You are on page 1of 8

Construction Health and Safety

QUARRYING

Section 15

15 - 1
Acknowledgement
Special Acknowledgement is made to the Lafarge
Cement Co Ltd for their invaluable assistance in the
preparation of this section

CONTENTS

Introduction 15-3
Legal Requirements 15-3
Opening a quarry 15-3
Formal appointments 15-3
Person entitled to work the quarry 15-3
Quarry operator 15-3
Health and Safety documentation 15-4
Management structure 15-4
Risk assessment 15-4
Design and Safety measures 15-4
Instructions, rules and schemes 15-5
Vehicle rules 15-5
Permits to work 15-5
Explosives 15-5
Excavations and tips 15-6
Geotechnical appraisal and assessment 15-6
Revision and availability of
Health and Safety Document 15-7
Records and reports 15-7
References 15-7

NOTE
Whilst every care has been taken to ensure accuracy within
this work, no liability whatsoever is accepted by Construction
Health and Safety, its sponsoring organisations or their
advisers in respect of the information given.

No material from this. book may be reproduced in any


shape or form without written permission from the publishers.

15 - 2 December 2002
QUARRIES ASSOCIATED WITH CONSTRUCTION OPERATIONS
Introduction The Regulations apply at all quarries:-
The Quarry Regulations 1999, are intended to protect the – being prepared for extraction of minerals
health and safety of all persons working in a quarry and – where mineral extraction or preparation takes place as
all other persons who may be affected by quarrying part of a work activity
operations. – where work to prevent water or other material flowing
In many respects, these regulations provide the into an adjacent quarry takes place (even after
framework within which health and safety is managed in quarrying has finished)
quarries. The detail, or specific legal requirements, are – being prepared for abandonment, for example
contained within other health and safety legislation landscaping.
common to all workplaces, for example, the Quarry The Regulations will not apply where a quarry is no
Regulations require the provision of operating rules in longer used for the extraction of minerals and HSE have
relation to vehicles, however much of the plant construction been notified. HSE do not need to be formally notified of
detail concerning suitability, reversing aids, visibility, temporary closures lasting up to 12 months. However,
maintenance etc. is contained in the Provision and Use of notification is required when quarries are abandoned or
Work Equipment Regulations 1998 suspended for periods of more than one year. As
In addition, the requirements of CDM Regulations apply indicated above The Health And Safety Executive are the
to building, civil engineering or engineering construction Enforcing Authority for quarries.
work at quarries prior to operations to extract mineral
resources. They also apply to those operations at quarries Opening a quarry
which are not directly related to the extraction of minerals Where a contractor carries out excavations outside the line
including erection of or demolition of buildings. of the easement with the aim of obtaining minerals he has
The purpose of this guidance is not to spell out familiar opened a quarry. This will require both planning consent
issues, but to explain some of the requirements specific to from the Local Authority and the completion of a formal,
quarries. These may be relevant if a quarry or "borrow written notification to the local office of the Health & Safety
pit" is opened up as part of a wider construction/civil Executive within 14 days of the start of the work.
engineering project.
A quarry is defined in the Quarry Regulations 1999, Formal Appointments
though the definition can become clouded when the A quarry cannot be worked unless a number of formal
mineral extraction is associated with a construction appointments have been made, these include the
project! following:
Any excavation used for the purpose of obtaining
minerals is a quarry however, where the The Person Entitled to Work the Quarry
excavation/extraction is within a construction site and the and the Quarry Operator
minerals are for use solely in connection with the project The Person Entitled to Work the Quarry may or may not be
the Quarry Regulations do not apply. The actual wording the operator, he is the person who owns the mineral rights.
from the Regulations is as follows: The Quarry Regulations However, whatever the arrangement, the Person
do not cover excavations made Entitled to Work the Quarry shall not permit another person
(a) solely for the purpose of carrying out any building, to be the Operator unless that person is suitable and has
civil engineering or engineering construction work; provided sufficient resources, including plant, machinery
and and expertise, to operate the quarry safely.
(b) where the minerals or products of minerals extracted Where the Person Entitled to Work the Quarry permits
are used on the site at which the extraction has another person to be the Operator, he shall make a written
taken place. record of that permission, signed by both parties and a
However, where materials are extracted for sale or use copy shall be given to the Operator. The signed record
at a location away from the extraction site (for example shall be retained by both parties for the duration of the
aggregates extracted solely for use in a road project, but permission.
away from the line of the road), the extraction site will The Person Entitled to Work the Quarry must pass to the
become a quarry as defined and the Quarry Regulations operator, any information he has available, relevant to
1999 will apply. Practical experience of this situation working the quarry safely for example, geological and
teaches that because the quarrying operations at this type geotechnical reports, details of past workings etc.
of site are limited in scope the implementation of the
Regulations, whilst tedious because of the paperwork Quarry operator
involved, is not difficult. The operator of a quarry is defined as the person, an
Meaning of Quarry and application of the Regulations individual or corporate body, in overall control of the
A quarry includes:- working of the quarry and most of the duties under these
– all surface mineral workings regulations fall on him. One of his duties is to notify the
– tips (even if they are outside the site boundary) Health & Safety Executive when the quarry is to be opened
– storage of minerals, including stockpiles or closed; he must also notify when the Operator changes.
– areas used for the preparation of extracted minerals for There is no prescribed form for this process but the
sale correspondence must contain key details such as the name
– buildings and structures at the quarry used for the and address of the Operator, the dates when quarrying
working of the quarry will begin or end and the exact location which may require
– common areas, e.g. quarry roadways and railways, a map reference. The Regulations expect him to ensure so
but not public roads or railways under the control of a far as is reasonably practicable that the quarry and its
rail company plant are designed, constructed, equipped, commissioned,
– sites where prospecting with a view to extraction of operated and maintained so that it can be run in safety.
minerals is carried out (where this is not covered by the The Operator also has the duty to co-ordinate the
Borehole Sites and Operations Regulations 1995). implementation of all health and safety measures and, on
completion of quarrying, ensure the quarry is left in a safe

