You are on page 1of 41

This drawing is the PROPERTY of

ANDRITZ HYDRO GmbH


Eibesbrunnergasse 20
1120 Vienna, Austria

AGRIMECO - JSC

BAN MONG HYDROPOWER PROJECT


Refer to protection notice ISO 16016

00 1st Issue 2019 05 20 HZX HJR LYN ZCN


Index Modification Date Prepared by Checked T Checked P Approved

Unit Start/Stop Sequence


Control System

2018

Client AGRIMECO JSC Drawn 2019.05.20 HZX File BMG-204-01-004.DOCX


Plant BAN MONG HPP Checked T 2019.05.20 HJR SaveDate 2019 05 20
Project Nº Checked P 2019.05.20 LYN Similar
Contract Nº 180726-BM/AG-AH Approved 2019.05.20 ZCN Replace
Internal N° =
+
Drawing N° Index Sheet 1
BMG-204-01-004 00 of 41 A4
Control System Unit Start / Stop Sequence

Table of Contents
1 Legend ................................................................................................................................ 4
2 Sequencing Step Overview ............................................................................................... 5
3 ST ........................................................................................................................................ 6
4 TO - EO ............................................................................................................................... 7
This drawing is the PROPERTY of
ANDRITZ HYDRO GmbH

5 LO ....................................................................................................................................... 8
Eibesbrunnergasse 20
1120 Vienna, Austria

6 Start Condition Alarm ........................................................................................................ 9


7 Ready Start to TO ............................................................................................................ 10
8 Ready Start to EO ............................................................................................................ 11
9 Ready Start to LO ............................................................................................................ 12
10 ST Order ........................................................................................................................... 13
11 TO Order ........................................................................................................................... 14
12 EO Order........................................................................................................................... 15
13 LO Order ........................................................................................................................... 16
14 Start Step 1....................................................................................................................... 17
15 Start Step 2....................................................................................................................... 18
16 Start Step 3....................................................................................................................... 19
17 Start Step 4....................................................................................................................... 20
18 Start Step 5(TO) ............................................................................................................... 21
19 Start Step 6(EO) ............................................................................................................... 22
20 Start Step 7....................................................................................................................... 23
21 Start Step 8(LO) ............................................................................................................... 24
22 Stop Step 1 ....................................................................................................................... 25
23 Stop Step 2(EO) ............................................................................................................... 26
24 Stop Step 3(TO)................................................................................................................ 27
25 Stop Step 4 ....................................................................................................................... 28
26 Stop Step 5 ....................................................................................................................... 29
27 Stop Step 6 ....................................................................................................................... 30
28 Stop Step 7 ....................................................................................................................... 31
29 Stop Step 8 (ST) ............................................................................................................... 32
30 Step Time Exceed ............................................................................................................ 33
31 QSD................................................................................................................................... 34
32 Unloaded QSD.................................................................................................................. 35
Refer to protection notice ISO 16016

33 Trip On .............................................................................................................................. 36
34 HPP ................................................................................................................................... 37
35 Cooling Water Pump........................................................................................................ 38
36 GOP Pump........................................................................................................................ 39
37 BOP Pump ........................................................................................................................ 40
38 SSWP Pump ..................................................................................................................... 41

Client AGRIMECO JSC Internal N° =


Plant BAN MONG HPP +
File BMG-204-01-004.DOCX Drawing N° Index Sheet 2
SaveDate 2019 05 20 BMG-204-01-004 00 of 41 A4
Control System Unit Start / Stop Sequence

Abbreviation
BOP – Bearing Oil Pump

CWP – Cooling Water Pump

EO – Energized State
This drawing is the PROPERTY of
ANDRITZ HYDRO GmbH

GOP – Governor Oil Pump


Eibesbrunnergasse 20
1120 Vienna, Austria

HPP – High Pressure Pump

LO – Synchronized

QSD – Quick Shutdown

SSWP – Shaft Sealing Water Pump

ST – Standstill State

TO – Speed No Load

VAR – Variable (Internal Used)


Refer to protection notice ISO 16016

Client AGRIMECO JSC Internal N° =


Plant BAN MONG HPP +
File BMG-204-01-004.DOCX Drawing N° Index Sheet 3
SaveDate 2019 05 20 BMG-204-01-004 00 of 41 A4
t 0 30s Timer ON Delay:After setting the input to TRUE,the
& AND Gate output follows time delayed.

PRE RES Time Step Transition : If previous sequencing step PRE is


>=1 OR Gate processed with success and if release RLE is set TRUE ,
Start / Stop Step RLE then ON is set TRUE to activate next sequencing step.If
result RES is not successful till Delay Time elapsed then
Inverter ON OT OT is set TRUE.

Pump Switch : If CMD is set TRUE(from sequencing


P1.Lock
Combine inputs in parallel control),one of P1.Start, P2.Start will be set TRUE to
P2.Lock P1.Start
P1.Running start P1 or P2 according to their status P1.Lock,
P2.Running P2.Start P2.Lock(available or faulty). The running pump will be
Set and Latch:If the Logic input is TRUE,the logic CMD switched to another available pump after set period of
R output is TURE and is latched.If the logic input running time.
becomes FALSE,the logic output will be held true
S until reset is TRUE.

LESS THAN
≤ MAX The output follows the maximum of intputs.

