PERFORMANCE QUALIFICATION
PROTOCOL FOR STRIP PACKING
MACHINE
:
EQUIPMENT NAME
:
EQUIPMENT ID.
:
MODEL NO.
:
PQ PROTOCOL NUMBER
:
EFFECTIVE DATE
Page 1 of 18
Annexure No. QA-048/A05/00
Protocol No: PQP/SP/001/00 TITLE: PERFORMANCE Equipment ID:- PDC/SP/001
QUALIFICATION PROTOCOL Model No.
Revision No.
FOR STRIP PACKING MACHINE
Supersedes No. NIL
PROTOCOL CONTENTS
2.0 OBJECTIVE 4
3.0 SCOPE 4
4.0 RESPONSIBILITY 4
15.0 REFERENCES 18
21.0 RECOMMENDATION 18
22.0 ABBREVIATIONS 19
Page 2 of 18
Annexure No. QA-048/A05/00
Equipment ID: PDC/SP/001
Protocol No: PQP/SP/001/00
TITLE: PERFORMANCE
Revision No. QUALIFICATION PROTOCOL FOR Model No.
STRIP PACKING MACHINE
Supersedes No. NIL Effective Date:-
INITIATED BY:
OFFICER/EXECUTIVE - QA
REVIEWED BY:
HEAD -PRODUCTION
HEAD -ENGINEERING
APPROVED BY:
HEAD - QA
Page 3 of 18
Annexure No. QA-048/A05/00
Protocol No: PQP/SP/001/00 TITLE: PERFORMANCE Equipment ID:- PDC/SP/001
QUALIFICATION PROTOCOL Model No.
Revision No.
FOR STRIP PACKING MACHINE
Supersedes No. NIL
2.0 OBJECTIVE:
To provide documented evidence that the Equipment is performing as per the parameter defined
in Operational Qualification and that it gives result as per the predetermined acceptance criteria.
To demonstrate that the system will operate reproducibly and consistently within its operating
range.
To confirm the suitability of the Standard Operating Procedures for all routine activities
associated with the system.
The Document also provides the observed and obtained values indicating compliance to the PQ
Report.
3.0 SCOPE:
The Protocol covers all aspects of Performance Qualification for the Strip Packing
Machine at GMH Laboratories Bhatoli Kalan, Baddi (H.P.)
This Protocol will define the methods and documentation used to qualify the Strip Packing
Machine at GMH Laboratories Bhatoli Kalan, Baddi (H.P.)
4.0 RESPONSIBILITY:
The Validation Group, comprising of a representative from each of the following Departments, shall
be responsible for the overall compliance of this Report:
DEPARTMENTS RESPONSIBILITIES
Review of Protocol.
Engineering
To co-ordinate and support Performance Qualification Activity.
Page 4 of 18
Annexure No. QA-048/A05/00
Equipment ID: PDC/SP/001
Protocol No: PQP/SP/001/00
TITLE: PERFORMANCE
Revision No. QUALIFICATION PROTOCOL FOR Model No.
STRIP PACKING MACHINE
Supersedes No. NIL Effective Date:-
Review of Report.
Production
To co-ordinate and support Performance Qualification Activity.
Equipment Name
Equipment ID.
Manufacturer’s Name
Supplier’s Name
Model
Equipment No.
Location of Installation
All main stations are Servo controlled, with the exception of the high speed section (perforation,
embossing and STRIP pack punch-out section).
In operation, the base-film is intermittently drawn from either of the two reel stocks and fed to the
STRIP forming station.
Base film unwind is motorized. It ensures drawing of the film (into the pre- heaters), without undue
tension or jerks, which would otherwise cause lengthwise stretching and widthwise shrinking of the
film.
The thermoform film is heated by platen heaters, just before the STRIP forming station and then (in
the next cycle) advanced into the dies of the STRIP forming station. The top and bottom preheaters
have individual temperature adjustment. Preheaters can open wide at machine stop to avoid
overheating of base film, and open just sufficiently between cycles to allow for index.
Page 5 of 18
Annexure No. QA-048/A05/00
Protocol No: PQP/SP/001/00 TITLE: PERFORMANCE Equipment ID:- PDC/SP/001
QUALIFICATION PROTOCOL Model No.
Revision No.
FOR STRIP PACKING MACHINE
Supersedes No. NIL
In the forming station, thermoform STRIPs are formed with the help of
compressed air alone, or
plug-assisted thermoforming, or
cold forming.
Preheaters are switched off while cold forming. Changeover between modes is simply by doing the
appropriate selection on the HMI.
The formed web is then led over a guide-track. Next, the product is filled into the STRIP cavities.
Then, the web enters the sealing unit along with the bidding material. The lid foil reel is also mounted
on a mandrel which is motorized, and a dancing arm switches the motor on or off to deliver additional
foil, as and when needed. Lidding material is pulled in to the sealing station, where it is sealed with the
base-web, thus enclosing the product hermetically. The sealed web is cooled immediately on exit from
the sealing station by a cooling plate.
