Professional Documents
Culture Documents
Mr. Waldi
Item
Description
No
RCA Team
List the team involved in the RCA investigation members from different department/ disciplines to provide
1
comprehensive perspective of the issue in hand
Welding Operators
Welding operatives qualification certificates available and valid . Confirm knowledge of WPS, pipe rig expie
1 of camera monitoring system etc. Confirm if Project specific awareness sessions were conducted prior to P
needs,requirements and expectations
Deposition of the 1st and subsequent clad layers, operators indents, are they fully traceable with respect t
2 defective barrel. Verify if there is a correlation between specific welders and repairs . Why were so many o
involved in the welding of the barrels, upto 7 on occasion
Is Welders’ KPI performance tracked and monitored. Identify Welders training, cladding experience, any ne
3
operators used, any operators used with historically high repair rates /required re training as a consequenc
Was Barrel surface preparation prior to overlay free from scale, paint, oil, rust, dirt, oxides, and other forei
2 Blasting used, was it conducted thoroughly, i.e in accordance with SA 2.5 profile standard. Confirm the dur
barrel blasting and overlay for each?
3 Confirm if Welding consumable /Filler metal size, type classification / brand conform with the approved cla
Weld Consumable control/ storage, was wire returned to the store at weekends/ the wire covered /protec
4
of the process ?
Welding Machine/Equipment
Verify that all the pipe cladding rig equipment were fully calibrated and in good working condition, not limi
• Welding power sources
• Pipe rotating equipments/rollers/ wire rope system/step back
• Arc Voltage Control Unit
2 • Twin or single welding head . Weld torch mounting
• Twin wire or single wire and hot wire current application
• Camera monitoring and housing
Verify if any breakdowns were reported during the barrel production window . Confirm if the identified rep
unique to one pipe clad rig station.
2 Was each barrel set up in accordance with requirements, chuck system, aligned and trued up
Environment Conditions
1 Environmental conditions during production welding, protected with shielding/drafts /factory doors open/
Welding Process / Procedures and Techniques
1 Welding execution -Any issues raised by operators during 1st layer deposition. Any interim repairs conduct
2 Approved Welding Procedure (WPS) available at site/copy provided/awareness of the WPS used
Classification: Internal #
Preheat Controls before and during all overlay activities. Was propane gas used, how was it applied, period
time ? Preheat temp (32deg) , where are the temperatures checked (OD only), verified by whom? How wa
3
thickness temp acheived and maintained How was preheating managed during breaks, lunch, shift change
working etc. All records to be collated
Overall WPS compliance with critical weld parameters, sequences, step back/overlap, hot wire current/ wi
4 speed , interpass temp,gas shielding , clad deposit thicknesses etc What verifiable records are available an
inputs . Was autogenous welding carried out on any of these areas?
Was a tungsten grinder used to sharpen all tungstens in all cases. How often were the tungsten sharpened
6
welders advised on the importance of the angle / sharpness requirements of the tungsten
Wire changes - Was each of the station weld torchs repositioned in the exact same location which the we
7 terminated prior to any wire change, how is this marked. Wire positioning, relative to tungsten, is a gauge
Is there a correlation between the wire changes and the location of the clad defects .
Detail exactly the differing surface preparation which would have achieved complete bonding between the
8 backing material when comparisons are made ? Why was this retrospective preparation not considered as
practice?
Having passed all the required WPS /PQR qualification tests with comparable surface preparation,, althoug
9
variables are met, is the procedure robust enough to successfully weld substrates of this magnitude
QC/NDT
1 State the QC inputs before ,during and after welding, compliance to WPS and ITP
Project specific ITP awareness -QC knowledge of Project Quality requirements, noting NDE was not perform
2
deposition of 1st clad layer
Verify UT Technicians qualifications. How many were involved. Cross checking expierence and performanc
3
recruits
Verify technicians understanding of Project NDE requirements, technique, material thickness/nominal any
4
sessions conducted
5 Operatives understanding of the materials to be scanned
6 Calibration/validation block used for equipment set up and preparation prior to applying UT scanning
7 Was scanning area adequate to cover scanning technique as per procedure
8 Was the UT technique applied in accordance with the procedure?
9 Was the correct calibration block selected
Is the calibration sensitivity, probe angle, actual probe angle performed correctly prior to carrying out UT s
10
applications
11 Was the sensitivity correctly used by NDT technician during UT scanning processes
12 Was the transfer correction value checked prior to all scanning applications?
13 Was the Rolling direction of material verified before each scanning application
Classification: Internal #
2 Is all the equipment regulary checked/ functionally fit for purpose, any faults reported during the productio
UT Reporting
1 UT reports, was the correct information based on the actual UT scanning application recorded
Clarify what has been used as tge datum, is this the distance from the end of the barrel? Circumferential l
3
circumference, need to know where location is compared to 12 o’clock position
5 Weld defect characterisation and reported location , interlayer versus lack of interface disbondment dispa
Classification: Internal #
RCA Investi
XPANSION (NFXP) OFFSHORE
Description
tion certificates available and valid . Confirm knowledge of WPS, pipe rig expierence c/w use
m etc. Confirm if Project specific awareness sessions were conducted prior to Production on
ectations
bsequent clad layers, operators indents, are they fully traceable with respect to each
re is a correlation between specific welders and repairs . Why were so many operators
he barrels, upto 7 on occasion
tracked and monitored. Identify Welders training, cladding experience, any newly qualified
rs used with historically high repair rates /required re training as a consequence
on prior to overlay free from scale, paint, oil, rust, dirt, oxides, and other foreign matter. If
ted thoroughly, i.e in accordance with SA 2.5 profile standard. Confirm the durations between
or each?