December 2003 15 - 3
condition. – Each person identified in the management structure
The two key elements central to the successful shall carry out the duties assigned to him in the Health
implementation of these regulations are:- and Safety Document.
– the development of a Health and Safety Document,
setting out the framework for managing health and Management structure
safety at the quarry and detailing many of the specific To ensure the health and safety of persons at the quarry or
requirements laid out in the regulations, and; those nearby who may be affected, the operator must
– The establishment of a management structure to enable establish a management structure, that enables the quarry
the quarry to be operated in accordance with the health to be operated in accordance with the health and safety
and safety document. document, detailing the extent of the authority and duties
of all persons in the structure.
Health and safety document A competent individual must be appointed, in writing,
Regulation 7 of the Quarries Regulations 1999 requires by the operator, to take charge of the operation of the
the quarry Operator to ensure that no work is carried out quarry at all times when people are working in the quarry.
at a quarry unless a health & safety document has been A deputy should be nominated as a substitute in the event
prepared. To those familiar with the requirements of of the appointed person being absent.
HASAWA and CDM, the Health and Safety Document is to
quarrying what the Health and Safety Policy and
Risk assessment
Construction Phase Plan is to construction.
The philosophy of risk assessment, i.e. anticipating
The Health and Safety Document is required to:-
problems before they arise and taking relevant
– Demonstrate that the risks to which persons at work in
precautions, is a crucial part of the management and
the quarry are exposed have been assessed in
planning process. The overwhelming majority of accidents
accordance with the Management of Health & Safety at
can be prevented by proper planning, anticipating
Work Regulations 1999 and other legislation requiring
hazards and risks and taking appropriate precautions,
assessments, e.g. COSHH, manual handling, etc.
before the task is started.
– Demonstrate that adequate measures, including those
Some activities undertaken at quarries are common to
concerning the design, use and maintenance of the
many locations and generic risk assessments may well be
quarry and of its plant, will be taken to safeguard the
available for those activities. However, non-routine tasks,
health & safety of persons at work in the quarry and
associated with maintenance and breakdown situations,
those in the area immediately surrounding the quarry
may not be covered by an existing risk assessment. Work
who are directly affected by the quarry's activities.
should not proceed until an assessment has been made for
– Include a statement of how the measures referred to
that task and control measures have been implemented.
above will be co-ordinated.
The significant findings from any assessment should be
The document should record the following information:-
recorded and retained as part of the Health and Safety
– Any rules in place at the quarry to ensure the health &
Document for future reference.
safety of persons who may be affected by its operation
Findings from other assessments carried out,
and the safe use of equipment. They shall be easily
particularly those involving the storage, handling and use
understandable and made available to anybody at the
of hazardous substances required under COSHH
quarry who may require them.
[including details of dust and silica surveys], Manual
– The arrangements for the review of safety measures in
Handling and Noise should also be retained.
place in the quarry.
It is also important to note that many
– Details of the inspection and maintenance schemes
maintenance/breakdown situations are entirely
operating in the quarry.
predictable, such as changing vee belts and building new
– Vehicle rules.
items of plant and therefore there is no reason why they
– Permit to Work Systems.
could not be risk assessed in a generic or draft format prior
– Shot firing rules (where explosives are used).
to them being customised to make them "bespoke" as the
– Tipping rules.
situation arises.
– The conclusions of any appraisal or assessment of the
stability/safety of an excavation or tip.
– The arrangements for health surveillance. Design and safety measures
Where appropriate, the document should also include:- Risk assessments carried out during the designing of the
– A plan detailing the equipment and measures required quarry must identify the safety measures required. Areas
to protect persons at work at the quarry from the risk of specific to Quarries, that are referred to in the Regulations
explosions. include:-
– Where toxic gases are, or may be, present in the – The provision of a suitable, properly maintained barrier
atmosphere in the quarry, in such concentrations that around the quarry boundary to discourage trespass.
the atmosphere may be harmful to the health of persons The regulations are non specific as to the type of
at work, a plan detailing the protective equipment and barrier, which could include hedges, stock fence or a
measures required to protect persons at work at the ditch. However, the barrier must deter trespass and the
quarry from the harmful atmosphere. type of construction will depend upon local conditions,
– A diagram of the quarry indicating those areas to e.g. proximity to centres of population.
which the Quarry Regulations 1999 do not apply. – Benches and haul roads which must be designed,
constructed and maintained so that vehicles and plant
The Operator must ensure that:- can be used and moved in safety. Road edge
– The Health and Safety Document, including any protection should be 1.5m or the radius of the largest
information recorded therein, such as inspections etc., wheel in height, which ever is the greatest. The
is both kept up-to-date and made available to all purpose of the edge protection is to stop the largest,
persons at work at the quarry and, where appropriate, fully laden vehicle crossing it at maximum foreseeable
their employer. speed. Large boulders are often used for the purpose.
– Measures identified in the Health and Safety Document – Danger areas which are required to be clearly marked
are implemented and that any plans included in it are with barriers installed to prevent inadvertent entry
followed. where there is a risk of falling or being struck by falling

