Scheduling Professional (PMI-SP) Código Revisión: RA

Compound Questions # 3 Fecha 10-Sep-22


Resolving Negative Float Pagina Pág. 1 de 1

1. Resolving Negative Float


In the schedule activity path in the figure below, the total float (that is shared among the activities) has
dropped to -4 work days during the current update cycle. The full logic of ho network is not shown, only part
of it. Activity D ties into activity E (not shown) and the path continues to the end of the project Activity path
A-B-C-D ls the only path for which you are responsible hat is currently negative. You are the lead scheduler
and you must come up with recommendations as to how this negative condition can be solved.
Answer the following questions:
1. What does the negative total float for this path indicate?
2. What options do you have to return this path to zero float? Explain how your recommendations will
solve the negative float condition.
Duration

8 4 5 2
Activity X Activity A Activity B Activity C Activity D E
-4 -4 -4 -4

Total Float All duration are in work days

2. Based on the figure besides, answer the following questions.

a. What is the duration of the critical path in this network?


b. What kind of Activity is the Activity I; Hint not have a successor?
c. What is the Total Float of Activity F?
d. What is the Free Float of the Activity H?
e. Will be a good idea to link Activity I with Activity J?
f. Can you see any Redundant Logic or Loop in this network?
g. See activities A and C have an SS and FF relationship, Is this a good practice? give some comments.