You are on page 1of 1

A BRIDGED 450mm Deep ALLOY BEAM

001
- Plan braced TOP chord - fixed at 1.00m centres
- Laced TOP chord at 1.00m centres

750
- Laced BOTTOM chord at 2.00m centres
- Section braced at 2.00m centres

All connection made using load bearing couplers.

700
Beam Capacities (Permissible Stress)

500
Min. Bending Moment Capacity = 15.70kN.m
Min. Shear Force Capacity = 12.70kN

CANTILEVERED 450mm Deep ALLOY BEAM


16.00kN TOTAL
UPLIFT REACTION Scaffold physically tied to the existing - Plan braced Bottom chord - fixed at 1.00m centres

1915
steel beam using paired girder couplers. Beams fixed to standards using 90° - Laced TOP chord at 2.00m centres
couplers at top and bottom chords - Laced BOTTOM chord at 1.00m centres
All tie tubes connected to standards
with a check transom to the underside - Section braced at 2.00m centres
using CLASS B 90° couplers.

315
of bottom chord.
All connection made using load bearing couplers.

Beam Capacities (Permissible Stress)


Beam support standards braced every
elevation (See Main Drawing). All Min. Bending Moment Capacity = 15.70kN.m
bracing fixed using load bearing Min. Shear Force Capacity = 12.70kN
couplers.

2215
Scaffold erected with bracing at EVERY
frame as shown. All bracing fixed using load
bearing couplers. Bracing connected no
greater than 300mm from the standard to
ledger node point. BEAM TO STANDARD
CONNECTION DETAIL

700
NTS
ALL 450mm Alloy beams fixed to support
60.00kN TOTAL standards using 90° couplers at top and bottom
REACTION (UNFACTORED) chords with a check transom fixed tight to the

2500
underside of the bottom chord connection.

Joints in standards spliced using a


butt tube with 1no. CLASS B swivel `

coupler BOTH sides of sleeve


coupler.
550

550
990

990
1000

1000
PUNCHEON & SUPPORT STANDARDS
SPLICE DETAIL
(1no. CLASS B swivel Connection)

Scaffold erected with section bracing at EVERY frame THE MAIN CONTRACTOR MUST ASSESS THE REACTION
B 750 2610 500 1420 2475 B 750 2610 500 1420 2475 as shown. All bracing fixed using load bearing couplers. LOADS SHOWN AND ENSURE THE SUPPORT FLOOR AND
001 001 Bracing connected no greater than 300mm from the EXISTING STEEL BEAMS ARE SUITABLE PRIOR TO
Puncheon guardrail post fixed to standard to ledger node point. ERECTION.
PLAN LAYOUT beams using 90° couplers at top PLAN LAYOUT ALL REACTION LOAD SHAVE BEEN SHOWN AS
All puncheons fixed to beams using 90° couplers
and bottom chords. All puncheons fixed to beams using 450mm Alloy beams fixed to support standards 'UN-FACTORED' LOADS.
LEVEL 1-1 at top and bottom chords with a check transom LEVEL 2-2 90° couplers at top and bottom using 90° couplers at top and bottom chords
A C fixed tight above the top chord connection.
chords with a check transom fixed with a check transom fixed tight to the
001 001
tight above the top chord underside of the bottom chord connection.
Scaffold erected with section bracing at EVERY frame as shown. All connection. 16.00kN UPLIFT
bracing fixed using load bearing couplers. Bracing connected no greater Denotes the Existing
Ducting Unit/Apparatus REACTION (SEE PLAN)
than 300mm from the standard to ledger node point.

