Project: Construction Of Broad Gauge Rail Line From Madhukhali To Magura Via Kamarkhali.

CREC-CCCL-JV
Subsection D: Bridges & Culverts
Single Vent Package WD-01 Date:13.08.21

1 Ch.00+793 (Culvert No:01)


N0 L B H Qty Unit
Top Slab 1 6.85 4.2 0.6 17.262 Cum
Bottom Slab 1 16.05 5.057 0.6 48.69891 Cum
Abbatment Wall 2 8.85 0.6 2 21.24 Cum
Wing wall 4 3.4 0.52 1.85 13.0832 Cum
Return Wall 4 1 0.52 1 2.08
Cut of Wall 2 8.914 0.2 1 3.5656 Cum
Wheel Guard 2 4.2 0.5 0.3 1.26 Cum
TOTAL 107.18971
CC 1 16.2 5.207 0.1 8.43534 Cum Reinforcement
Cut of Wall CC 2 8.914 0.2000 0.1 0.35656 21035.9805875
TOTAL 8.792 Cum OK
Box Cutting 1 16.2 5.207 1.31 110.502954 Cum
Filling Sand 1 16.2 5.207 0.3 25.30602 Cum

Single Vent
2 Ch.01+434 (Culvert No:01)
N0 L B H Qty Unit
Top Slab 1 6.85 4.2 0.6 17.262 Cum
Bottom Slam 1 20.85 6.554 0.6 81.99054 Cum
Abbatment Wall 2 8.85 0.6 3.4 36.108 Cum
Wing Wall 4 6 0.52 2.5 31.2 Cum
Cut Of Wall 2 11.908 0.2 1 4.7632 Cum
Wheel Guard 2 4.2 0.5 0.3 1.26 Cum
TOTAL 172.58374
CC 1 21 6.704 0.1 14.0784 Cum Reinforcement
Cut of Wall CC 2 11.908 0.2000 0.1 0.47632 33869.558975
TOTAL 14.555 Cum OK
Box Cutting 1 21 6.704 1.708 1683.213504 Cum
Filling Sand 1 21 6.704 0.5 492.744 Cum

Single Vent
3 2+050
N0 L B H Qty Unit
Top Slab 1 6.85 4.2 0.6 17.262 Cum
Bottom Slam 1 18.99 6.018 0.6 68.569092 Cum
Abbatment Wall 2 8.85 0.6 2.9 30.798 Cum
Wing Wall 4 5.07 0.52 2.25 23.7276 Cum
Cut Of Wall 2 10.836 0.2 1 4.3344 Cum
Wheel Guard 2 4.2 0.5 0.3 1.26 Cum
TOTAL 145.951092
CC 1 19.14 6.168 0.1 11.805552 Cum Reinforcement
Cut of Wall CC 2 10.836 0.2000 0.1 0.43344 28642.901805
TOTAL 12.239 Cum OK
Box Cutting 1 19.14 6.168 1.968 1858.66610688 Cum
Filling Sand 1 19.14 6.168 0.5 472.22208 Cum

Single Vent
4 2+420
N0 L B H Qty Unit
Top Slab 1 6.85 4.2 0.6 17.262 Cum
Bottom Slam 1 22.45 7.014 0.6 94.47858 Cum
Abbatment Wall 2 8.85 0.6 3.5 37.17 Cum
Wing Wall 4 6.8 0.52 2.55 36.0672 Cum
Cut Of Wall 2 12.828 0.2 1 5.1312 Cum
Wheel Guard 2 4.2 0.5 0.3 1.26 Cum
TOTAL 191.36898
CC 1 22.6 7.164 0.1 16.19064 Cum Reinforcement
Cut of Wall CC 2 12.828 0.2000 0.1 0.51312 37556.162325
TOTAL 16.704 Cum OK
Box Cutting 1 22.6 7.164 1.476 716.9215392 Cum
Filling Sand 1 22.6 7.164 0.5 242.8596 Cum
Single Vent
5 2+920
N0 L B H Qty Unit
Top Slab 1 6.85 4.2 0.6 17.262 Cum
Bottom Slam 1 23.25 7.244 0.6 101.0538 Cum
Abbatment Wall 2 8.85 0.6 4 42.48 Cum
Wing Wall 4 7.2 0.6 2.8 48.384 Cum
Cut Of Wall 2 13.288 0.2 1 5.3152 Cum
Wheel Guard 2 4.2 0.5 0.3 1.26 Cum
TOTAL 215.755
CC 1 23.4 7.394 0.1 17.30196 Cum Reinforcement
Cut of Wall CC 2 13.288 0.2000 0.1 0.53152 42341.91875
TOTAL 17.833 Cum OK
Box Cutting 1 23.4 7.394 1.72 297.593712 Cum
Filling Sand 1 23.4 7.394 0.5 86.5098 Cum
Single Vent Culvert
SI Description of Item QUANTITY UNIT Proportion
No Cement Sand Aggregate

1 RCC 12365.146462 Cum 1 1.25 2.25


2 CC 955.29 cum 1 2 4
3 Box Cutting 4666.90 cum
4 Filling Sand 5559.63 cum

Total
Qty. of Sand Sand Sand Stone Brick 1st Class
Cement(bag) (F.M = 1.5) (F.M = 2.5) (F.M =0.8) Aggregate Aggregate Bricks
cft cft cft cft cft Nos
123651.46 231,846.50 347769.74
6141.13 18,423.39 30705.65
- - - -
245,422.95
129,792.60 250,269.89 245,422.95 378,475.40
129,793.00 250,270.00 - 245,423.00 378,476.00 - -
Project: Construction Of Broad Gauge Railway Line From Madhukhali To Magura Via Kamarkhali.
Location : Magura
CREC-CCCL-JV
Subsection D: Bridges & Culverts
Package WD-01
QUANTITY OF MATERIAL FOR CULVERT

SL NO. ITEM UNIT Quantity Rate (tk) Amount (Tk.) Remarks


1 Cement cum Err:509 450.00 Err:509
2 Sand (F.M 0.80) cft Err:509 8.00 Err:509
3 Sand (F.M 1.5) cft Err:509 30.00 Err:509
4 Sand (F.M 2.5) cft 0.00 55.00 0.00
5 20 mm down well graded Stone chips cft Err:509 150.00 Err:509
7 Reinforcement (60 Grade) ton 270.86 72000.00 19502136.00
8 Polythene sheet Rool 10.00 1200.00 12000.00
Err:509

Page 5 of 5