45 AM Re-Scheduled
A00-0572 171-230004-DC 0001
layer. Number of test 01.
Survey Inspection as built Box 24 Phase 02 1st
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
17 Strip Filter Area after Structural backfill of 3rd 22-Feb-24 11:45 AM Re-Scheduled
A00-0573 171-230004-DC 0001
layer. Elev-6.10 M
Field Density test for Box 24 Phase 02 1st strip of
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
18 Filter area after structural backfill of 3rd layer. 22-Feb-24 11:45 AM Re-Scheduled
A00-0574 171-230004-DC 0001
Number of test 01.
Plate load test for box 25 Phase 02 1st strip of PE_ZULUF_DRA-0020-01,
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
19 Filter area after structural backfill of 3rd layer. 22-Feb-24 11:15 AM 171-230004-DC, As per Re-Scheduled
A00-0575 0001
Number of test 01. attached points of PLT
Plate Load test for box 25 Phase 02 2nd strip of PE_ZULUF_DRA-0020-01,
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
20 Filter area after structural backfill of 3rd layer. 22-Feb-24 1:00 PM 171-230004-DC, As per Re-Scheduled
A00-0576 0001
Number of test 01. attached points of PLT
Survey Inspection as built Box 24 Phase 02 2nd
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
21 Strip Filter Area after Structural backfill of 3rd 22-Feb-24 1:00 PM Scheduled
A00-0577 171-230004-DC 0001
layer. Elev-6.10 M
Field Density test for Box 24 Phase 02 2nd strip
WT2201-FIS-QA-NOI- PE_ZULUF_DRA-0020-01, WT2201-FIS-QA-ITP-A00-
22 of Filter area after structural backfill of 3rd layer. 22-Feb-24 1:00 PM Scheduled
A00-0578 171-230004-DC 0001
Number of test 01.
Plate load test for Box 24 Phase 02 1st strip of PE_ZULUF_DRA-0020-01,
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
23 Filter area after structural backfill of 3rd layer. 22-Feb-24 3:00 PM 171-230004-DC, As per Scheduled
A00-0579 0001
Number of test 01. attached points of PLT
Plate Load test for Box 24 Phase 02 2nd strip of PE_ZULUF_DRA-0020-01,
WT2201-FIS-QA-NOI- WT2201-FIS-QA-ITP-A00-
24 Filter area after structural backfill of 3rd layer. 22-Feb-24 4:45 PM 171-230004-DC, As per Scheduled
A00-0580 0001
Number of test 01. attached points of PLT