LARGER THAN

t 2s
Single Shot:When the logic input to a single
shot transitipn from FALSE to TRUE,the
output is set TRUE for a specific interval

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Legend
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 4


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
Unit Sequencing Step Overview

Standstill(ST)
Step 8
Step 1 Stop High Pressure Pump.
Start High Pressure Pump. Stop Bearing Oil Pump.
Start Bearing Oil Pump. Stop Shaft Sealing Water Pump.
Start Shaft Sealing Water Pump.
Start Cooling Water Pump.
Stop Cooling Water Pump.
Start Generator Cooling Fans. Stop Generator Cooling Fans.
Start Fans for Oil Vapour Exhaust. Stop Fans for Oil Vapour Exhaust.
Start Mist Separator for Oil Head. Stop Mist Separator for Oil Head.
Reset Accumulator Stop Valve. Activate Accumulator Stop Valve.

Step 2
Open Bearing Oil Valve.
Step 7
Close Bearing Oil Valve.
Close Standstill Sealing Control
Valve. Open Standstill Sealing Control Valve.

Step 3 Step 6
Release Mechanical Brake. Activate Emergency Shutdown Valve.

Step 4 Step 5
Reset Emergency Shutdown Valve.
Apply Mechanic Brake.

Step 4 Step 4
Start Gorvernor. Stop Gorvernor.

Speed No Load(TO)

Step 3
Step 5 Stop Excitation.
Start Excitation.

Energized Operation(EO)

Step 6 Step 2
Start Synchronization. Open GCB.

Step 7
Preset Minimum P&Q. Step 1
Set Governor Power Mode.
Decrease P&Q To No Load.
Set Excitation Reactive Power Mode.

Line Operation(LO)

CLIENT AGRIMECO JSC DRAWN HZX Document No.


PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence Sequencing Step OverView BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 5


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

DI Field Circuit Breaker Open AA29:34

DI General Circuit Breaker Open AA29:00

VAR Wicket Gate Full Closed

VAR Speed <1 % of rated speed

DI Bearing Oil Valve Closed AA21:38

DI Brake Calliper 1 ON AA25:01

DI Brake Calliper 2 ON AA25:02

DI Generator Cooling Water Pump 1 ON AA37:00

DI Generator Cooling Water Pump 2 ON AA37:01

DI Bearing Pressure Oil Pump 1 (AC) ON AA37:02

DI Bearing Pressure Oil Pump 2 (DC) ON AA37:03

DI Bearing Oil Pump 1 ON AA37:04

DI Bearing Oil Pump 2 ON AA37:05

DI Generator Cooling Fans 1~2 ON AA37:06

DI Generator Cooling Fans 3~4 ON AA37:07

DI Shaft Sealing Water Pump 1 ON AA37:14

DI Shaft Sealing Water Pump 2 ON AA37:15

DI Fan for Oil Vapour Exhaust ON AA37:08

DI Mist Separator for Oil Head ON AA37:16

&

VAR Standstill(ST) State

DI Field Circuit Breaker Open AA29:34

DI General Circuit Breaker Open AA29:00

VAR Wicket Gate Full Closed

DI Bearing Oil Valve Closed AA21:38

DI Brake Calliper 1 ON AA25:01

DI Brake Calliper 2 ON AA25:02

DI Generator Cooling Water Pump 1 ON AA37:00

DI Generator Cooling Water Pump 2 ON AA37:01

DI Bearing Pressure Oil Pump 1 (AC) ON AA37:02

DI Bearing Pressure Oil Pump 2 (DC) ON AA37:03

DI Bearing Oil Pump 1 ON AA37:04

DI Bearing Oil Pump 2 ON AA37:05

DI Generator Cooling Fans 1~2 ON AA37:06

DI Generator Cooling Fans 3~4 ON AA37:07

DI Shaft Sealing Water Pump 1 ON AA37:14

DI Shaft Sealing Water Pump 2 ON AA37:15

DI Fan for Oil Vapour Exhaust ON AA37:08

DI Mist Separator for Oil Head ON AA37:16

&

VAR Standstill(ST) Unit Protection

CLIENT AGRIMECO JSC DRAWN HZX Document No.


ST
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 6


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

DI Field Circuit Breaker Open AA29:34

DI General Circuit Breaker Open AA29:00

VAR Speed >95% of rated speed

DI Brake Calliper 1 ON AA25:01

DI Brake Calliper 2 ON AA25:02

&

VAR Speed No Load Steady State(TO)

DI Field Circuit Breaker Closed AA29:35

DI General Circuit Breaker Open AA29:00

VAR Speed >95% Rated

MODBUS Generator Voltage >95% Rated

&
VAR Energized Operation State(EO)

CLIENT AGRIMECO JSC DRAWN HZX Document No.


TO - EO
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 7


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

DI Field Circuit Breaker Closed AA29:35

DI General Circuit Breaker Closed AA29:01

VAR Speed >95% of rated speed

& MODBUS Generator Voltage >75% Rated

MODBUS Generator Active Power > 2MW

VAR Line Operation State(LO)

VAR Trip ON P36

CMD Sequence to Auto Mode

CMD Sequence to Single Step Mode


≥1
VAR Sequence in Single Step Mode

VAR Sequence in Auto Step Mode

VAR Sequence in Auto Step Mode P8


R S
VAR Sequence in Single Step Mode P8

CMD Single Step Release Command

&

≥1
VAR Step Release

CLIENT AGRIMECO JSC DRAWN HZX Document No.


