REQUEST FOR QUOTATION

Description of work Unit Qty Price Cost


Supply and application of zinc primer, primer and Self
1 levelling screed of ardex endura make and Vinyl Sft 120 -
flooring of 1 MM thick
Supply and fabrication of MS works of FE350 grade for
2 Glass partition works kg 500 -
supply and installation of 12mm thick cement board
and finishing the same with 2 coats of putty , 1coat of
3 primer and 2 coats of exterior grade paint to match Sft 1,500 -
the colour with existing finish

Supply and installation of 12mm tuffen glass partion


4 with channels. Weather resistant silicon to be filled in sft 460 -
grooves of glass

Supply and installation of 12mm tuffen glass doors of


6 5x7 feets double doors.Price to include all necessary Nos 2 -
hardware and cutouts

Supply and application of 2 coats of apex ultima paint


6 on elevation of building including crack filling using Sft 85,000 -
dr.fixit shrinkfree material
Supply and application of texture including 2 coats of
apex ultima paint on elevation of building including
7 crack filling using dr.fixit shrinkfree material Sft 200 -

Supply and installation of Wooden door and flush


8 door of 3X6.5 feet including painting Nos 1 -
providing and construction of solid block work of
9 200mm thick sft 300 -
Plastering of blockwork with 20 mm thick with 1:4
10 cement and sand ratio sft 800 -
11 Providing and laying of M35 concrete works cum 12 -
12 supply and installation of frosted flim Sft 230 -
TOTAL -

Note:
1 Scaffolding supply and fixing is in contractors scope all rates are included in above BOQ
2 The above quoted price is excluding GST @ 18% or as applicable
3 All the quantities calculated are on priliminary survey conducted. Bill shall be claimed as per actuals
4 Power and water shall be provided by client
5 Any laisoning between authorities shall be under clint scope