CH 1340.00-1440.00 M
PROPOSED CROSS SECTION CH 1440.00-1900.00 M
A A
Existing
Drain Shoulder CARRIAGEWAY
CL CARRIAGEWAY Shoulder
Existing
Drain
Existing
Drain Shoulder CARRIAGEWAY
CL CARRIAGEWAY Shoulder
Proposed
Drain
1200 Variable 5000 5000 Variable 1200
1200 Variable 5000 5000 Variable 1200
3750 Soil CBR>7% 3750 Soil CBR>7%
GSB 150 MM THK. GSB 150 MM THK.
WMM 250 MM THK. WMM 250 MM THK.
STONE DUST 50 MM STONE DUST 50 MM DBM 50 MM THK.
DBM 50 MM THK. B
PAVER BLOCK 100 MM BC 30 MM THK. PAVER BLOCK 100 MM BC 30 MM THK.
3.0% 3.0% 3.0%
3.5% 3.0% 3.5% 3.5% 3.5%
TYPICAL CROSS SECTION OF ROAD (TCS-9) TYPICAL CROSS SECTION OF ROAD (TCS-10)
F
PROJECT NAME ROAD DETAIL CONSULTANT APPROVAL AUTHORITY CONSTRUCTION AGENCY NORTH SHEET NO: MPUDC-TTAM-RC-04
E
DEVELOPMENT OF ROAD FROM THANA TO 0+000M TO 3+715 M AATVIK CONSULTANCY MADHYA PRADESH DIAMOND INFRA