LO
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 8


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

DI Control Mode Revision AA21:7


DI 220VDC Power 1 Supply Failure AA21:8
DI 220VDC Power 2 Supply Failure AA21:9
DI 24VDC Power Supply Failure AA21:10
DI Generator Hot Air Temperature High Alarm AA21:14
DI Generator Cold Air Temperature High Alarm AA21:16
DI Main Thrust Bearing Pad Temperature High Alarm AA21:18
DI Counter Thrust Bearing Pad Temperature High Alarm AA21:20
DI Guide Bearing Shell Temperature High Alarm AA21:22

DI Oil Sump Tank-Low Alarm AA21:41


DI Oil Sump Tank-High Alarm AA21:43
DI Main Thrust Bearing High Pressure Oil Filter High AA21:46
DI Generator Guide Bearing High Pressure Oil Filter 1 High AA21:47
DI Generator Guide Bearing High Pressure Oil Filter 2 High AA21:48
DI Differential Pressure Switch Oil Filter Alarm AA21:56
DI Brake Lining Abrasion 1 AA25:4
DI Brake Lining Abrasion 2 AA25:5
DI turbine bearing metal temperature 3 high AA25:12

DI governor sump tank oil level too low AA25:29


DI Return oil filter 1 clogged AA25:30
DI Return oil filter 2 clogged AA25:31
DI Oil circulting filter clogged AA25:32
DI Pilot oil filter clogged AA25:33
DI Leakage oil tank oil level too low AA25:37
DI Leakage oil tank water detected AA25:39

DI Vibration Generator Bearing Alarm AA29:58


DI Vibration Turbine Bearing Alarm AA29:60
DI Generator Cooling Water Pump 1 Fault AA37:27
DI Generator Cooling Water Pump 2 Fault AA37:28
DI High Pressure Oil Pump 1 (AC) Fault AA37:29
DI High Pressure Oil Pump 2 (DC) Fault AA37:30
DI Bearing Oil Pump 1 Fault AA37:31
DI Bearing Oil Pump 2 Fault AA37:32
DI Generator Cooling Fans1~2 Fault AA37:33
DI Generator Cooling Fans3~4 Fault AA37:34
DI Fan for Oil Vapour Exhaust Fault AA37:35
DI Governor oil actuator tank Oil pump 1 Fault AA37:36
DI Governor oil actuator tank Oil pump 2 Fault AA37:37
DI Governor oil Leakage oil pump 1 Fault AA37:38
DI Governor oil Leakage oil pump 2 Fault AA37:39
DI Governor oil Cooling water pump Fault AA37:40
DI shaft sealing water pump 1 Fault AA37:41
DI shaft sealing water pump 2 Fault AA37:42
DI Mist Separator for Oil Head Fault AA37:43
DI Oil heating motor 1~4 in bearing oil sump tank Fault AA37:44
DI Heater in bearing oil high tank Fault AA37:45
DI Auxiliary Cubicle AC Voltage Failure AA37:46
DI Auxiliary Cubicle DC Voltage Failure AA37:47

≥1
VAR Sart Condition Alarm

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Start Condition Alarm
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 9


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Trip ON P36

VAR Start Condition Alarm P9

RTD Oil Head Temperature < 52 ℃ A117:IN V0


RTD Bearing Temperature Oil In Oil Sump Tank >= 20 ℃ A114:IN V0
RTD Oil Temperature In Bearing Upper Oil Tank >= 20 ℃ A114:IN V1
AI Hydraulic link pressure measuring >=28bar AA65:08

DI Governor Remote Auto AA25:46


DI Governor Local Auto AA25:47

≥1

DI Auxiliary Cubicle Control Switches Auto Position AA37:49


DI Power Converter 1 OK AA37:52
DI Power Converter 2 OK AA37:53
DI Power Converter 3 OK AA37:54
DI Servomotor Dowel Lock OFF AA25:19
DI Guide Vane(Buckling Link) 1-8 Fault AA25:16
DI Guide Vane(Hydraulic Link) 1-8 OK AA25:17

VAR Standstill(ST) P6

&
VAR Ready Start to TO

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Ready Start to TO
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 10


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Trip ON P36

DI Control Mode Revision AA21:7


DI 220VDC Power 1 Supply Failure AA21:8
DI 220VDC Power 2 Supply Failure AA21:9
DI 24VDC Power Supply Failure AA21:10
DI 6.3kV MCB's trip AA29:15
DI Excitation Ready for operation AA29:27
DI excitation alarm AA29:28
DI AC supply fail AA29:30
DI DC supply fail AA29:31
DI regulator fault AA29:32
DI excitation auto mode AA29:33
DI excitation remote AA29:36
DI Multifunction Meter Supply Failure AA37:48

&

VAR Ready Start to EO

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Ready Start to EO
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 11


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Trip ON P36

DI Synchronization Automatic AA21:2


DI SYN3000 Fault AA21:4
DI Control Mode Revision AA21:7
DI 220VDC Power 1 Supply Failure AA21:8
DI 220VDC Power 2 Supply Failure AA21:9
DI 24VDC Power Supply Failure AA21:10
DI 6.3kV MCB's trip AA29:15
DI 6.3kV generator CB Q01 isolated position AA29:4
DI 6.3kV generator CB Q01 service position AA29:5
DI 6.3kV generator CB Q01 gas pressure low AA29:6
DI 6.3kV generator CB Q01 gas pressure insufficient AA29:7
DI 6.3kV generator CB Q01 springs discharged AA29:8
DI 6.3kV generator CB Q01 control switch remote AA29:9

DI Multifunction Meter Supply Failure AA37:48

DI 6.3kV main transformer feeder earthing switch opened AA29:10

&

VAR Ready Start to TO

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Ready Start to LO
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 12


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Stop Step 4 Time Exceed P28

VAR Standstill (ST) State P6

VAR Joint Control Active P13

CMD Joint Control Stop Order

&

CMD Standstill (ST) Order Pushed

VAR ST -> TO Time Exceed P33

VAR Unit Trip Exists

≥1 ≥1

R S

VAR Standstill(ST) Internal Order

CMD Individual Mode Order

CMD Joint Control Mode Order

R S

VAR Joint Control Active

CLIENT AGRIMECO JSC DRAWN HZX Document No.