2000
2345

2345
DETAIL 1

750 700 500 1915 2215 2500 550 990 1000


1000 990 550 2500 2215 1915 500 700 750
750 2610 500 1420 2475

3360 Max Cantilever Beams fixed to the support


puncheon using 90° couplers at the
top and bottom chords with a check
ELEVATION A-A 60.00kN TOTAL REACTION
ELEVATION B-B transom positioned tight to the SECTION C-C (UNFACTORED - SEE PLAN)
underside of the bottom hcord.
D 01/11/2022 Scaffold Layout Amended as Client Email M.E R.P
Scaffold physically tied to the C 21/02/2022 Scaffold Layout Amended as Client Email M.E R.P
existing steel beam using paired B 21/02/2022 Scaffold Layout Amended as Client Email M.E R.P
girder couplers. All tie tubes GENERAL NOTES Wind Loading
A 18/02/2022 Scaffold Layout Amended as Per Site Visit M.E R.P
Rev Date Revision Description Prepared by Checked by
connected to standards using This drawing is the Intellectual property of TAD Ltd. No unauthorised use, copy or disclosure is to be made without Wind loads have been generated in accordance with BS EN 1991-1-4: 2005. Kentledge
written consent. Peak Velocity Pressure (Qp): 0.690kN/m² Kentledge Loads should be positioned on the scaffold as per the drawing.
CLASS B 90° couplers. Main Contractor to ensure wind loads are adequate. Kentledge Load Per Bay: N/A
CDM Regulations 2015 Leg Loads Kentledge should be applied to scaffold on completion of first lift. Office: (+44) (0) 02921 660126
TAD LTD have understood and conformed with the responsibilities imposed by the Construction (Design & Maximum Axial Load: See Drawing Web: www.tad-designs.co.uk
Management) Regulations 2015. The Contractor should be aware of their duties imposed by the CDM Regulations Support Scaffolds Info@tad-designs.co.uk
2015. Standards founded on steel base plates (150 x 150mm) and 38mm thick soleboards unless stated otherwise. TAD Ltd will not pass comment on the condition of the existing building fabric. It is the contractors responsibility to 9 Bradenham Place, Penarth
Main Contractor to ensure the foundations are capable of supporting the leg loads stated. ensure that the existing structure will safely span between scaffold supports, and can be safely supported in the way
Design Guidance Vale of Glamorgan
Where the scaffold is supported or suspended from an additional structure the main contractor must ensure that the indicated.
This drawing has been prepared in accordance with the following Standards and Technical Guidance: structure is capable of supporting the imposed loads. CF64 2AG
- NASC TG20:21 Temporary Roofs/Shelters
- BS EN 12811-1 Tie Loads TAD Ltd cannot ensure temporary roofs are erected watertight.
- BS 5975:2019 Temporary works procedures and the permissible stress design of falsework. Maximum Tie Load: See Drawing for Steel Work All ties indicated on the drawing must be installed prior to the construction of the roof structure. Job Title
-
-
BS EN 1991-1-4 : 2005 Wind Actions
BS EN 1991-1-3 : 2003 Snow Loads
Maximum Tie Load (Tensile):
Required Test Load (2.00 FoS):
10.00kN (5.00kN Per Band & Plate 2.50kN Per Anchor/Bolt)
5.00kN Per Anchor/Bolt
For mono-pitch temporary roofs, the minimum slope angle of the roof sheeting is 5° when using CI sheets.
For all roof systems the manufacturers guidance should be followed.
Finsbury Square - London
- SG4:15 - Preventing Falls in Scaffolding Operations Maximum Butt Load: N/A
Joints in standards spliced using a - Working at Height Regulations 2005. Cladding
Client
The Main Contractor is responsible for ensuring the existing structure is capable of supporting the imposed loads. No sheeting, signboards or hoarding, unless already shown, should be added to the scaffold without the written
butt tube with 1no. CLASS B swivel Loading The Contractor should consult with anchor specialist prior to selection. permission from TAD Ltd. Hawk Scaffolding Ltd
coupler BOTH sides of sleeve All Self-weights of materials comply with the loads stated within the TG20:21 and BSEN12811-1.
All Self-weights of proprietary equipment are in accordance with manufacturer's information.
Tie selection should be made by the contractor using guidance from TG4. All sheeting should be fixed externally to the scaffold unless otherwise stated on the drawing.
Ties should be tested in accordance with TG4.
coupler. Main Contractor to ensure that no ties are removed without the written approval of TAD LTD. Erection/Modification Drawing Title
Platform Loading
Scaffold platform loads are in accordance with the TG20:21 and BSEN12811-1. Scaffold Boards
This design has been prepared from information supplied to us by the Contractor. The Contractor should check that
their requirements have been correctly interpreted and depicted in a practicable design solution prior to erection. Cantilevered Access Scaffold
BOARDED LIFT LEVEL LEDGERS Load Class: 2 All Scaffold boards to comply with BS2482:2009. The contractor should verify all site dimensions and notify TAD Ltd of any discrepancies prior to erection.
1no. Lift at: 1.50kN/m² All scaffold boards are to be restrained. See TG12 for restraint guidance. No alterations are to be made to the scaffold structure detailed on this drawing without written consent from TAD Ltd.
SPLICE DETAIL 1no. Lift at: N/A (1no. Lift Loaded at Any one Time) All Written dimensions shall take precedence over scaled dimensions. Drawing Number Rev Prepared By Checked By

(1no. CLASS B swivel Connection) DETAIL 1 - GIRDER COUPLER TO Inside Boards:


No. of Boarded Lifts:
0.75kN/m²
2
Tube/Fittings
All scaffolding materials and fittings are to comply with TG20:21 and BS EN 12811-1. Drawing Status
21/TAD/181-001 D R.P M.E
EXISTING STEEL CONNECTION Main contractor to ensure the live load allowance is adequate prior to erection.
Scaffold tube has been taken as BS EN 39 type 4 'new' condition.
All scaffold fittings taken as load-bearing CLASS B fittings unless otherwise stated on the drawing. FOR DISCUSSION
NTS No alteration to the live load allowance should be made without the written consent of TAD Ltd. All proprietary equipment has been designed in accordance with the manufacturers specifications. Not For Construction Scale @ A1
1:50
Date
17/08/2021 CHECK CATEGORY (BS5975) 2

You might also like