15 - 4 June 2007
objects. Areas for consideration will include edges of – Instructions to drivers concerning the reporting of
excavations liable to collapse, the bottom of faces defects.
where material may fall, or places where people could – Brake testing.
fall more than 2m along with water lagoons in sand – Daily maintenance checks.
and gravel quarries. – Relevant cross-references to the scheme for inspection
and maintenance of plant.
Instructions, rules and schemes
The Operator should develop and implement site rules Permits to work
(e.g. operating procedures) to secure the health & safety of Where any hazardous operations or other straightforward
those working in the quarry and the safe use of equipment. operations which may interact with other activities to cause
Such rules must include issues such as, but not limited to:- a serious hazard exist, for example where control
– Carrying out a risk assessment before starting a task measures have been removed [e.g. during maintenance of
and implementing its precautions plant say, someone entering a crusher], the operator shall
– Only undertaking tasks if trained and competent to do ensure that such tasks are not carried out unless a permit to
so work has been raised for that task. Such tasks will have
– Complying with all other rules in force (Vehicle, been identified through risk assessment and may include,
shotfiring, excavation/tips) but not be restricted to, entry into confined spaces, work
– PPE requirements on machinery where isolation/lock off procedures are
– Emergency procedures insufficient and work on complicated/high voltage
– First aid requirements equipment and other dangerous situations as defined in
– Reporting defects Regulation 22 of the Quarries Regulations 1999.
Copies of all instructions, rules and schemes shall be Permits to work need to specify the conditions to be
kept at the quarry and explained to and provided for fulfilled, the precautions to be taken before, during and
persons upon whom they impose duties in an effort to after the task and must be issued, signed and dated by a
ensure that they are understood by those to whom they suitable person in the management structure and accepted,
apply. The rules effectively form the operating procedures signed and dated by another suitable person. Therefore, a
and should be specific to the quarry. The rules will also suitable permit to work system should identify:-
form an important part of the Induction process. – What work requires a permit
The Operator is required to prepare and keep up-to- – Those authorised to issue and accept permits and the
date a written scheme for the systematic inspection, limit of their authority
maintenance and, where appropriate, testing by – How the safety of a proposed system of work is to be
appointed, competent persons of all parts of the Quarry checked
including buildings and plant. Written reports shall be – How information about hazards is to be communicated
made that record any significant defects and the actions – The maximum time a permit may be valid
required to put them right. The scheme should outline the – Hand-over, hand-back, suspension and cancellation
frequency of inspections, what should be covered and arrangements for both completed and incomplete work
what remedial action should be taken (e.g. prioritisation of – Arrangements for monitoring and review of the system
remedial work)
The scheme of inspection should cover areas of the Explosives
quarry and plant liable to create significant risk. These Where quarrying operations involve the use of explosives,
areas should include but are not restricted to:- the Operator shall ensure that all explosives are stored,
– Vehicles, including brake testing, reversing aids etc. transported and used safely and securely and that
– Machinery guarding operations are carried out by suitably qualified and
– Other safety devices such as interlocks, pull cords and competent individuals. One of his key duties is to appoint
emergency equipment one or more competent individuals as Explosives
– Electrical equipment Supervisor[s], to organise and supervise all work at the
– Pressure systems, including those on vehicles quarry involving the use of explosives. The other duties
– Pedestrian routes, roadways and any edge protection imposed on the Operator in relation to explosives are to
– Excavations and tips ensure shot firing rules and written blast specifications are
– Buildings and structures prepared.
– Boundary fencing Shot Firing Rules need to cover arrangements for:-
– The appointment and authorisation of shot firers,
Vehicle rules trainee shot firers, store keepers and others working
The operator shall develop a series of written rules to with explosives.
ensure the safety of all persons at the Quarry from the risk – Checking mechanisms that enable the Explosives
arising from the use of vehicles [the "Vehicle Rules"]. Supervisor to ensure that the equipment provided is
Vehicle Rules prepared for the Quarry need to cover the suitable and safe and the site conditions are in line with
following points:- the blast specification.
– Details for assessing the competence of drivers and – Times when shot firing is permitted.
authorising them to operate vehicles. – The determination of the danger zone and its
– Security arrangements including the control of keys. evacuation and the provision of effective shelters when
– Restrictions on where vehicles may be used. shots are tested or fired.
– Restrictions [if any] on reversing. – Warning systems including, as appropriate:-
– Speed limits. The use of flags or notices.
– Restriction on traffic routes. A system of audible signals.
– Pedestrian safety. The positioning of sentries.
– Fitting and use of safety devices, including seat belts, Direct personal notification of local residents.
visibility aids, e.g. CCTV, reversing bleepers, etc. – Inspection of the blast site after firing to check the state
– Use of vehicles in adverse weather conditions. of the face and whether a misfire has occurred.
– Precautions where quarry vehicles or trailers with – Ensuring that normal working is resumed only when the
tipping bodies or tipping gear are loaded, unloaded or shot firer is fully satisfied that it is safe and the all clear
sheeted. has been sounded.

