15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 31
A ROTARY JIB CRANE 1 TON 48
1 Drawing
1.1 Acc Drawing 1 PT Indotara 1
1.2 Drawing Production 2 PT Indotara 1 1
2 Material
2.1 Material Preparation 5 PT Indotara 1 1 1 1 1
3 Production

LIBUR NASIONAL

LIBUR NASIONAL
3.1 Cutting Material 6 PT Indotara 1 1 1 1 1 1
3.2 Setting 5 PT Indotara 1 1 1 1 1
3.3 Welding 10 PT Indotara 1 1 1 1 1 1 1 1 1 1
3.4 Accsessories Installation 2 PT Indotara 1 1
3.5 Painting 5 PT Indotara 1 1 1 1 1
3.6 Electrical Instalation 3 PT Indotara 1 1 1
3.7 Finishing 1 PT Indotara 1
4 Delivery
4.1 Loading Material 1 PT BBB 1
4.2 Delivery Material 7 PT BBB 1 1 1 1 1 1 1

Noted:
1. Untuk fabrikasi mengalami kemunduran dikarenakan libur nasional natal dan tahun baru