SHELL MOBILITY (EPCM CONTRACTORS WORK METHODOLOGY)

METHOD OF STATEMENT
LIFELINE SYSTEM FOR
CANOPY ROOF REPLACEMENT

1
Approval & Revision
Approval
Prepared Prepared Prepared Prepared Accepted by
Rev Date Description
IPMSB ENOTEK PJC KYCSB MEINHARDT

1 27/04/2022 ISSUE FOR REVIEW KAMARUL

Revision

Rev. Date Issue Sections Page Brief of Description of Change

0 27/4/2022 all all 1st draft

2
HSSE Requirements Recommended Tools & Equipment
• Personal Protective Equipment PPE • General

Description Picture

Hard Hat
Scaffold
Safety Glasses

Start Anchor Plate

High Visibility Vest


Middle Anchor Plate

Gloves
End Anchor Plate

Safety Harness Retractable Lanyard 10m


Tensioner

Traveller

Crimp Fitting

Safety Shoes
Spanner

Hand tools

Lifeline – Stainless steel, 8mm


7x7.
HSSE Requirements DO’s and DON’Ts
• Documentation available on site
• DO’s • DON’Ts
Permit
(if required)

JHA
(Job Hazard
Analysis)

WCF
(Work
Clearance
Form)

Attendance
list

• Last Minute Risk Assessment (LMRA)


▪ A LMRA is a final check for extra risks before, and during the work task at • Ask yourself :
hand.
▪ It means quickly reviewing the task and environment, mentally and visually, ▪ Ensure 100% tie off while working at height at canopy at all phases of
to ensure all hazards have been identified, and control measures put in work
place. This should also be done throughout the duration of the work at ▪ Are you aware where is nearest hospital, fire station and police station?
each job step. Do you have contact?
Guidelines ▪ What can hurt me? What can hurt my co-workers?
▪ This could include:
▪ Global control framework ver. 5.1 ▪ Do we have the right PPE for the job?
- Weather changes
▪ Shell PTW ver. 5.1 ▪ Is my area free of housekeeping hazards?
- Review of all necessary PPE ▪ Retails contractor HS requirements ver. 5.1
- Work method (change to job steps) ▪ ▪ Am I working in the area of another trade?
Global risk register
▪ Am I in the line of fire? Will I be in the line of fire if I change my position?
▪ Global Innovations Design Standard (GIDS)
▪ Is this the safest way to do the job?
Competency Requirement If you ask yourself these questions as you work you can assess
and address all changes to your work, your safety, and your co-worker’s
▪ Valid WAH certificates prior to work
▪ Only personnel trained by the supplier are allowed to
safety.
install the lifeline systems.

4
Site Preparation

Engage with Station Manager / Tool Box Talk (Talk Not Tick)
Representative • Explain JHA
• Obtain WCF • Explain 9 Life Saving Rules
• Check all PPE
• Inform nearest Hospital, Police
Station and Fire Station

Barricade work area


• Hard barricade
• Signage

Traffic Control (if required) Scaffold erection as an access


• Flagman to top of building/canopy
• Baton light

5
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION
No. Description
1.

6
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION

No. Description
2.

2. PERSON 1 HOOK HIS 10M


RETRACTABLE LANYARD 1 TO THE
SCAFFOLD

3. THEN PERSON 1 GET ON THE SHOP


ROOF TO INSTALL ACHOR PLATE X1
WITHIN MINIMUM 1.8M FROM THE
SHOP ROOF EDGE

Remark:
• Nylon Rope diameter is 12mm
minimum
• The manual lift shall be done on top
of scaffold with top and mid rail
installed to prevent fall from height

7
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION
No. Description
3.

2. PERSON 1 UNHOOK HIS 10M


RETRACTABLE LANYARD 1 FROM HIS
BODY

3. PERSON 1 MOVE NEAREST TO THE


CANOPY TO INSTALL ANCHOR PLATE X2

Remark:
-Workers shall ensure to 100%
tie off during working at height
through all work sequence

8
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION
No. Description
4.

2. PERSON 1 HOOK 10M RETRACTABLE


LANYARD 3 TO THE LIFELINE

3. PERSON 1 UNHOOK RETRACTABLE


LANYARD 2 FROM THE ANCHOR PLATE
X1

4. THEN PERSON 1 WAIT PERSON 2


CAME UP WITH LADDER EQUIPMENT

5. PERSON 2 BRING THE LADDER


EQUIPMENT PIECE BY PIECE ONTO
SCAFFOLD

6. THEN PERSON 2 GET ON THE SHOP


ROOF WITH THE SAME STEP ON PERSON
1

7. PERSON 2 PASS ALL LADDER


EQUIPEMNT TO PERSON 1

8. PERSON 1 & 2 WILL ASSEMBLE /


INSTALL THE LADDER

• Hoist the ladder up to the shop


roof using crane
• Only 2 persons allowed to
install fall protection system at
this stage

9
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION
No. Description
5.

