Professional Documents
Culture Documents
Introduction
Using this technique, we protect the well casing from corrosion. Corrosion is
produced in a metal as a result of natural oxidation so using this technique we
minimize the effect of oxidation and protect the well casing from corrosion.
Data submittal
We do submit our data to SAMPT to get their comments regarding the hole.
After geological department approval we do start the installation of anode
process.
Installation of ANODES
After this we do start the installation of anodes one by one and the first anode
with longest cable would be installed firstly along with anode centralizer,2” steel
pipe as its support and blue colored perforated 1” vent pipe.
The purpose of blue color perforated vent pipe is to release any gases produced
as a result of anodes reaction with backfill material. These gases may also react
with anodes so by using these perforated slotted pipes; this would release all
gases like chlorine and bromine upwards through them to atmosphere.
The 1 inch vent pipe will touch the bottom cement plug and first anode distance
from the bottom cement plug would be as per IFC design drawings.
The end of every anode would be tied together with 2”steel support pipe and 1”
vent pipe by steel clamp to prevent anodes from hanging in the hole.
We do use the coupling to connect 1” inch pvc vent pipe to another same pipe
and 2” Steel pipe to another 2” steel pipe for continual support to remaining
anodes.
After installation of all anodes we do install 1” (6 meters in length) white pvc vent
pipe without slots because they would not have any anodes to make reaction
with backfill and as a result no Chance of gas release in those intervals.
Holiday Testing
After this we do conduct holiday testing for positive Cp cable, we do fix voltage at
18000 DC volts and check cables dielectric strengths in the presence of assigned
CP Qc inspector and PID.
Cp cable lay down and backfilling
After holiday testing, we lay down the cp cables in their respective trenches and
backfill the trenches
Cable Termination
After this do terminate the positive Cp cable between Solar panel positive
terminal and Positive Junction box and also we do terminate negative Cp cable
between Well head and Negative terminal of Dc solar power source.
Pre commissioning
In the Pre commissioning we do take individual anode resistance reading and if
the value is acceptable then we do tell Sampt to schedule the well for final CP
commissioning. And it should be done by certified NACE technician