Schedule Health Check Dashboard

Activity Type
Available Available % Target
Description
Start Milestone 3 1.69% 2.00%
Finish Milestone 3 1.69% 2.00%
WBS Summary 0 0.00% 0.00%
Level Of Effort 4 2.26% 5.00%
Task Dependent 167 94.35% 90.00%
Resource Dependent 0 0.00% 1.00%
Update Index
Description Available % Target
Activity Status: Not Started 29 16.38% -
Activity Status: In Progress 35 19.77% -
Activity Status: Completed 113 63.84% -
Activity does not Available in BSL 0 0.00% 2.00%
Count if activitiess need to define in baseline
Not Started Error - Start > 0 0 0.00% 0.05%
Activity not started but the start included the date
In Progress Error - ACT > DD 2 1.13% 0.00%
Actual Date is greater than Data Date
In Progress Error - ACT = 00.0% 2 1.13% 1.00%
In progress Activity with 0% progress
Completed Error - ACT < 100% 0 0.00% 1.00%
Completed activity with less than 100% Progress
Completed Error - ACT > 00.0% 0 0.00% 0.50%
Completed Activity without Finish Date
Invalid Date 2 1.13% 0.00% 0
Missed Task 0 0.00% 5.00% 1

Page 1 of 5 Adobted with Primavera P6


Schedule Health Check Dashboard
Resource Index
Description QTY % Target
Activity Without Resource 0 0.00% 1.00% 1
Resource does not assigned to the activities
Labor 46,352 65.06% -
Nonlabor 4,248 15.66% -
Material 1,744 19.29% -

Critical Path
Description Available % Target
Critical Activities 6 3.39% 3~5%
Start to Start (SS) SS 1 16.67% 16.00%
Finish to Start (FS) FS 4 66.67% 80.00%
Start to Finish (SF) SF 0 0.00% 1.00%
Finish to Finish (FF) FF 1 16.67% 3.00%
Days 0
Free Float 0.00% -
QTY 0
Large Free Float > 44 QTY 0 0.00% 0.05%
Relationships Lead Days 0 0.00% 1.00%
Large Lead > -25 Days 0 0.00% 0.00%
Relationships Lag Days 8 0.47% 2.50%
Large Lag > 5 QTY 1 0.47% 1.00%

Critical Path Length + Total Float


CPLI Calculator:
Critical Path Length

BEI Calculator: Total No of Tasks Complete


(Baseline Execution Index) No of Tasks that should be Complete

Page 2 of 5 Adobted with Primavera P6


Schedule Health Check Dashboard

Relasionship
Description Available % Target
Start to Start SS 19 8.88% 8.00%
Finish to Start FS 186 86.92% 90.00%
Start to Finish SF 0 0.00% 1.00%
Finish to Finish FF 9 4.21% 1.00%
Predessessor Free 1 0.56% 2.50%
Dangle Activities
Successor Free 4 2.26% 2.50%
Lead 0 0.00% 0.00%
Lead is Negative Lag between relationships
Lag 17 9.60% 5.00%
Lag: delay between two activity relationships
Long Lag > 8 Days 5 2.82% 2.50%
High Duration > 44 Days 4 2.26% 5.00%
Free Float QTY 11 6.21% 7.00%
Large Free Float > 44 Days 6 3.39% 5.00%
Total Float QTY 64 36.16% 10~12%
Large Total Float > 44 Days 36 20.34% 5.00%
Negative Float 0 Days 0 0.0% 0.00%
Mandatory Start 0 0.00% 2.50%
Hard Constraint
Mandatory Finish 0 0.00% 2.50%
Finish On or After 0 0.00% 0.50%
Finish On 0 0.00% 0.50%
Start On or After 1 0.56% 0.50%
Soft Constraint Start On 0 0.00% 0.50%
Start On or Before 0 0.00% 0.50%
As Late As Possible 0 0.00% 0.50%
Finish On or Before 0 0.00% 0.50%

Page 3 of 5 Adobted with Primavera P6


Schedule Health Check Dashboard
DCMA-14 Short Result
Index Status Remarks
1. Logic Pass
2. Lead Pass
3. Lag Fail
4. FS Relationship Pass
5. Hard Constraint Pass
6. High Float Pass
7. Negative Float Pass
8. High Duration Pass
9. Invalid Date Fail
10. Invalid Resources Pass
11. Missed Activities Pass
12. Critical Path Test Pass Please Insert the result Manually
13. CPLI Pass
14. BEI Fail

Specifications:

1- Adopted with Primavera P6 (all versions)


2- Easy to use
3- Online support
4- Covers all DCMA-14 indexes
5- Easy adaptation to new project indexes

Page 4 of 5 Adobted with Primavera P6


Schedule Health Check Dashboard

R Resource Report

E
M
P Activity Type
A Report
O
P
R Activity
T Relationships
Report
Contact us
www.globalprojectcontrol.com