ST Order
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 13


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR ST -> TO Time Exceed P33

VAR LO -> EO Time Exceed P33

VAR EO -> TO Time Exceed P33

VAR Turbine Operation (TO) State P7

VAR Standstill(ST) Internal Order P13

VAR Ready Start to TO P10

VAR Standstill (ST) State P6

&

VAR Energized Operation(EO) State P7

VAR Line Operation(LO) State P8

≥1 ≥1
CMD Turbine Operation(TO) Order Pushed

&

R S

VAR Turbine Operation(TO) Internal Order

CLIENT AGRIMECO JSC DRAWN HZX Document No.


TO Order
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 14


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR ST -> TO Time Exceed P33

VAR TO -> EO Time Exceed P33

VAR LO -> EO Time Exceed P33

VAR Energized Operation (EO) State P7

VAR Standstill(ST) Internal Order P6

VAR Turbine Operation (TO) State P7

VAR Ready Start to EO P11

VAR Standstill (ST) State P6

VAR Ready Start to TO P10

& &

VAR Line Operation(LO) State P8

≥1 ≥1
CMD Energized Operation(EO) Order Pushed

&

R S

VAR Energized Operation(EO) Internal Order

CLIENT AGRIMECO JSC DRAWN HZX Document No.


EO Order
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 15


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR ST -> TO Time Exceed P33

VAR TO -> EO Time Exceed P33

VAR EO -> LO Time Exceed P33

VAR Line Operation(LO) P8

VAR Standstill (ST) Internal Order P6

VAR Energized Operation (EO) State P7

VAR Ready Start to LO P12

& VAR Turbine Operation (TO) State P7

VAR Ready Start to EO P11

VAR Standstill (ST) State P6


&
VAR Ready Start to TO P10

&

VAR Joint Control Active P13

CMD Joint Control Start Order

≥1 ≥1 &

CMD Line Operation(LO) Order Pushed

≥1

&

R S

VAR Line Operation(LO) Internal Order

CLIENT AGRIMECO JSC DRAWN HZX Document No.


LO Order
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 16


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Standstill (ST) State P6

VAR Line Operation(LO) Internal Order P12

VAR Energized Operation(EO) Internal Order P11


≥1
VAR Turbine Operation(TO) Internal Order P10

VAR Start Step 1 Result P18


&

Constant Start Step 1 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT
VAR Start Step 1 Time Exceed P33

VAR Start Step 1 Running P18

VAR Start High Pressure Pump (HPP) P37

VAR Start Bearing Oil Pump(BOP) P40

VAR Start Shaft Sealing Water Pump(SSWP)

VAR Start Cooling Water Pump (CWP) P38

DO Generator Cooling Fans ON AA45:13,15

DO Accumulator Stop valve Reset AA49:27

DO Fan for Oil Vapour Exhaust ON AA45:19

DO Mist Separator for Oil Head ON AA45:36

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Start Step 1
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 17


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Start Step 1 Running P17

DI Differential Pressure Switch for Cooling Fan1 OK AA21:24

DI Differential Pressure Switch for Cooling Fan2 OK AA21:25

DI Differential Pressure Switch for Cooling Fan3 OK AA21:26

DI Differential Pressure Switch for Cooling Fan4 OK AA21:27

VAR Cooling Water Pump (CWP) ON and Flow OK P38

VAR Bearing Oil Pump (BOP) ON P40

VAR High Pressure Pump (HPP) ON and Pressure OK P37

DI Generator Cooling Fans ON AA37:06,07

VAR Shaft Sealing Water Pump(SSWP) ON

DI Fans for Oil Vapour Exhaust ON AA37:08

DI Mist Separator for Oil Head ON AA37:16

DI Stop valve activated AA25:34

&

VAR Start Step 1 Result P17

VAR Start Step 2 Result P19


&
Constant Start Step 2 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT
VAR Start Step 2 Time Exceed P33

VAR Start Step 2 Running P19

VAR Standstill Sealing Control Valve Release

DO Main Bearing Oil Valve Open AA45:21

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Start Step 2
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 18


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Start Step 2 Running P18

DI Bearing Oil Valve Open AA21:39

DI Oil Flow Main Thrust Bearing Low AA21:34

DI Oil Flow Generator Guide Bearing Low AA21:35

DI Oil Flow Counter Thrust Bearing Low AA21:36

& DI Oil Flow Turbine Guide Bearing Low AA21:37

DI Standstill Sealing Pressure Low AA25:15

VAR Start Step 2 Result P18


&
VAR Start Step 3 Result P20

Constant Start Step 3 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Start Step 3 Time Exceed P33

