Faculty of Engineering
Petroleum Department
Petroleum Production Engineering
Sheet 3
Problem #1
Production interval 6507-6551 ft
Tubing depth 6500 ft
Static pressure at 6500 ft 2000 psig
Tubing size 2 3/8 inch
Horsepower 32
Gas is available at 15 psig. what would be the well’s production rate on gas lift,
assuming a THP of 250 psig? The well is currently flowing 200 bbl/day of clean oil
with a GOR of 600 cuft/bbl and a CHP of 1225 psig.
Problem #2
Production interval 9050-9200 ft
2 7/8 inch tubing 9100 ft
Static pressure at 9100 ft 3000 psig
PI 0.333 bbl/day/psi
GOR 450 cuft/bbl
Water cut zero