The filled, sealed and cooled web is gripped and pulled through the set index (advance) value by a
gripped indexing mechanism. The index value is settable on the HMI.
The sealed web, then, moves over a dancer arm, into the high speed section of the machine, where it is
independently advanced intermittently by a servo-driven punch index roller. Its index frequency is
determined by the “number of repeats per frame" and its index value (in degrees) is determined by the
“punch index slots”.
Embossing, perforation and punching are carried out and the packs are thus separated from the web.
At the same time, trim is cut and dropped into the trim chute. Packs are picked up by an oscillating
pack-pickup assembly, off the punching tool. These are transported up to the outfeed conveyor or
chute if they are good, or are dropped earlier into a reject chute (this is possible if the machine is
equipeed with an optional non-fill detect camera).
Electrical supply to the machine is 415Vac, 3-Phase/N/E, 50Hz (nominal). There are two separate
supply points given in the machine, viz. Electrical supply for the Heaters & Electrical supply for the
rest of the machine components. The scheme is to provide UPS supply to the machine (supplying
Control circuit, Servo amplifiers, VFDs, 24Vdc SMPS & PLf only) & raw Mains 3-Phase supply for
the heating circuit. Each of these supply input points are indicated with respective stickers that indicate
UPS SUPPLY & HEATER SUPPLY.
The Mains supply to the UPS is interlocked in a way that a digital input in the machine controller rack,
changes state whenever this supply to UPS, falls below certain value that is preset within the UPS unit.
In cnse of Mains supply failure, the machine HMI indicates an alarm as such & allows the machine
cycle to run (in cnse the machine is running in cycle) till a settable count (in HMI).
Page 6 of 18
Annexure No. QA-048/A05/00
Equipment ID: PDC/SP/001
Protocol No: PQP/SP/001/00
TITLE: PERFORMANCE
Revision No. QUALIFICATION PROTOCOL FOR Model No.
STRIP PACKING MACHINE
Supersedes No. NIL Effective Date:-
Tablet Primary Packing Area at GMH Laboratories Bhatoli Kalan, Baddi (H.P.)
In case of any deviation observed during PQ, inform to Head QA for necessary action.
Document the deviation detail in observed deviation section.
The Head QA will study the impact of deviation. If deviation is acceptable and it does not
have an impact on operation as well as on performance of the machine, prepare final conclusion.
The results of any tests should meet the limits and acceptance criteria specified in the test documents.
Any deviations or issues should be rectified and documented prior to PQ commencing
Page 7 of 18
Annexure No. QA-048/A05/00
Protocol No: PQP/SP/001/00 TITLE: PERFORMANCE Equipment ID:- PDC/SP/001
QUALIFICATION PROTOCOL Model No.
Revision No.
FOR STRIP PACKING MACHINE
Supersedes No. NIL
CHECKED BY VERIFIED BY
DOCUMENT/ COMPLETED
S. No. DOCUMENT NAME (PRODUCTION) (QA)
SOP No. (YES / NO)
(SIGN& DATE) (SIGN/DATE)
1. DQ Protocol
2. IQ Protocol
3. OQ Protocol
Operating Procedure
4.
SOP
Cleaning Procedure
5.
SOP
Verify that all critical instruments associated with the system will be in a calibrated state. Review the
calibration status for the test equipment to be utilised and record the calibration due dates in the table
below.
EQUIPMENT / EQUIPMENT /
CALIBRATION CALIBRATION OBSERVED BY
INSTRUMENTS INSTRUMENTS
DONE ON DUE ON SIGN & DATE
NAME ID.
Page 8 of 18
Annexure No. QA-048/A05/00
Equipment ID: PDC/SP/001
Protocol No: PQP/SP/001/00
TITLE: PERFORMANCE
Revision No. QUALIFICATION PROTOCOL FOR Model No.
STRIP PACKING MACHINE
Supersedes No. NIL Effective Date:-
SELECTION OF BATCH
Sr. No Name of the Product Batch Number Batch Size Mfg. Exp.
Materials:
Ensure that, below listed; required materials are available before the performance qualification
activities are carried out.
Material Availability
Batch Checked Verified
Date Name of Product Aluminium
Number Tablets Stereos By By
foil
Page 9 of 18
Annexure No. QA-048/A05/00
Protocol No: PQP/SP/001/00 TITLE: PERFORMANCE Equipment ID:- PDC/SP/001
QUALIFICATION PROTOCOL Model No.
Revision No.
FOR STRIP PACKING MACHINE
Supersedes No. NIL
Page 10 of 18
Annexure No. QA-048/A05/00
Equipment ID: PDC/SP/001
Protocol No: PQP/SP/001/00
TITLE: PERFORMANCE
Revision No. QUALIFICATION PROTOCOL FOR Model No.
