MANUFACTURING DATA RECORDS BOOKS

ALOR GAJAH CITY GATE RECTIFICATION WORKS

PETRONAS GAS BERHAD

CONTRACT NO. 4120113513 PROJECT NO. P2025

TABLE OF CONTENT
S/N Description Remarks

1.0 PROJECT COMPLETION & HAND-OVER CERTIFICATE

2.0 VALVE DATA SHEET

2.1 MANUAL BALL VALVE

2.2 CHECK VALVE

3.0 GA DRAWING

3.1 REMOVAL

3.2 NEW

4.0 P&ID DRAWING

4.1 REMOVAL

4.2 NEW

5.0 VALVE DRAWING (MANUAL BALL VALVE)

6.0 FABRICATION DRAWING

7.0 PIPE WALL THICKNESS & HOOP STRESS CALCULATION

8.0 MATERIAL RECEIVING INSPECTION REPORT (MRIR)

9.0 MATERIAL (MILL) CERTIFICATE

10.0 RADIOGRAPHY TEST REPORT

11.0 HYDROTEST REPORT

12.0 VALVE LEAK TEST REPORT

13.0 PAINTING INSPECTION REPORT

14.0 MAGNETIC PARTICLE INSPECTION (MPI) REPORT

15.0 FIT-UP REPORT

16.0 VISUAL INSPECTION REPORT

17.0 DIMENSIONAL CONTROL REPORT


MANUFACTURING DATA RECORDS BOOKS
ALOR GAJAH CITY GATE RECTIFICATION WORKS

PETRONAS GAS BERHAD

CONTRACT NO. 4120113513 PROJECT NO. P2025

TABLE OF CONTENT
S/N Description Remarks

18.0 VENDOR DOCUMENT MASTER LIST

19.0 PROJECT SCHEDULE

20.0 PROJECT ORGANIZATION CHART

21.0 PROGRESS REPORT

22.0 INSPECTION TEST PLAN

23.0 PROJECT SAFETY/QUALITY PLAN

24.0 CATALOGUE

25.0 WELDING PROCEDURE (WPS/WPQR / WQT)

26.0 RADIOGRAPHY TEST PROCEDURE

27.0 HYDROSTATIC TEST PROCEDURE

28.0 SURFACE PREPARATION & PAINTING PROCEDURE

29.0 VALVE LEAK TEST PROCEDURE

30.0 PRESERVATION,PACKING & SHIPPING PROCEDURE

31.0 ERECTION AND INSTALLATION PROCEDURE

32.0 COMMISIONING PROCEDURE

33.0 MAGNETIC PARTICLE INSPECTION (MPI) PROCEDURE

34.0 DIMENSIONAL CONTROL PROCEDURE