PROJECT NAME: DISTRIBUTION 13.

8 KV
.1A.....
SEC 5-STAR SAFETY
OHS-PR-07-OJ-13 • �.,..s:.u �•,-.It
;u�, Sadi
Electricity Company
FIRE RISK ASSESSMENT - JOINT AREA

A competent person must carry


out a fire risk assessment of A competent person will have the By developing your own knowledge,
the premises. knowledge to identify the risks training a suitable, interested member of
and suggest practical precautions staff, or employing a qualified advisor.
you can take.

Use the blank fire assessment form provided on the last page to go through this process and do a fire risk assessment
of your remises. Photocopy the form for additional areas if required.

Identify fire hazards


t Identify:
• Electrical short circuit.
• Over loading of cable extension drum.
• Chemical for jointing cable.
• LPG
Identify people at risk
2 Identify:
• People in and around the premises
• People who are especially at risk as jointer & technician.

Evaluate, remove reduce, and protect from risk


• Evaluate the risk of a fire starting
3 • Evaluate the risk to people from a fire
• Remove or educe fire hazards
• Remove or reduce the risks to people from a fire
• Protect people by providing fore precautions

Record, plan, inform, instruct and train


• Record any major findings and action you have taken
4 • Discuss and work with other responsible people
• Prepare an emergency plan
• Inform and instruct relevant people
• Provide training

5 Review
• Review your fire-risk assessment regularly
• Make changes where necessary

Remember to rc,ir\\ �our fire-risk assrssmrnt regular!�


Page 1 of 4 f Rev.2 [0SApril-2019) Projects Business Unit
�(' . . . . .
SAFETY
EC 5 -S T A R
PROJECT NAME: DISTRIBUTION 13.8 KV

OHS-PR-07-OJ-13 t\ •�.,4Dl�,-..JIU_,.:Ji
Saudi Electricity Com�ny

Fm.E RISK ASSESSMENT- JOINT AREA

I' JOINT AREA


I I Employer!Person in control the workplace:
ocation: 13.8 KV .
Mohammad Al-Ojaimi Contracting
EST. Name: Eng.Mohammad jamal
Date of Risk Assessment:
01.01.2022 . Date of Review 01.12.2022
Engr. Sharif,
Name & Relevant Details of the person who Project Manager. Mohammad jamal
carried out of the Fire Risk Assessment Site Safety officer. Mohammad al Shimri,
Site Safety Manager Amar Alfehail,

Times the Premises are in use:


7.00 AM to 6.00 PM Building foot print(m*m): 6MX3M
The Total Number of persons Employed
06 Number of floor& Rooms: NIA
Within the remises at an onetime:
The Total Number of persons who may
06 Number of Stairs: NIA
Resort to the premises at any onetime:

ire Warning System:


i.e. automatic, m a n u a l , B a t t e r y )
Emergency Lighting:
Battery operated emergency light.
(i.e. Battery Operated, Automatic charge)

Smoke Detector, Fire extinguisher DCP 6KG

Source of Ignition:
1. Electrical Short circuit.
2. Overheating of portable electrical tools.
3. Hot work.

Source of Fuel:
1. Temporary storage of chemical for joint work.
2. LPG gas
3. Combustible material.
4. In-built diesel tank of the generator

ctivity in Progress:
1. Cable Joint.
�!'*····
r,
DISTRIBUTION 13.8 KV
OHS-PR-07-OJ-13 o "'_,.sll ',!�,-JI 4$�1
EC 5-STAR SAFETY Saudi Electricity Company

FIRE RISK ASSESSMENT - JOINT AREA

Structural features that could promote spread fire:

• Poor Housekeeping like paper wastes, plastics wastes, wood waste & food wastes, etc. may lead to spread of fire
which is normally eliminated by daily housekeeping or cleaning the work area.
• Spillage of diesel from the generator may lead to spread of fire. However drip tray is provided to avoid spillage on
the ground.

Emergency Action plan is written & Available at the site for reference

• STAY CALM.
• STOP ALL YOUR ACTTVITES.
• WALK BRISKLY, BUT DO NOT RUN.
• ASSIT OTHERS, WHERE NEEDED. E.G. VISITORS, NEW LABOURS ETC.
• IN CASE OF INJURY, NOTIFY THE FIRST AIDER AT SITE.
• DO NOT GO FOR SEARCHING ANYBODY.
• GO TO ANY OPEN OR SAFE AREA AND STAY THERE.
• CHECK FOR ANY MISSING PERSON OR VISITORS.

Calling CIVIL DEFENCE AT 998.


Calling Fire Co-Ordinator (Mr. Amar Al Fehail) at 0594130085.
Calling Fire Response Team:
MOHAMMAD AL SHAMMRI - 0594326851.

• FIRE FIGHTING TRAINING CONDUCTED FOR ALL THE SITE HSE REPRESENTATIVES.
(CERTIFICATES ATTACHED).
• All technicians are also trained about how to us the Fire Extinguishers in case of emergency.
Page 3 of 41 Rev.2 [0SApril-2019] Projects Business Unit
PROJECT NAME: DISTRIBUTION 13.8 KV
(t� EC S•STAR SAFETY
OHS-PR-07-OJ-13 �
ol,ij4S:U ��,-Jt .S.,.:Jt

Saudi Electricity Company



FIRE RISK ASSESSMENT - JOINT CONTAINER

FIRE MOCK DRILL CONDUCTED ONCE IN 6 MONTHS

ARE THERE ANY MAINTENANCE /REGULAR CHECKS BEEN CARRIED SUCH AS SIGNS, ESCAPE ROUTE,
WARNING SYSTEM, FIGHTING EQUIPMENT ETC.?

• MONTHLY INSPECTION IS DONE FOR ALL THE FIRE EXTINGUISHERS.


• PERIODIC MAlNTENANCE IS DONE FOR ALL THE FIRE EQUIPMENT.
• Regular inspection is done for escape routes, warning system etc.

Responsible
Significant Findings Control Measures Action Date
Person

Fire Coordinator Name: Amar Al Fehail


01/01/2022
2

Safety Officer Name: MOHAMMAD AL SHAMRI Signature:


01/01/2022
Date: 01.01.2022

Site Manager Name: MOHAMMAD JAMAL Signature:


01/01/2022
Date: 01.01.2022
Page4 of41 Rev.2 [08April-2019) Projects Business Unit