Professional Documents
Culture Documents
Delay
NGAI Kwan Wa 20038435S
WONG Cheong Fat 22056830S
WONG Shi Hon 22043963S
YIU Ho Pan 22046105S
Definition
Definition of Time for Completion and
Concurrent Delay
According to the Standard Form of Building Contract Private Edition – With
Quantities 2005 Edition Cl. 23 – Possession, commencement and
completion, sub-clause 23.2, the definition of completion can be defined
as follow:
The Contractor shall commence the Works on the Commencement Date stated in
the Appendix or when instructed to do so by the Architect, proceed regularly and
diligently with the Works and complete the Works, and, where sectional
completion is provided for in the Contract, any Section on or before the
Completion Date of the Works or that Section stated in the Appendix.
Concurrent Delay
The term "concurrent delay" is generally used in circumstances where a period
of delay to the completion of a project is caused by two or more factors, one of
which is the contractor's responsibility and one of which is the employer's
responsibility. In practice, the phrase is more often used to describe the
situation where the competing events occur at different times but their
delaying effects on the work are felt at the same time.
Dispute
The Main Contractor’s entitlement to extensions of time for delays but
Developer's (“defendant's”) associated entitlement to levy liquidated damages
for the Main Contractor's own culpable delay.
The Developer relies on a notice provision in the extension of time (“EOT”)
clause which is framed as a condition precedent, with which the Developer
alleges the plaintiff has not complied, thus barring any EOT claim.
Contra the plaintiff, who relies in particular on the absence of any certificate
from the Architect as provided for in the liquidated and ascertained damages
(“LADs”) clause (or the entitlement to one) certifying the Architect's opinion
that the works ought reasonably to have been completed by the Date of
Completion.