STRIP PACKING MACHINE
Supersedes No. NIL Effective Date:-
Page 11 of 18
Annexure No. QA-048/A05/00
Protocol No: PQP/SP/001/00 TITLE: PERFORMANCE Equipment ID:- PDC/SP/001
QUALIFICATION PROTOCOL Model No.
Revision No.
FOR STRIP PACKING MACHINE
Supersedes No. NIL
Collect 100 STRIPs after cutting and Physically There should not be any abnormal
Foil Shift check the smooth flow of foils as per the speed of sifting of foils and cutting of the
machine. STRIPs should be proper.
Equipment / system should pass through the following challenge test or worse case scenario test to
check the performance of the equipment in the worse case condition.
Page 12 of 18
Annexure No. QA-048/A05/00
Equipment ID: PDC/SP/001
Protocol No: PQP/SP/001/00
TITLE: PERFORMANCE
Revision No. QUALIFICATION PROTOCOL FOR Model No.
STRIP PACKING MACHINE
Supersedes No. NIL Effective Date:-
Run the machine at high speed and No empty pocket, No leak of pocket and
Speed Performance
collect STRIPs of consecutive 100 clear over printing should be observed and
(High Speed)
cuttings. out put should match with set speed.
All safety features and alarm performance should be verified during the performance qualification
Page 14 of 18
Annexure No. QA-048/A05/00
Equipment ID: PDC/SP/001
Protocol No: PQP/SP/001/00
TITLE: PERFORMANCE
Revision No. QUALIFICATION PROTOCOL FOR Model No.
STRIP PACKING MACHINE
Supersedes No. NIL Effective Date:-
Pin hole detection performance should be verified during the performance qualification and should
be documented.
Test Method of Test Acceptance Criteria
The pack having a pinhole is detected
by the pinhole Detector. On the MMI
screen the alarm displayed is:
PINHOLE DETECTED IN BASE
Using a pin, pierce a tiny traceable/ FOIL. Machine cycle is not
identifiable hole in the aluminium interrupted. Subsequently, the entire
Pin Hole Detection Check
base foil before the base foil enters corresponding repeat containing the
into forming station. defective pack is discharged into
Rejection chute by the pick-and-place
device at the punching tool along with
a repeat earlier & later to the defective
pack.
Page 15 of 18
Annexure No. QA-048/A05/00
Protocol No: PQP/SP/001/00 TITLE: PERFORMANCE Equipment ID:- PDC/SP/001
QUALIFICATION PROTOCOL Model No.
Revision No.
FOR STRIP PACKING MACHINE
Supersedes No. NIL
This checklist is provided to ensure that all tests or checks required for this Protocol have been
executed. Physical and chemical characteristics consisting of following tests.
S.
TESTS OR CHECKS EXECUTED [Y/N] COMMENT
No.
1. Product Feeding Checking
2. Strip Sealing Check
3. Over Printing Quality Check
4. Punching / Cutting Check
5. Physical Appearance Check
6. Foil Shift Test
7. Speed Performance Test-Low Speed
8. Speed Performance Test-High Speed
9. Speed Performance Test-Optimum Speed
10. Sealing Temperature Check - 130˚C
11. Sealing Temperature Check - 150˚C
12. Vibration Check
13. Strip Formation Check
14. Emergency Stop Check
Checked By Verified By
(Production) Quality Assurance)
(Sign & Date) (Sign & Date)
Inference:______________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
Reviewed By:__________________
(Manager QA)
Page 16 of 18
Annexure No. QA-048/A05/00
Equipment ID: PDC/SP/001
Protocol No: PQP/SP/001/00
TITLE: PERFORMANCE
Revision No. QUALIFICATION PROTOCOL FOR Model No.
STRIP PACKING MACHINE
Supersedes No. NIL Effective Date:-
WHO Essential Drugs and Medicines Policy, QA of Pharmaceuticals, Vol-2 Good Manufacturing
Practices and Inspection.
Final SOPs
Any Other Relevant Documents
20.0 CONCLUSION:
21.0 RECOMMENDATION:
22.0 ABBREVIATIONS:
QA : Quality Assurance
Page 17 of 18
Annexure No. QA-048/A05/00
Protocol No: PQP/SP/001/00 TITLE: PERFORMANCE Equipment ID:- PDC/SP/001
QUALIFICATION PROTOCOL Model No.
Revision No.
FOR STRIP PACKING MACHINE
Supersedes No. NIL
QC : Quality Control
DQ : Design Qualification
IQ : Installation Qualification
OQ : Operational Qualification
PQ : Performance Qualification
mg : Milligram
kg : kilogram
Ltd : Limited
Page 18 of 18
Annexure No. QA-048/A05/00