You are on page 1of 5

NEOM-NLF-FRM-002.

01 NEOM Risk Assessment Form

Name of project
or activity:
Limak & Al-Ayuni Joint Venture – Neom Trojena Time Travel Tunnel, Depot & Vault Excavation NEOM code:
Component or
aspect of work:
Fatigue Sheet no. 1 of 5

Initial assessment Residual risk


Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Farooq Aziz
UL = Unlikely – unlikely but possible R N N A A A Prep’d: 28/2/24
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
3 =–Medium several causalities that might require hospitalization with long term effect M = Possible – possible at some time UL N A A AR AR Mushtaq Ansari
H =Likely – likely to occur several times Rev’d: 28/2/24
5 to 15 man-days (LTI) P A A AR AR UA

Likelihood
AC = Frequent – likely to occur many times
4 =High – •Would cause serious causalities result in long term physical impairment of personnel L A AR AR UA UA
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Limak & Al-Ayuni Joint Venture – Neom Trojena Time Travel Tunnel, Depot & Vault Excavation NEOM code:
Component or
aspect of work:
Fatigue Sheet no. 2 of 5

1 Work Related: Workers at work Fatigue Reduction Measures: • Control


People in Measures should
Poorly designed roster patterns Surroundings, Adequate and appropriate rostering be adhered by all
Appropriate working hours for tasks being members.
Length of shifts Public
undertaken • Team leader
Poor work Appropriate and adequate breaks within and should make sure
scheduling and planning between work periods all controls in
Timing of shifts e.g. night shift Ensuring high risk activities are conducted place every time
Insufficient recovery between during the day rather than at night where before and during
shifts possible
activity.
Long periods of time awake Reduce highly complex tasks Appropriate
4 H UA overtime policies Napping policy 4 P AR
Mentally or Appropriate staffing levels
physically draining work Team work/group reduce working alone.
Inadequate rest
breaks
Arduous tasks Fatigue Proofing Measures:
Excessive workload
Check lists for signs and symptoms of fatigue
Lack of work force Rotation of tasks.
(Mental Health Appropriate lighting levels
Issues Car-pooling
Provision of air conditioning Radio contact
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Farooq Aziz
UL = Unlikely – unlikely but possible R N N A A A Prep’d: 28/2/24
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
3 =–Medium several causalities that might require hospitalization with long term effect M = Possible – possible at some time UL N A A AR AR Mushtaq Ansari
H =Likely – likely to occur several times Rev’d: 28/2/24
5 to 15 man-days (LTI) P A A AR AR UA

Likelihood
AC = Frequent – likely to occur many times
4 =High – •Would cause serious causalities result in long term physical impairment of personnel L A AR AR UA UA
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Limak & Al-Ayuni Joint Venture – Neom Trojena Time Travel Tunnel, Depot & Vault Excavation NEOM code:
Component or
aspect of work:
Fatigue Sheet no. 3 of 5

Initial assessment Residual risk


Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
Sleep Apnea Provision of transport for personnel for
Irritating commutes after overtime
Behaviour Appropriate areas for taking breaks in comfort
Adequate ventilation
Injuries
Access to drinking water facility. Close
Fatality) supervision
Working in pairs or teams’ dependent on the
task
Self-checklists to assess for signs and
symptoms of fatigue
Experienced personnel to support new
personnel Communication at shift handover
Conversation
Reporting of other who may be fatigued.

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Farooq Aziz
UL = Unlikely – unlikely but possible R N N A A A Prep’d: 28/2/24
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
3 =–Medium several causalities that might require hospitalization with long term effect M = Possible – possible at some time UL N A A AR AR Mushtaq Ansari
H =Likely – likely to occur several times Rev’d: 28/2/24
5 to 15 man-days (LTI) P A A AR AR UA

Likelihood
AC = Frequent – likely to occur many times
4 =High – •Would cause serious causalities result in long term physical impairment of personnel L A AR AR UA UA
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Limak & Al-Ayuni Joint Venture – Neom Trojena Time Travel Tunnel, Depot & Vault Excavation NEOM code:
Component or
aspect of work:
Fatigue Sheet no. 4 of 5

2 Individual/ Lifestyle Based: Fatigue Reduction Measures:


Workers at work
Sleep loss and/or disruption of People in
internal. Surroundings, Know how much sleep they need and get it
Public Set up sleep environment to promote and protect
Poor quality of sleep Sleeping sleep
disorders Travel time Fatigue awareness/competency training.
Family needs
Sporting commitments Fatigue Proofing Measures:
Social life 4 H UA 4 P AR
A second job
Alcohol and/or drug abuse Self-selected break times when appropriate
Self checklists to assess for signs and symptoms of
Stress caused my factors outside of
fatigue
work
Self-reporting of fatigue
General physical and mental health
Easy access to family/friends via communication modes
Religious events when working away from home
(Mental Health Issues
Sleep Apnea Irritating behaviours
Injuries Fatality)

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Farooq Aziz
UL = Unlikely – unlikely but possible R N N A A A Prep’d: 28/2/24
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
3 =–Medium several causalities that might require hospitalization with long term effect M = Possible – possible at some time UL N A A AR AR Mushtaq Ansari
H =Likely – likely to occur several times Rev’d: 28/2/24
5 to 15 man-days (LTI) P A A AR AR UA

Likelihood
AC = Frequent – likely to occur many times
4 =High – •Would cause serious causalities result in long term physical impairment of personnel L A AR AR UA UA
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
NEOM-NLF-FRM-002.01 NEOM Risk Assessment Form

Name of project
or activity:
Limak & Al-Ayuni Joint Venture – Neom Trojena Time Travel Tunnel, Depot & Vault Excavation NEOM code:
Component or
aspect of work:
Fatigue Sheet no. 5 of 5

Health & safety severity: Likelihood: Assessed Severity Name & signature Date
risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI R = Rare – unlikely to occur Farooq Aziz
UL = Unlikely – unlikely but possible R N N A A A Prep’d: 28/2/24
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
3 =–Medium several causalities that might require hospitalization with long term effect M = Possible – possible at some time UL N A A AR AR Mushtaq Ansari
H =Likely – likely to occur several times Rev’d: 28/2/24
5 to 15 man-days (LTI) P A A AR AR UA

Likelihood
AC = Frequent – likely to occur many times
4 =High – •Would cause serious causalities result in long term physical impairment of personnel L A AR AR UA UA
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives.
AC A AR UA UA UA
Incident resulting in complete shutdown of operations

NEOM-NLFPRC-003 FRM 001 – Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible

You might also like