Professional Documents
Culture Documents
Serial Rev
DOCUMENT REVISIONS
This document is the property of the CONTRACTOR who will safeguard its rights according to the civil and penal provisions of the law.
The only controlled version of this document resides in the CONTRACTOR Electronic Document Management System.
Any copies made of this document shall be considered UNCONTROLLED unless it is being viewed on-screen on the CONTRACTOR INTRANET.
TABLE OF CONTENTS
1 PURPOSE........................................................................................................................................................ 3
2 SCOPE............................................................................................................................................................. 3
3 DEFINITIONS................................................................................................................................................... 3
4 REFERENCES................................................................................................................................................. 3
4.1 General..................................................................................................................................................... 3
4.2 SAES / SAEP........................................................................................................................................... 3
5 ABBREVIATION.............................................................................................................................................. 3
6 RESPONSIBILITIES........................................................................................................................................ 4
7 PROCEDURE................................................................................................................................................... 4
7.1 Control of Field Engineering Changes.................................................................................................. 4
7.3 Issuance................................................................................................................................................... 6
7.4 Tolerances............................................................................................................................................... 6
8 WAIVERS......................................................................................................................................................... 6
9 Documentation............................................................................................................................................... 6
10 ATTACHMENTS.............................................................................................................................................. 6
1 PURPOSE
The purpose of this procedure is to establish the procedural steps to be followed in implementing Field
Engineering changes that may arise during the course of Construction / Fabrication.
2 SCOPE
This procedure is applicable for Shop Drawing preparations for facilitating construction activities, Red Line
mark-ups on IFC Drawings and management of Technical Query on technical problems and/or
modifications encountered which require disposition/clarification from Saudi Aramco for Upgrade
Uthmaniyah Abqaiq Pipelines Project (BI/JO-10-01196/0001).
3 DEFINITIONS
COMPANY - A company is a legal entity formed by a group of individuals to engage in and operate
a business enterprise in a commercial or industrial capacity. Here the COMPANY is “SAUDI ARAMCO”.
CONTRACTOR - A contractor is engaged by a principal (the other party) to perform services under a
contract for services. Here the Contractor is “SICIM SAUDI ARABIA CO”.
Red Line Mark Up - Throughout the design, fabrication, and construction phases of an engineering
project, drawings get marked up. These markups are often referred to as markups or
redlines. Drawings will be marked up many times throughout a project.
As-Built Drawing: - an Engineering drawing that has been revised to reflect actual field conditions after
the completion of construction. Additions or changes to a drawing resulting from facility modification must
also be verified as 'As-Built' and referenced to the Job Order (JO) in case of PMT, Engineering Work
Order (EWO) in case of Design office and organization code in case of operation.
4 REFERENCES
All work for this scope shall be completed following the latest issue of Saudi Aramco’ Project standards
(Cut off June 2017), procedures, material specifications, GI, inspection requirements, drawings, codes,
process industry practices and technical alerts including but not limited to the following:
4.1 General
IFC Drawings Issued for Construction
Schedule ‘B’ Job Specification
SOW Scope of Work
Project Quality Plan SA010-00-0803-SC-0001
Schedule ‘Q’ Quality Requirements
Engineering Change Management Procedure SA010-00-0301-SC-0001
5 ABBREVIATION
CONTRACTOR SICIM Saudi Arabia
COMPANY Saudi Aramco
SAPMT Saudi Aramco Project Management Team
QA/QC Quality Assurance and Quality Control
6 RESPONSIBILITIES
Project Manager (PM) shall be responsible to ensure that the work described hereunder is
executed in accordance with all the contract requirements including this special process
procedure.
Field Engineering Manager (FEM) shall be responsible to review and ensure that all Red Line
Marked Drawings shall be included in As Built. Assure that changes have been approved by
COMPANY before work commencement, otherwise, potential consequences of field change work
commencement without COMPANY approval and notification will result to an immediate rejection of
the work leading to SICIM re-work as necessary with no cost or schedule impact.
QA/QC Manager shall be responsible to monitor the control and distributions of the approved
Technical Query and Red Line Marked Drawings are implemented in accordance with the
established document control system.
Construction Manager (CM) shall be responsible to check all initiated site Technical Query and/or
Red Line Mark Up Drawing that no drawbacks are present with the Constructability requirements.
QC Inspector shall verify the Redline Mark Up Drawings as per the actual Site condition, changes
in IFC drawing shall comply with MSAERs and project Quality requirements. Inspections shall be
with approved redline Mark-up Drawing.
Document Controller (DC) shall manage all IFC and Red Line Marked drawings. This involves
checking the IFC & Red Lined Marked drawings to make sure it is up-to-date and controlled with
maintained log. DC shall ensure that superseded IFC/Red Line Marked Up drawings were
removed on site.
7 PROCEDURE
a) Clarification of IFC Drawings that are not clear or consistent and/or conflict with dimensions from
each other interfacing work disciplines.
b) Verification of some conflicts and/or ambiguities between IFC Drawings and Specifications.
c) Lack or absence of Construction detailed designed drawings.
d) Encountered restraints or extreme difficulties in the site construction activities where IFC Drawings
is not workable (i.e. space clearance limitation, obstruction to existing facilities, etc.).
e) Violation of Safety and/or maintenance code provision if IFC Drawing or Job Specification will
govern, thereby a clarification is needed.
f) Other matter that is deemed necessary to seek clarification from the Contractor’s Engineering
Department before proper execution.
g) Refer the Engineering Change Management Procedure (SA010-00-0301-SC-0001)
Revision numbers to as-built drawings must be following the guidelines outlines in SAES-A-202 Clause 5.7
All Red Line Mark Up drawings are interpreted using red ink pen and deleted (affected) areas are clouded
with shaded of green ink. The As-Built drawings are delineated neatly and professionally.
Once the As-Built changes are completed, the original red-lined mark up and a copy of as-built drawing
that incorporates all the changes shall be checked against each to ensure that all changes were made are
noted.
Once verification is completed and signed off by SAPMT, two (02) red-lined marked up sets of full size ‘As-
Built’ blueprints drawings shall be produced to reflect and sufficient detailed records of all field modification.
One set of drawings shall remain at site during mechanical completion inspection or to be used as Request
for Inspection (RFI) reference during PID inspection at the construction site and one set of drawings shall
be provided to Contractor’s Engineering for revision to the project drawings.
The number of prints of "As-Built" shall be as per contract and shall be handed over to SAPMT along with
an electronic file.
As-built documents shall be marked “RED LINE MARK UP” if there is change or “AS-BUILT NO
CHANGE” if No Changes from IFC as per site condition/construction.
Changes will be marked by the originator and dated, below is a sample stamp, however, it is not necessary
to have a stamp, information handwritten on drawings are acceptable.
7.3 Issuance
Major changes on pipeline re-routing affecting the approved LUP will be requested via TQ. Changes to
original routing may be acceptable with prior approval per Section 6 of SAES-L-450.
7.4 Tolerances
The accuracy tolerances will be following PROJECT requirements.
8 WAIVERS
Responded Technical Query or Signed Red Line Mark Up drawing by Saudi Aramco shall not be used to
substitute a Waiver for Standard Violation.
Where there is a deviation from MSAERs, a Waiver shall be processed after TQ review and approval
without the need for a redline mark-up. Waiver request shall be managed in line with SAEP-302.
9 Documentation
A log will be maintained for all Red Line Mark Up IFC Drawings with revision number.
10 ATTACHMENTS