VAR Start Step 3 Running P20

VAR Mechanical Brake(MB) Release

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Start Step 3
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

BMG-HAH APPR. ZCN Control System Index Size 19


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Start Step 3 Running P19

DI Brake Calliper 1 ON AA25:1

DI Brake Calliper 2 ON AA25:2

VAR Start Step 3 Result P19

&
VAR Start Step 4 Result P21

Constant Start Step 4 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Start Step 4 Time Exceed P33

VAR Start Step 4 Running P21

DO Reset Emergency Shut Down Valve 1 AA49:25

DO Reset Emergency Shut Down Valve 2 AA49:26

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Start Step 4
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 20


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Start Step 4 Running P20

DI ESD Valve Activated AA25:35

VAR Start Step 4 Result P20

&
VAR Start Step 5 Result P22

Constant Start Step 5 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Start Step 5 Time Exceed P33

VAR Start Step 5 Running P22

VAR Turbine Governor Start

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Start Step 5(TO)
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 21


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Start Step 5 Running P21

VAR Line Operation(LO) Internal Order P16

VAR Energized Operation(EO) Internal Order P15

≥1

VAR Speed >95% Rated

VAR Start Step 5 Result P21

&
VAR Start Step 6 Result P23

Constant Start Step 6 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Start Step 6 Time Exceed P33

VAR Start Step 6 Running P23

DO Excitation Start AA53:16

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Start Step 6(EO)
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 22


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Start Step 6 Running P22

VAR Line Operation(LO) Internal Order P16

MODBUS Generator Voltage > 95%

DI Field Circuit Breaker Closed AA29:35

VAR Start Step 6 Result P22

VAR Start Step 7 Result P24


&
Constant Start Step 7 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Start Step 7 Time Exceed P33

VAR Start Step 7 Running P24

DO Synchronizatin Start(V/V Mode) AA53:05

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Start Step 7
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 23


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Start Step 7 Running P23

DI General Circuit Breaker Closed AA29:01

VAR Start Step 7 Result P23

&
MODBUS Active Load Minimum( P > 2.0MW)

&

Constant Start Step 8 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Start Step 8 Time Exceed P33

VAR Start Step 8 Running

VAR Governor to Active Power Control Mode

IEC104 Excitation to Reactive Power Control Mode

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Start Step 8(LO)
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 24


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Standstill(ST) Internal Order P13

VAR Energized Operation(EO) Internal Order P15

VAR Turbine Operation(TO) Internal Order P14

≥1

VAR Line Operation(LO) State P8

&

≥1
VAR Stop Step 1 Result P26

Constant Stop Step 1 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Stop Step 1 Time Exceed P33

VAR Stop Step 1 Running P26

VAR Governor No Load

AO Exitation No Load AA65:18

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Stop Step 1
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 25


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Stop Step 1 Running P25

MODBUS Active Load Minimum( P < 2MW)

MODBUS Reactive Load Minimum( Q < 2MVar)

&

VAR Stop Step 1 Result P25

&
VAR Stop Step 2 Result P27

Constant Stop Step 2 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Stop Step 2 Time Exceed P33

VAR Stop Step 2 Running P27

DO GCB Open AA53:04

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Stop Step 2(EO)
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 26


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Stop Step 2 Running P26

VAR Turbine Operation(TO) Internal Order P14

DI General Circuit Breaker Open AA29:00

VAR Stop Step 2 Result P26

&
VAR Stop Step 3 Result P28

Constant Stop Step 3 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Stop Step 3 Time Exceed P33

VAR Stop Step 3 Running P28

DO Excitation Stop AA53:15

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Stop Step 3(TO)
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 27


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Stop Step 3 Running P27

VAR Standstill(ST) Internal Order P13

DI Field Circuit Breaker Open AA29:34

MODBUS Generator Voltage < 30%

&

VAR Stop Step 3 Result P27

&
VAR Stop Step 4 Result P29

Constant Stop Step 4 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Stop Step 4 Time Exceed P33

VAR Stop Step 4 Running P29

≥1

VAR Turbine Governor Stop

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Stop Step 4
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 28


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Stop Step 4 Running P28

VAR Speed < 20% Rated

VAR Wicket Gate Full Closed

&
VAR Stop Step 4 Result P28

&
VAR Stop Step 5 Result P30

Constant Stop Step 5 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT
VAR Stop Step 5 Time Exceed P33

VAR Stop Step 5 Running P30

DO Mechanical Brake Apply AA45:23

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Stop Step 5
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 29


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Stop Step 5 Running P29

VAR Speed <1 % of rated speed

DI Brake Calliper 1 ON AA25:01

DI Brake Calliper 2 ON AA25:02

VAR Stop Step 5 Result P29

&
VAR Stop Step 6 Result P31

Constant Stop Step 6 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Stop Step 6 Time Exceed P33

VAR Stop Step 6 Running P31

DO ESD Valve1 Act (Shutdown While Power ON) AA49:25

DO ESD Valve2 Act (Shutdown While Power OFF) AA49:26

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Stop Step 6
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 30


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Stop Step 6 Running P30

DI ESD Valve Activated AA25:35

&
VAR Stop Step 6 Result P30

&
VAR Stop Step 7 Result P32

Constant Stop Step 7 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Stop Step 7 Time Exceed P33

VAR Stop Step 7 Running P32

DO Turbine Standstill Sealing Control Valve Open AA45:34

DO Close Main Bearing Oil Valve AA45:20

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Stop Step 7
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 31


