F0 33:SAFETY ORGANIZATION

JOB SAFE PRACTICE (5.19.2)

DEPARTMENT SAFETY EMPLOYEE JOB TITLE SAFETY ENGINEER


JOB/TASK TITLE FOC Splicing/Cable Termination works inside Hajar/Nujha S/S
STEPS HAZARDS CONTROLS REQUIRED TO OBSERVATION
STEP# LIST ALL STEPS IN PERFORMING THIS TASK IN EACH STEP , WHAT MINIMIZE /ELEMINATE HAZARD
COULD CAUSE INJURY,LOSS
DAMAGE
INTERUPTION,OR
POLUTION?
4. FOC End to End testing 1. Electrical shock 1. Permit to work (PTW),
hazards while should be obtained2.
testing 2. Fire & Tool box talk must be
explosion hazards 3. conducted before
Slight sparking may starting the activities
happen.4. During a 3. Arrange permanently
test, arching installed grounding
through or over facilities and test leads to
faulty insulation. a point where
instruments activity.
4. Use low voltage testing
instruments.
5. Do not disconnect the
test leads for at least 30
to 60 seconds even after
shuttering off the testing
device.
6. The circuit under test
must be switched off, de

Prepared by: Approved by: Element 5.19 Page No: Page 1 of 2 Revision No: 00
Reference No:
F0 33:SAFETY ORGANIZATION
JOB SAFE PRACTICE (5.19.2)

energized and isolated


before any test
connection are made.7.
The workers are involed
in megger activity shall
be trained in arc flash
hazards and control
measures. 8. Sufficent
and suitable fire
extinguiser and fire
warden must be available
at site.9. Personal
protective equipments
should be used such as
rubber insulated gloves
and HRC dress.

COMPILED BY Mr Shariq, Mr.Emad DATE 02- July-2020