December 2002 15 - 5
– Safeguarding charged but unfired shot holes at the end are or have been extracted and includes the ground,
of the working day. faces or sides of the quarry and any other incline"
– Dealing with misfires and the discovery of unfired – Tip:- "an accumulation or deposit of any substance at a
explosives from previous operations. quarry (whether in a solid or liquid state or in solution
– Monitoring arrangements to ensure the rules are or suspension) and includes, but is not limited to,
complied with. overburden dumps, backfill, spoil heaps, stock piles
and lagoons, and where any wall or other structure
The Blasting Specification must be specific for each blast retains or confines a tip then it shall be deemed to form
and take into account the conditions on site. The part of the tip.
Specification should be designed to:- Excavation and Tips Rules need to be prepared by the
operator to ensure the safe construction and operation of
– Ensure that the risk of fly rock being projected outside excavations and tips. The rules must detail how operations
the danger zone is as low as reasonably practicable. are to be carried out, the levels of supervision required, the
– Minimise the risk of misfires. precautions to be taken to ensure safety and the inspection
– Enable the location of any misfired shots to be and maintenance regeme.
determined accurately. Excavation and tips rules should specifically address, as
– Ensure that faces are left in a safe condition after relevant:-
blasting. – Maximum depth/height
The Specification should take account of:- – Preparations necessary [e.g. foundations]
– Experience gained from previous blasts at the quarry. – Provision of drainage
– Any unusual circumstances present or likely to arise. – Height/slope of faces and thickness of layers
– The design of the excavation. – Plant and machinery used
Matters to be considered when preparing for a blast and – Construction standards of roads, wheel stops and
the specific details that need to be recorded, in addition to bunds
those above, in the blasting specification are:- – The responsibilities of Supervisors
– The part of the quarry to be blasted, shown on a plan. – What action to take if a defect is discovered
– The intended hole positions, showing the length, – System of work for removing material
diameter, the angle of inclination and direction at which – Sequence of excavation/tipping
the drill is to be set for each hole, marked on a drilling – Arrangements for maintaining faces
plan. – Degree of compaction - solid tips
– The surface position and number or other identifier for – In the case of lagoons: Provision of emergency
each shot hole. overflows, minimum freeboard heights, operation and
– The angle of inclination, direction, length and diameter maintenance of pumps, recovery of material and
and the extent of any sub grade drilling for each covering lagoons, protection and fencing of the edges,
completed shot hole. the provision and maintenance of rescue equipment
– Where the minerals form a face, the profiles or other and emergency procedures.
data required to determine the burden around each
shot hole. Geotechnical appraisal and assessment
– Any geological anomalies which could affect the blast, The Operator must ensure that a suitable and sufficient
in particular those identified during drilling and appraisal of proposed (or existing) quarrying operations is
inspection, e.g. cavities, clay bands, joint planes, undertaken by a geotechnical specialist. Where the
bedding planes or discontinuities. appraisal identifies a significant hazard, then a
– By using plans and sections determine from the geotechnical assessment needs to be undertaken. In this
available information the burden for each shot hole and context, a significant hazard is defined in the Regulations
consequently the amount, type and placement of as a situation where a failure would, directly or indirectly,
explosives to be used, so that the blast can be carried be liable to endanger premises, roadways or other places
out safely. where people are likely to be found off site, or likely to kill
– In addition to the amount, type and position of or seriously injure anyone. Some situations where a
explosives, the description and position of any significant hazard is likely to exist are detailed below:
detonator and the type and position of any stemming It is unlikely in the context of a quarry associated with a
actually used for each shot hole. construction site that either an excavation or a tip is likely
– The system for initiation, including full details of any to present a significant hazard and thus require a
delay sequence and timing. geotechnical assessment. However, for completeness, if
– The danger zone, shot firing position and sentry the following criteria are satisfied, then the hazards should
positions should be determined. be treated as significant:-
The visibility and other precautions required to minimise Tips in a solid state:-
the risk of:- – The area of land covered exceeds 10000m2
– Material being projected by the blast. – The tip height exceeds 15m
– Misfires. – The average gradient of land covered by the tip
– Injury during inspection of the site before and after the exceeds 1 in 12
blast. – Irrespective of size, other factors (e.g. geology, location
– The date and timing of the blast and prevailing weather or proximity to an excavation) that could lead to a
conditions. significant hazard being present.
Excavations in:-
Excavations and tips Moderately weak or stronger rocks (usually rock
The Operator must ensure that excavations and tips are requiring blasting)
designed, constructed, operated and maintained so as to – If the height of an individual face exceeds 15m
ensure that instability or movement, which is likely to give – The height of a benched face is between 15 and 30m,
rise to a risk to the health and safety of any person is and the angle is over 45∫
avoided. Weak or very weak rocks (usually extracted using
Both excavation and tip are defined in the regulations:- excavators or draglines)
– Excavation:- "any place at the quarry where minerals – If the height of any part of the excavation is over 7.5m