2. PERSON 1 HOOK HIS 1.8M LANYARD


TO THE LADDER

3. PERSON 1 UNHOOK HIS 10M


RETRACTABLE 3 LANYARD FROM HIS
BODY

4. THEN, PERSON 1 GET ON THE CANOPY


ROOF

5. AFTER ASSEMBLY DONE, PERSON 2


GET ON THE LADDER

6. PERSON 2 HOOK HIS LANYARD TO THE


LADDER

7. THEN, PERSON 2 RETURN BACK TO


THE LIFELINE Y & UNHOOK THE 10M
RETRACTABLE LANYARD 3 & 4 FROM
THE LIFELINE Y

8. PERSON 2 PASS LANYARD 3 &4 TO


PERSON 1

9. PERSON 6 GET ON THE SCAFFOLD

10. PERSON 6 HOOK THE 10M


RETRACTABLE LANYARD 1 TO HIS BODY

11. PERSON 6 GET ON THE SHOP ROOF


AND MOVE TO LIFELINE Y

12. PERSON 6 HOOK THE 10M


RETRACTABLE LANYARD 2 TO THE
LIFELINE Y & TO HIS BODY

13. THEN PERSON 6 UNHOOK THE 10M


RETRACTABLE LANYARD 1 FROM HIS
BODY

• Only 2 persons allowed to


install fall protection
system at this stage

10
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION
No. Description
6.

2. THEN, PERSON 1 UNHOOK HIS 1.8M


LANYARD FROM THE LADDER

3. THEN PERSON 2 INSTALL ANCHOR


PLATE 1

• Only 2 persons allowed to


install fall protection
system at this stage

11
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION
No. Description
7.

2. PERSON 1 INSTALL ANCHOR PLATE 2

• Only 2 persons allowed to


install fall protection
system at this stage

12
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION
No. Description
8.

2. PERSON 1 UNHOOK LANYARD 4 FROM


THE LADDER

3. PERSON 1 MOVE TO THE NEXT POINT


TO INSTALL ANCHOR PLATE 3

4. PERSON 1 HOOK THE 10M


RETRACTABLE LANYARD 4 TO ANCHOR
PLATE 3

5. PERSON 1 RETURN BACK TO ANCHOR


POINT 1 TO UNHOOK LANYARD 3 FROM
THE ANCHOR PLATE 1

6. PERSON 2 WILL GO TO ANCHOR


POINT 1TO UNHOOK LANYARD 3 FROM
THE ANCHOR PLATE 1

7. PERSON 2 WILL REPEAT THE PROCESS


SAME PERSON 1

• Only 2 persons allowed to


install fall protection system at
this stage

13
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION
No. Description
9.

• Only 2 persons allowed to


install fall protection
system at this stage

14
WORK SEQUENCE : FALL PROTECTION SYSTEM PLAN & INSTALLATION
No. Description
10.

• Only 2 persons allowed to


install fall protection
system at this stage
• Before start works, pi and
PH to do inspection after
the workers set up the
Hann system life line

15
WORK SEQUENCE : LOAD TEST ON THE FALL PROTECTION SYSTEM
No. Description
11.

1. Inspect Hann System to ensure the method


is as per manufacturer guidelines

2. Load test wire rope are secured with


shackles.

3. Attach to weight meter and webbing sling.

4. Rubber mat placed under load test rope to


prevent damage to canopy fascia

5. 8 Knot used to tie load test rope to 2”D-


Shackle & tension meter bypass loop

6. 3 men required to pull on load test rope to


reach 70 kg & 140 kg mark.

7. Record the reading

Remark:
• Ensure there is no damage to wire
rope for lifeline system
• Wire rope install shall not be less
than 8mm diameter

16
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
12.

2. PERSON 1 UNHOOK 1.8M LANYARD


FROM LIFELINE A

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work

17
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
13.

2. PERSON 1 WAIT PERSON 4 TO JOIN HIM

4. PERSON 2 WAIT FOR PERSON 3 TO JOIN

6. PERSON 3 HOOK THE 10M


RETRACTABLE LANYARD 1 TO HIS BODY
THEN MOVE TO LIFELINE Y

7. THEN PERSON 3 HOOK 10M


RETRACTABLE 2 TO HIS BODY

8. PERSON 3 UNHOOK LANYARD 1


FROM HIS BODY & GET ON TO THE
LADDER

9. THEN, PERSON 3 HOOK HIS 1.8M


LANYARD TO THE LADDER & UNHOOK
LANYARD FROM HIS BODY

10. PERSON 6 KEEP MONITORING


PERSON 1,2,3

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work

18
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
14.