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Stop Step 7 Running P31

DI Bearing Oil Valve Closed AA21:38

DI Standstill Sealing Pressure Low AA25:15

&

VAR Stop Step 7 Result P31

DI Stop valve activated AA25:34

DI Generator Cooling Water Pump 1 ON AA37:0

DI Generator Cooling Water Pump 2 ON AA37:1

DI High Pressure Oil Pump 1 (AC) ON AA37:2

DI High Pressure Oil Pump 2 (DC) ON AA37:3

DI Bearing Oil Pump 1 ON AA37:4

DI Bearing Oil Pump 2 ON AA37:5

DI Generator Cooling Fans1~2 ON AA37:6

DI Generator Cooling Fans3~4 ON AA37:7

DI Fan for Oil Vapour Exhaust ON AA37:8

DI shaft sealing water pump 1 ON AA37:14

DI shaft sealing water pump 2 ON AA37:15

DI Mist Separator for Oil Head ON AA37:16

& & Constant Stop Step 8 Operation Time

PRE RES Time

Start / Stop Step RLE VAR Step Release P8

ON OT

VAR Stop Step 8 Time Exceed P33

VAR Stop Step 8 Running

VAR Stop High Pressure Pump (HPP) P37

VAR Stop Bearing Oil Pump(BOP) P40

VAR Stop Cooling Water Pump (CWP) P38

VAR Stop Shaft Sealing Water Pump (SSWP) P38

DO Accumulator Stop valve Activate AA49:28

DO Stop Fans for Oil Vapour Exhaust AA45:18

DO Stop Mist Separator for Oil Head AA45:35

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Stop Step 8 (ST)
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 32


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41
ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Start Step 1 Time Exceed P17

VAR Start Step 2 Time Exceed P18

VAR Start Step 3 Time Exceed P19

VAR Start Step 4 Time Exceed P20

VAR Start Step 5 Time Exceed P21

≥1

VAR ST -> TO Time Exceed

VAR Start Step 6 Time Exceed P22

≥1

VAR TO -> EO Time Exceed

VAR Start Step 7 Time Exceed P23

VAR Start Step 8 Time Exceed P24

≥1

VAR EO -> LO Time Exceed

VAR Stop Step 1 Time Exceed P25

VAR Stop Step 2 Time Exceed P26

≥1

VAR LO -> EO Time Exceed

VAR Stop Step 3 Time Exceed P27

≥1

VAR EO -> TO Time Exceed

VAR Stop Step 4 Time Exceed P28

VAR Stop Step 5 Time Exceed P29

VAR Stop Step 6 Time Exceed P30

VAR Stop Step 7 Time Exceed P31

VAR Stop Step 8 Time Exceed P32

≥1

VAR TO -> ST Time Exceed

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Step Time Exceed
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 33


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41
ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref

DI General Circuit Breaker opened AA29:00

DI Field Circuit Breaker off AA29:34

DI Hydraulic Overspeed Valve Act AA25:36

DI Excitation Trip (Summary Trip Signal) AA29:29

DI Protection Trip (Summary Trip Signal) AA33:06


& ≥1
DI Actuator Tank Pressure Too Low AA25:27

VAR Governor Fault

DI Actuator Tank Level Too Low AA25:26

VAR Speed > 115% with 20 Senconds Delay

VAR Speed > 154% of Rated Speed

DI Emergency Push Button On AA21:00

CMD Emergency Shut Down Command from SCADA

RTD Stator Winding-Phase U (Center Stator Core)Temperature > 125 ℃ A103:IN V03

RTD Stator Winding-Phase V (Center Stator Core)Temperature > 125 ℃ A104:IN V00

RTD Stator Winding-Phase W (Center Stator Core)Temperature > 125 ℃ A104:IN V01

RTD Stator Winding-Phase U (Center Stator Core)Temperature > 125 ℃ A104:IN V02

RTD Stator Winding-Phase V (Center Stator Core)Temperature > 125 ℃ A104:IN V03

RTD Stator Winding-Phase W (Center Stator Core)Temperature > 125 ℃ A105:IN V00

RTD Temperature Stator core (Center stator core) > 110 ℃ A106:IN V03

RTD Temperature Stator core (Center stator core) > 110 ℃ A107:IN V00

RTD Temperature Stator core (Center stator core) > 110 ℃ A107:IN V01

RTD Excitation Transformet Phase U Temperature > 150 ℃ A117:IN V03

RTD Excitation Transformet Phase V Temperature > 150 ℃ A118:IN V00

RTD Excitation Transformet Phase W Temperature > 150 ℃ A118:IN V01

DI Stop valve activated AA25:34

DI ESD Valve Activated AA25:35

≥1

VAR Speed > 95% Rated

&

2s
t 0

≥1

DO Electical Quick Shut Down Trip AA53:22

DO Emergency Shut Down Trip AA53:24

VAR QSD is ON

DO Activate Emergency Shut Down Valve 1 AA49:25

DO Activate Emergency Shut Down Valve 2 AA49:26

VAR Governor No Load

VAR Digital Governor Quick Shut Down

DO Field Circuit Breaker Open AA53:17,18

DO GCB Open AA53:04

CLIENT AGRIMECO JSC DRAWN HZX Document No.


