12.0 General conditions applicable during supply, installation and commissioning phase
12.1 Vendor shall organize construction power supply on their own. Accordingly, if required, DG sets of
suitable capacity shall be deployed by the vendor for construction works.
12.2 Similarly, water required for construction works shall be organized by vendor. Vendor shall organize
bore wells at the site if required. In case bore well is not successful, vendor shall
make their own alternate arrangements (water tankers etc).
12.3 All machinery such as cranes, hydra, JCBs, forklifts, transport trucks, trolleys, concrete mixers, Ajax
machines etc necessary for movement and installation of materials shall be organized by the vendor.