Professional Documents
Culture Documents
Activity Type
Available Available % Target
Description
Start Milestone 3 1.69% 2.00%
Finish Milestone 3 1.69% 2.00%
WBS Summary 0 0.00% 0.00%
Level Of Effort 4 2.26% 5.00%
Task Dependent 167 94.35% 90.00%
Resource Dependent 0 0.00% 1.00%
Update Index
Description Available % Target
Activity Status: Not Started 29 16.38% -
Activity Status: In Progress 35 19.77% -
Activity Status: Completed 113 63.84% -
Activity does not Available in BSL 0 0.00% 2.00%
Count if activitiess need to define in baseline
Not Started Error - Start > 0 0 0.00% 0.05%
Activity not started but the start included the date
In Progress Error - ACT > DD 2 1.13% 0.00%
Actual Date is greater than Data Date
In Progress Error - ACT = 00.0% 2 1.13% 1.00%
In progress Activity with 0% progress
Completed Error - ACT < 100% 0 0.00% 1.00%
Completed activity with less than 100% Progress
Completed Error - ACT > 00.0% 0 0.00% 0.50%
Completed Activity without Finish Date
Invalid Date 2 1.13% 0.00% 0
Missed Task 0 0.00% 5.00% 1
Critical Path
Description Available % Target
Critical Activities 6 3.39% 3~5%
Start to Start (SS) SS 1 16.67% 16.00%
Finish to Start (FS) FS 4 66.67% 80.00%
Start to Finish (SF) SF 0 0.00% 1.00%
Finish to Finish (FF) FF 1 16.67% 3.00%
Days 0
Free Float 0.00% -
QTY 0
Large Free Float > 44 QTY 0 0.00% 0.05%
Relationships Lead Days 0 0.00% 1.00%
Large Lead > -25 Days 0 0.00% 0.00%
Relationships Lag Days 8 0.47% 2.50%
Large Lag > 5 QTY 1 0.47% 1.00%
Relasionship
Description Available % Target
Start to Start SS 19 8.88% 8.00%
Finish to Start FS 186 86.92% 90.00%
Start to Finish SF 0 0.00% 1.00%
Finish to Finish FF 9 4.21% 1.00%
Predessessor Free 1 0.56% 2.50%
Dangle Activities
Successor Free 4 2.26% 2.50%
Lead 0 0.00% 0.00%
Lead is Negative Lag between relationships
Lag 17 9.60% 5.00%
Lag: delay between two activity relationships
Long Lag > 8 Days 5 2.82% 2.50%
High Duration > 44 Days 4 2.26% 5.00%
Free Float QTY 11 6.21% 7.00%
Large Free Float > 44 Days 6 3.39% 5.00%
Total Float QTY 64 36.16% 10~12%
Large Total Float > 44 Days 36 20.34% 5.00%
Negative Float 0 Days 0 0.0% 0.00%
Mandatory Start 0 0.00% 2.50%
Hard Constraint
Mandatory Finish 0 0.00% 2.50%
Finish On or After 0 0.00% 0.50%
Finish On 0 0.00% 0.50%
Start On or After 1 0.56% 0.50%
Soft Constraint Start On 0 0.00% 0.50%
Start On or Before 0 0.00% 0.50%
As Late As Possible 0 0.00% 0.50%
Finish On or Before 0 0.00% 0.50%
Specifications:
R Resource Report
E
M
P Activity Type
A Report
O
P
R Activity
T Relationships
Report
Contact us
www.globalprojectcontrol.com