15 - 6 December 2002
– The face angle is over 27∫ to the horizontal quarry, to ensure that control measures are in place and
And if the bottom of the excavation is more than 30m the are effective.
below any surrounding land or irrespective of the above,
other factors (e.g. geology, location or proximity to an Records and Reports
excavation) that could lead to a significant hazard being The Operator must ensure that records and reports
present. required to be maintained under the regulations, are kept
Where no significant hazard is identified, the appraisal at the quarry (or elsewhere if easily retrievable) for the
should be reviewed at appropriate intervals, and in specified time period. They include:-
particular following changes to working methods, at least Three years:
geological knowledge, evidence of failure or following – Inspection and maintenance records
incorrect assumptions during the appraisal. – Blasting specifications
The conclusions of the appraisal should be recorded in – Details of misfires
the health and safety document. – Conclusions of geotechnical appraisals and
assessments
Revision & Availability of Health and – Substances tipped
Safety Document Twelve months after the appointment has ceased copies of
The health and safety document needs to be available to written appointments of:
all persons at work in the quarry. It should be used as a – Quarry Manager (appointed person)
"live" document and regularly reviewed, especially where – Explosive Supervisor
there have been changes to the process or new equipment – Shotfirer
is introduced. – Trainee Shotfirer
The document should also be referred to by those – Storekeeper
undertaking health & safety audits/inspections of the

REFERENCES
Legislation All of the above reference material is available from:
Quarries Regulations 1999 Construction Industry Publications Ltd.,
Manufacture and Storage of Explosives Regulations 2005 17 Gatelodge Close, Round Spinney,
Northampton NN3 8RJ
Approved Code of Practice Tel: 0870 078 4400
Health and safety at quarries - (L118) Fax: 0870 078 4401
e-mail sales@cip-books.com

December 2005 15 - 7
This page is intentionally blank

15 - 8 December 2002

You might also like