4. PERSON 4 HOOK 10M RETRACTABLE


LANYARD 1 TO HIS BODY
5. THEN, PERSON 4 MOVE TO LIFELINE
Y& HOOK THE 10M RETRACTABLE
LANYARD 2 TO HIS BODY

6. PERSON 4 RETURN BACK TO THE


SCAFFOLD & UNHOOK LANYARD 1.8
FROM SCAFFOLD & BRING WITH HIM

7. THEN, PERSON 4 HOOK THE 1.8M


LANYARD TO THE LADDER

8. THEN, PERSON 4 PASS LANYARD 1&2


TO PERSON 4

9. PERSON 6 KEEP MONITORING


PERSON 1,2,3&4

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work

19
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
15.

4. PERSON 4 HOOK LANYARD 1 TO THE


LADDER

5. PERSON 4 MOVE TO THE LIFELINE B


TO HOOK THE LANYARD 2

6. THEN, PERSON 4 UNHOOK LANYARD


1 FROM HIS BODY

7. PERSON 6 KEEP MONITORING


PERSON 1,2,3 & 4

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work

20
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
16.

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work

21
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
17.

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work

22
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
18.

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work
• Not more than 5 roofing sheets
are allowed to be dismantled at
any time to minimise the
openings at each area.

23
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
19.

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work
• Not more than 5 roofing sheets
are allowed to be dismantled at
any time to minimise the
openings at each area.

24
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
20.

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work
• Not more than 5 roofing sheets
are allowed to be dismantled at
any time to minimise the
openings at each area.
• New roofing sheet to be
mobilised using crane and
stored on the roof. Refer
detailed lifting plan in the CRR
• Material storage shall not
exceed 1.8m from the edge

25
WORK SEQUENCE : PHYSICAL ACTIVITY COMMENCEMENT
No. Description
21.

Important note:
• At each line, only 2 person
allowed to be restrained on each
line.
• It is suggested to limit people
movement perpendicularly from
the lifeline during all phases of
work
• Not more than 5 roofing sheets
are allowed to be dismantled at
any time to minimise the
openings at each area.

26
WORK SEQUENCE : DEMOBILISATION
No. Description
22.

* Only 2 persons allowed to


dismantle fall protection
system at this stage

27
WORK SEQUENCE : DEMOBILISATION
No. Description
23.

* Only 2 persons allowed to


dismantle fall protection
system at this stage

28
WORK SEQUENCE : DEMOBILISATION
No. Description
24.

2. PERSON 4 HOOK 1.8M LANYARD TO


LIFELINE Y & MOVE TO ANCHOR POINT
X1

3. THEN, PERSON 4 HOOK THE LANYARD


1 TO LIFEELINE A & UNHOOK THE 1.8M
LANYARD

4. THEN, PERSON 4 GET ONTO THE


SCAFFOLD & HOOK 1.8M LANYARD ON
IT

5. PERSON 4 UNHOOK LANYARD 1


FROM HIS BODY & UNHOOK 1.8M
FROM THE SCAFFOLD THEN GOING
DOWN

6. PERSON 3 REPEART AT THE SAME


PROCEDURE AS PERSON 4

7. PERSON 1 & 2 KEEP IN HIS POSITION

* Only 2 persons allowed to


dismantle fall protection
system at this stage

29
WORK SEQUENCE : DEMOBILISATION
No. Description
25.

2. PERSON 1 WILL UNHOOK THE


EXISTING RETRACTABLE LANYARD 4
AND SECURE IT TO ANCHOR PLATE 1

* Only 2 persons allowed to


dismantle fall protection
system at this stage

30
WORK SEQUENCE : DEMOBILISATION
No. Description
26.

* Only 2 persons allowed to


dismantle fall protection
system at this stage

31
WORK SEQUENCE : DEMOBILISATION
No. Description
27.

* Only 2 persons allowed to


dismantle fall protection
system at this stage

32
WORK SEQUENCE : DEMOBILISATION
No. Description
28.

33
WORK SEQUENCE : DEMOBILISATION
No. Description
29.

Housekeeping and close related


documents

1. Housekeeping After finish job

2. Quality check with dealer

3. Close related documents

Demobilization

1. De-Brief Station on Completion &


Conduct Site Pre-Handover

2. Dismantle Mobile Aluminium


Scaffolding

3. Site Clearing, Cleaning and Touch-


up Works

4. Dismantle Green Zone etc

5. Demobilisation

34