QSD
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 34


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A2 41
ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref

RTD Oil Head Temperature > 57 ℃ A117:IN V00

RTD Temperature main thrust bearing pad > 75 ℃ A109:IN V03

RTD Temperature main thrust bearing pad > 75 ℃ A110:IN V00

RTD Temperature main thrust bearing pad > 75 ℃ A110:IN V01

RTD Temperature guide bearing shell > 75 ℃ A113:IN V00

RTD Temperature counter thrust bearing pad > 75 ℃ A113:IN V02

DI Main Thrust Bearing Pad Temperature High Trip AA21:19

DI Counter Thrust Bearing Pad Temperature High Trip AA21:21

DI Guide Bearing Shell Temperature High Trip AA21:23

DI Water Level Indicator in Bulb Activate Trip AA21:33

DI Oil Sump Tank-Low Trip AA21:42

DI Oil Sump Tank-High Trip AA21:44

DI Oil Level Upper Oil Tank-Low Trip AA21:53

DI Oil Level Upper Oil Tank-High Trip AA21:55

DI turbine bearing metal temperature 4 too high AA25:13

DI Vibration Generator Bearing Trip AA29:59

DI Vibration Turbine Bearing Trip AA29:61

DI Oil Flow Turbine Guide Bearing Low AA21:37

DI Oil Flow Main Thrust Bearing Low AA21:34

DI Oil Flow Generator Guide Bearing Low AA21:35

DI Oil Flow Counter Thrust Bearing Low AA21:36

≥1
VAR Speed < 1 % of Rated Speed

&

20s
t 0

≥1
DO Mechanical QSD Trip AA53:20

VAR Unloaded QSD is ON

DO Activate Emergency Shut Down Valve 1 AA49:25

DO Activate Emergency Shut Down Valve 2 AA49:26

VAR Governor No Load

VAR Digital Governor Quick Shut Down

VAR Wicket Gate Full Closed

&

≥1

DO Field Circuit Breaker Open AA53:16

DO GCB Open AA53:04

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Unloaded QSD
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
Project Nº BMG-HAH APPR. ZCN Control System Index Size 35
FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A2 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

DI Backup Circuit Protection Active AA21:1

VAR QSD is ON P34

VAR Unloaded QSD is ON P35

≥1

VAR Trip On

VAR Mechanical Brake(MB) Release P19

DI Speed Detection Failure

AI Speed < 20% of Rated Speed

≥1

DO Release Mechanical Brake(MB)

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Trip On
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 36


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A4 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

DI Bearing pressure oil pump 1 (AC) on AA37:2

DI Bearing pressure oil pump 2(DC) on AA37:3

≥1
Generator Guide Bearing High Pressure
DI Oil Pressure Low AA21:49

Turbine Guide Bearing High Pressure


DI Oil Pressure Low AA21:50

& &
VAR High Pressure Pump (HPP) is off

VAR High Pressure Pump (HPP) ON and Pressure OK

VAR Speed >95% Rated

VAR Speed <1 % Rated

&
VAR High Pressure Pump (HPP) Start P17

VAR Standstill(ST) Unit Protection P6

VAR Speed <1 % of rated speed

VAR Speed Detection Failure

VAR High Pressure Pump (HPP) is off

&

VAR High Pressure Pump (HPP) Stop P32

VAR Speed Detection Failure

≥1 ≥1

R
DO High Pressure Oil Pump 1 (AC) ON AA45:5
S

t 0 30s

VAR High Pressure Pump (HPP) ON and Pressure OK P37

& VAR High Pressure Pump (HPP) Stop P32

R
DO High Pressure Oil Pump 2 (DC) ON AA45:7
S

CLIENT AGRIMECO JSC DRAWN HZX Document No.


HPP
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 37


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

DI Generator Cooling Water Pump 1 ON AA37:0

DI Generator Cooling Water Pump 2 ON AA37:1

DI Pressure in Cooling System Low Alarm AA21:59


& ≥1
DI Pressure after cooling water pumps Low Alarm AA21:57

DI Cooling Water Flow Generator Low AA21:61

VAR Cooling Water Pump (CWP) ON and Flow OK

VAR Cooling water pump (CWP) is off

VAR Cooling water pump (CWP) Stop P32

VAR Cooling water pump (CWP) Start P17

VAR Standstill(ST) Unit Protection P6

VAR Speed <1 % of rated speed

VAR Speed Detection Failure

VAR Cooling water pump (CWP) is off P38

≥1 &

R S

DI Generator Cooling Water Pump 2 ON AA37:1

DI Generator Cooling Water Pump 1 ON AA37:0

DI Generator Cooling Water Pump 2 Fault AA37:28

DI Generator Cooling Water Pump 1 Fault AA37:27

P1.Lock
P2.Lock P1.Start DO Generator cooling water pump 1 on AA45:1
P1.Running
P2.Running P2.Start DO Generator cooling water pump 1 on AA45:3
CMD

VAR Standstill Sealing Control Valve Release P18

VAR Standstill(ST) Unit Protection P6

VAR Speed <1 % of rated speed

VAR Speed Detection Failure

DI Standstill Sealing Pressure Low AA25:15

≥1 &

DO Turbine Standstill Sealing Control Valve Close AA45:33

CLIENT AGRIMECO JSC DRAWN HZX Document No.