Page 5 of 5 Adobted with Primavera P6


Prepared on: Prepared By:
Schedule Health Check Dashboard 05-Dec-2022
Data Date 20-Apr-22 Ahmad Setayandeh
Activity Type
Description
Available Available % Target
Description
Relasionship
Available % Target
Critical Path Index Chart
Start Milestone 3 1.69% 2.00% Start to Start SS 19 8.88% 8.00%
Finish Milestone 3 1.69% 2.00% Finish to Start FS 186 86.92% 90.00% 1
WBS Summary 0 0.00% 0.00% Start to Finish SF 0 0.00% 1.00%
1.00%
Level Of Effort 4 2.26% 5.00% Finish to Finish FF 9 4.21% 1.00%
Large Lag >
Task Dependent 167 94.35% 90.00% Predessessor Free 1 0.56% 2.50% 1
Dangle Activities 0.47%
Resource Dependent 0 0.00% 1.00% Successor Free 4 2.26% 2.50%
Lead 0 0.00% 0.00% 1
Update Index Lead is Negative Lag between relationships
Description Available % Target Lag 17 9.60% 5.00% 0
Activity Status: Not Started 29 16.38% - Lag: delay between two activity relationships
Activity Status: In Progress 35 19.77% - Long Lag > 8 Days 5 2.82% 2.50%
0.00%
Activity Status: Completed 113 63.84% - High Duration > 44 Days 4 2.26% 5.00% 1 Lead >
Large
Activity does not Available in BSL 0 0.00% 2.00% Free Float QTY 11 6.21% 7.00%
0.00%
Count if activitiess need to define in baseline Large Free Float > 44 Days 6 3.39% 5.00% 1
Not Started Error - Start > 0 0 0.00% 0.05% Total Float QTY 64 36.16% 10~12%
Activity not started but the start included the date Large Total Float > 44 Days 36 20.34% 5.00%
In Progress Error - ACT > DD 2 1.13% 0.00% Negative Float 0 Days 0 0.0% 0.00% 1
Actual Date is greater than Data Date Mandatory Start 0 0.00% 2.50% 1
Hard Constraint
In Progress Error - ACT = 00.0% 2 1.13% 1.00% Mandatory Finish 0 0.00% 2.50%
0.05%
In progress Activity with 0% progress Finish On or After 0 0.00% 0.50%
Large Free Float >
Completed Error - ACT < 100% 0 0.00% 1.00% Finish On 0 0.00% 0.50%
0.00%
Completed activity with less than 100% Progress Start On or After 1 0.56% 0.50%
Completed Error - ACT > 00.0% 0 0.00% 0.50% Soft Constraint Start On 0 0.00% 0.50%
Completed Activity without Finish Date Start On or Before 0 0.00% 0.50%
Invalid Date 2 1.13% 0.00% 0 As Late As Possible 0 0.00% 0.50%
0.00% 0.20% 0.40% 0.60% 0.80% 1.00% 1.20%
Missed Task 0 0.00% 5.00% 1 Finish On or Before 0 0.00% 0.50%
Target Available %
Resource Index DCMA-14 Short Result
Description QTY % Target Index Status Remarks Index Status Remarks
Activity Without Resource 0 0.00% 1.00% 1 1. Logic Pass 8. High Duration Pass
Resource does not assigned to the activities 2. Lead Pass 9. Invalid Date Fail
Labor 46,352 65.06% - 3. Lag Fail 10. Invalid Resources Pass
Nonlabor 4,248 15.66% - 4. FS Relationship Pass 11. Missed Activities Pass
Material 1,744 19.29% - 5. Hard Constraint Pass 12. Critical Path Test Pass Please Insert the result Manually
6. High Float Pass 13. CPLI Pass
Critical Path 7. Negative Float Pass 14. BEI Fail
Description Available % Target
Critical Activities 6 3.39% 3~5%
CPLI Calculator:
Critical Path Length + Total Float Critical Path Length 44888 CPLI = Pass
Start to Start (SS) SS 1 16.67% 16.00% Critical Path Length CP Total Float 0
Finish to Start (FS) FS 4 66.67% 80.00%
Start to Finish (SF) SF 0 0.00% 1.00% BEI Calculator: Total No of Tasks Complete Tasks Complete: 113 BEI = Fail
Finish to Finish (FF) FF 1 16.67% 3.00% (Baseline Execution Index) No of Tasks that should be Complete Should be Complete: 146
Days 0
Free Float 0.00% -
QTY 0 Narrative Report:
Large Free Float > 44 QTY 0 0.00% 0.05%

Monitor Projects KPIs with DCMA-14 indexes


Relationships Lead Days 0 0.00% 1.00%
Large Lead > -25 Days 0 0.00% 0.00%
Relationships Lag Days 8 0.47% 2.50%
Large Lag > 5 QTY 1 0.47% 1.00%