ble /Filler metal size, type classification / brand conform with the approved clad WPS
torage, was wire returned to the store at weekends/ the wire covered /protected at all stages
ing rig equipment were fully calibrated and in good working condition, not limited too;
es raised by operators during 1st layer deposition. Any interim repairs conducted
during all overlay activities. Was propane gas used, how was it applied, periodically or full
) , where are the temperatures checked (OD only), verified by whom? How was through
d maintained How was preheating managed during breaks, lunch, shift change, weekend
be collated
h critical weld parameters, sequences, step back/overlap, hot wire current/ wire angle , travel
hielding , clad deposit thicknesses etc What verifiable records are available and level of QC
lding carried out on any of these areas?
to sharpen all tungstens in all cases. How often were the tungsten sharpened. Are the
ortance of the angle / sharpness requirements of the tungsten
the station weld torchs repositioned in the exact same location which the weld arc was
change, how is this marked. Wire positioning, relative to tungsten, is a gauge used to verify?
en the wire changes and the location of the clad defects .
urface preparation which would have achieved complete bonding between the WO and
parisons are made ? Why was this retrospective preparation not considered as a standard
ed WPS /PQR qualification tests with comparable surface preparation,, although essential
cedure robust enough to successfully weld substrates of this magnitude
ss -QC knowledge of Project Quality requirements, noting NDE was not performed after
cations. How many were involved. Cross checking expierence and performance . Any new
checked/ functionally fit for purpose, any faults reported during the production window
s tge datum, is this the distance from the end of the barrel? Circumferential length is <full
w where location is compared to 12 o’clock position
Finding / Verified
1. There is no welding operator KPI perfomance with regard to weld overlay method due to the difficulty of
measurement. The repair of weld overlay shall be calculated based on area instead of component quantity.
2. Yes, all the welding operator are trained and monitored the welding performance based on the live project. The
priodic monitoring is in accordance with ASME IX. Welding operator validity is updated every 6 months.
1. Surface preparation prior to weld overlay was carried out based on ITP SR# 13 that is in accordance with SA 2.0 as
blast condition only.
Confirmed.
Cladtek has internal procedure to control the wire consumable. This procedure is available at Cladtek premises and can
be reviewed by customer on site.
No welding consumable returned to the store. Welding was carried out continuosly both shift and over the week end
24/7.
1. Enclosed the validation certificate for Welding power sources, Pipe rotating equipments/rollers/ wire rope
system/step back, Arc Voltage Control Unit.
Twin or single welding head (Weld torch mounting), Twin wire or single wire and hot wire current application and
Camera monitoring and housing are in the good condition.
2. Any break down during the weld overlay will be reported by break down record. In regard to repair identification
from break down case, the repair type mostly in the form of tungtens inclusion and/or start stop welding.
Yes.
No.
Yes.
Classification: Internal #
1. Yes
2. Yes. Enclosed sample welding survailance record for this project.
3. Yes, Autogenus welding on the start stop area as per approved WPS.
1. Change of wire was carried out in accordance with the approved the WPS and all the positions are the same since
the welding equipment setup are typical and the same for all welding machine stations. Please refer to approve WPS
page 2 of 2 (QW-410).
2. No.
Submitted and approved WPS / PQR was considered 3.0 mm FBH with 80% FSH while the new project requirement is
3.0 mm FBH with 50% FSH. This gap is due to the unclear requirement during project hand over. Also, Cladtek
understands that the UT LD is not required as per approved CT798-ITP-001 Rev. 2
No input the Quality prior to start, during and after weld overlay until new ITP revision received which is require UT LD.
Unfortunately all the barrels has been complete weld overlay.
Yes, project specific requirement which is desciribe at the approve ITP has been aknowladge to quality member at the
shop floor.
All UT technicians are qualified and certified according to Cladtek writen practice procedure.
Yes
Yes
Yes
Yes
Pulse Echo technique with probe twin crystal (contact testing) and UT digital thickness gauging to measure the total
thickness (CS+CRA)
Yes, Calibration block was made from similar material which is provided by customer (NOV).
Yes, before scanning NDE technician was perform calibration. Only 0 degree (straight beam) applicable for UT
lamination and disbondment and the activity is witnessed by customer.
3.0 mm FBH set to 80% FSH mentioned as 100% reference level
No. Transfer correction is not required, since the thickness/material specification of calibration block is similar with the
actual barrels.
No
Classification: Internal #
Confirmed.
Yes, following the calibration shall be performed prior daily inspection activity and witnessed by customer.
Yes
Yes, Cladtek datum always started from R side with 0 degree 12 o'clock position located at exact position of the
hardstamp with clockwise calculation for circumferential.
The actual thickness cannot provide at the LOB location. However, the actual thickness was taken before weld overlay
with interval 500mm along the pipe
Yes, understod. Defect position between carbon steel interface to CRA layer is call as lack of bonding, defect position
CRA layer to CRA layer is call as lack of fusion or interrun fusion. UT thickenss before weld overlay as reference to
decide the LOB defect considering depth of defect not exceeding thickness before weld overlay.
Classification: Internal #
Evidence Remarks
Attachment 1
N/A
Classification: Internal #
Attachment 5
N/A
N/A
N/A
Attachment 8
Attachment 8
Attachment 8
Attachment 11
Attachment 9 & 11
N/A
N/A
Classification: Internal #
Attachment 9
Attachment 9
Attachment 12
N/A
Attachment 11
Attachment 13
Attachment 11
Attachment 11