Professional Documents
Culture Documents
500 KV AC Underground Transmission Evaluation. Fred Ritter, P.Eng. Technical Lead - Engineering
500 KV AC Underground Transmission Evaluation. Fred Ritter, P.Eng. Technical Lead - Engineering
Evaluation
2
Study Objectives
3
Edmonton Area Transmission System
Development
Line Voltages
240 kV
Fort
McMurray
500 kV
Heartland
East Side
HVDC
West Option Terminal
To
Southern
Alberta
Ellerslie
East Option
Keephills
Genesee
4
Feasibility Study Focus Areas
Technical
Feasibility
Study
Life
Losses Cycle
Costing
500 kV
Rating
Underground Capital Costs
Capability
Cables
Reliability
Availability Risks
Maintainability
Quantify
Practicability
5
Transmission Circuit Layout with
Underground
6
Underground Cable System –
Main Components
7
Single Line Representation – Scenario - A
8
Single Line Representation – Scenario – B
9
Cable Capacity to Match Overhead Line
10
Two Groups of Cable for 3,000 MW Capacity
11
Transition Station Termination
13
Technical Aspects of Study
Europe- 400 kV
North America- 240 kV
and 345 kV
China-
500 kV
15
Cumulative Quantities of Underground
Cables installed in each Country
16
Shinkeiyo-Toyosu 500 kV Line
The first long underground 500 kV XLPE transmission line in the world
17
Shinkeiyo - Toyosu 500 kV Line
Copper
Conductor
XLPE Insulation
Aluminum Sheath
Outer Jacket
Cable Reel for long cable
• Cable Length: 1,800m
• Flange Diameter: 4,250mm
500kV XLPE Cu Cable
• Drum Diameter: 2,750mm
Conductor Size: 2,500mm2 Insulation Thickness: 27mm • Outer Width: 8,300mm
Corrugated Aluminum Sheath PVC Jacket
• Total Weight: 9,500kg
Cable Outer Diameter: 170mm Cable Weight: 35kg/m
18
Shinkeiyo - Toyosu 500 kV Line-Tunnel
19
Shinkeiyo - Toyosu 500 kV Line-Tunnel
20
Cable Reel- Viscas Plant-Tokyo
21
Number of Faults: 220 – 500 kV AC
Land Circuits by Installation Type
22
System Factors - Thermal Transfer
Capabilities (3,000 MVA)
With Reactors
3000 3500
3000
2500
Charging MVA
2500
2000
Effective Power Transfer MVA
Without Reactors
2000
1500
1500
1000
1000
Charging MVA All O/H 75 Charging MVA
500 3x1590 500
0 0
10 20 30 40 50 60 70 80
Underground cable lengths (km)
23
CCI Study Findings
SCFF XLPE
24
CCI’s Key Conclusions
25
Estimated Capital Costs
27
CCI’s Key Conclusions
28
Lifecycle Cost Estimates
30
CCI’s Key Conclusions (continued)
1.00
Losses Difference MW
0.00
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
2600
2800
3000
-1.00
-2.00
55 km OH and 10 km UG
(AIS)
-3.00 45 km OH and 20 km UG
(AIS)
100 % OH
-4.00
MW
31
CCI’s Key Conclusions (continued)
32
Continued Work Activities
33
Questions and References
34