Cooling Water Pump
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 38


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

AI Actuator Tank Pressure AA65:11

179.5 bar ≥

R
169.0 bar ≤ VAR Start Governor Oil Pump Main
S

AI Actuator Tank Pressure AA65:11

179.5 bar ≥

R
165.0 bar ≤ VAR Start Governor Oil Pump Standby
S

AI Piston Accumulator 1 Level AA65:12

VAR Stop Governor Oil Pumps


87.50% ≥

VAR Start Governor Oil Pump Main P39

DI Governor Oil Pump 2 ON AA37:10

t 0 6s
DO Oil Pump 2 Load/Unload Valve AA49:30

DI Governor Oil Pump 1 ON AA37:9

t 0 6s
DO Oil Pump 1 Load/Unload Valve AA49:29

DI Governor Oil Pump 2 Fault AA37:37

DI Governor Oil Pump 1 Fault AA37:36

P1.Lock
P2.Lock P1.Start VAR Start Governor Oil Pump 1
P1.Running
P2.Running P2.Start VAR Start Governor Oil Pump 2
CMD

VAR Stop Governor Oil Pumps P39

VAR Start Governor Oil Pump 2 P39

VAR Start Governor Oil Pump Standby P39

VAR Start Governor Oil Pump 1 P39

≥1 ≥1

& &
DO Governor Oil Pump 1 ON AA49:32

DO Governor Oil Pump 2 ON AA49:34

AI Pressure measuring for hydraulic link AA65:08

32.5 bar ≥

R
31.0 ≤ DO Solenoid Valve For Hydraulic Linke Open AA49:23
S

DO Solenoid Valve For Hydraulic Linke Close AA49:24

AI Oil temprature for governor sump oil tank AA69:00

45 ℃ ≥

DO Governor Oil Circulating Pump ON AA53:01

DO Governor Oil Circulating Pump OFF AA53:00

CLIENT AGRIMECO JSC DRAWN HZX Document No.


GOP Pump
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 39


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A2 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

VAR Stop Bearing Oil Pump(BOP) P32

VAR Start Bearing Oil Pump(BOP) P17

VAR Standstill(ST) Unit Protection P6

VAR Speed <1 % of rated speed

VAR Speed Detection Failure

DI Oil Flow Turbine Guide Bearing Low AA21:37

DI Oil Flow Main Thrust Bearing Low AA21:34


R S ≥1
DI Oil Flow Generator Guide Bearing Low AA21:35

VAR Main Bearing Oil Valve Open P18

&
≥1

DO Open Main Bearing Oil Valve AA45:21

DI Oil Level Upper Oil Tank-Low Alarm AA21:52

VAR Stop Bearing Oil Pump(BOP) P32

DI Oil Level Upper Oil Tank-Normal AA21:54

& ≥1
R
VAR Start Bearing Oil Pump Standby
S

DI Bearing Oil Pump 2 ON AA37:5

DI Bearing Oil Pump 1 ON AA37:4

DI Bearing Oil Pump 2 Fault AA37:32

DI Bearing Oil Pump 1 Fault AA37:31

P1.Lock
P2.Lock P1.Start VAR Start Bearing Oil Pump 1
P1.Running
P2.Running P2.Start VAR Start Bearing Oil Pump 2
CMD

VAR Start Bearing Oil Pump 2 P40

VAR Start Bearing Oil Pump Standby P40

VAR Start Bearing Oil Pump 1 P40

≥1 ≥1
DO Bearing Oil Pump 1 ON AA45:9

DO Bearing Oil Pump 2 ON AA45:11

DI Bearing Oil Pump 2 ON AA37:5

DI Bearing Oil Pump 1 ON AA37:4

≥1
DI Oil Level Upper Oil Tank-Normal AA21:54

DI Oil Level Upper Oil Tank-Low Alarm AA21:52

&
VAR Bearing Oil Pump (BOP) is ON

VAR Standstill(ST) State

600s
t 0

DO Generator Cooling Fans OFF AA45:12,14

CLIENT AGRIMECO JSC DRAWN HZX Document No.


BOP Pump
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 40


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41
FUNCTION ID NUMBER SIGNAL TEXT DENOMINATION LCU INTERFACE Ref.

DI shaft sealing water pump 1 ON AA37:14

DI shaft sealing water pump 2 ON AA37:15

& ≥1

DI turbine sealing water flow measuring OK AA25:14

VAR Shaft Sealing Water Pump (SSWP) ON and Flow OK

VAR Shaft Sealing Water Pump (SSWP) is OFF

VAR Stop Shaft Sealing Water Pump (SSWP) P32

VAR Start Shaft Sealing Water Pump (SSWP) P17

VAR Standstill(ST) Unit Protection P6

VAR Speed <1 % of rated speed

VAR Speed Detection Failure

VAR Shaft Sealing Water Pump (SSWP) is OFF P41

≥1 &

R S

DI shaft sealing water pump 2 ON AA37:15

DI shaft sealing water pump 1 ON AA37:14

DI shaft sealing water pump 2 Fault AA37:42

DI shaft sealing water pump 1 Fault AA37:41

P1.Lock
P2.Lock P1.Start DO shaft sealing water pump 1 Start AA49:3
P1.Running
P2.Running P2.Start DO shaft sealing water pump 2 Start AA49:5
CMD

CLIENT AGRIMECO JSC DRAWN HZX Document No.


SSWP Pump
PLANT BAN MONG HPP CHECK HJR Unit Start/Stop Sequence BMG-204-01-004
HCN

Project Nº BMG-HAH APPR. ZCN Control System Index Size 41


FILE NAME Start/Stop Sequence FILE DATE 2019-05-20 00 A3 41