Professional Documents
Culture Documents
Ref. No.
Date of issue
Prepared by
Revised by
____________________________________________________________________________________
Page 1 of 6 Method Statement for Plastering
Method Statement______________________________________________
Contents:
1. Introduction.
3. Construction equipment.
4. Personnel.
6. Construction procedures.
7. Quality assurance.
1. Introduction:
____________________________________________________________________________________
Page 2 of 6 Method Statement for Plastering
Method Statement______________________________________________
2.1. N/A.
3. Construction equipment:
4. Personnel
5.1. Assure that all working persons are well known of the safety
instructions and seriously following it.
5.2. Check for clearance of the working place from any other activities.
5.3. Assure safe scaffoldings for high applicable areas.
6. Construction procedures:
____________________________________________________________________________________
Page 3 of 6 Method Statement for Plastering
Method Statement______________________________________________
____________________________________________________________________________________
Page 4 of 6 Method Statement for Plastering
Method Statement______________________________________________
6.2.6. Start connecting the guide points by the horizontal guide lines of
pure cement and sand contents without gypsum additives taking in
consider to apply a guide line 50cm below the slab soffit and
another one 50 cm above slab top then divide the inner distance
into equal dimensions not more than 2 .00 meters.
6.2.7. Check the straightness in each corner and add grout to hold the
external corner beads in correct and internal position to be fixed
using corrosion resistant fasteners.
6.2.8. Before plastering starts, dampen, by spraying water concrete dash
coat surfaces that are to receive plaster with clean water.
6.3. Application:
6.3.1. All plaster shall be prepared in a mechanical mixer mix 1:5 (1 part
cement and 5 parts sand) using sufficient water to produce a
workable consistency. After all the ingredients have been added
including the remaining mixing water, the plaster should be mixed
for a further few minutes until uniform fibred dispersion. Plaster
not used within 1.5h from start of mixing shall be discarded.
6.3.2. The second coat shall be applied with sufficient material and
pressure to ensure tight contact with dash coat.
6.3.3. The surface of the second coat shall be brought to a true, even
plane with a rod or straightedge, filling surface defects in place
with plaster.
6.3.4. Applied plaster shall be floated as smooth as possible and then
steel-troweled. Steel trowel shall be delayed as long as possible
and used only to eliminate the uneven points and to force
aggregate particles into the plaster surface.
6.3.5. Each plaster coat shall be applied to an entire wall or ceiling panel
without interruption to avoid cold joints and abrupt changes in the
uniform appearance of succeeding coats. Wet plaster shall abut set
plaster at naturally occurring interruptions in the plane of the
plaster, such as corner angles, openings and control joints where
this is possible.
6.3.6. Make internal angles and corners square.
____________________________________________________________________________________
Page 5 of 6 Method Statement for Plastering
Method Statement______________________________________________
6.3.7. Finished grooves shall be neat, of uniform width and depth, sharp
straight edges and exact vertical and horizontal lines. Elevation
grooves shall be cut before plaster sets by using molded guide or
wooden strip and fixing it in temporary grout and screed.
Regarding recessed, follow the procedures same as grooves.
6.3.8. Form cornices by plastering additional coats against pre-formed
wood templates fixed onto plastered elevation. Make form wood
templates to shapes, dimensions and projection indicated on
drawings. Apply additional under coats in thickness not more that
10mm until obtaining required projection.
6.3.9. Plaster should not deviate more than plus or minus 3mm in 3m
from a true plane in finished plaster surfaces, as measured by a 3-
m straight edge placed in any location on surface.
7. Quality Assurance:
7.1. Each activity should be performed by the assigned employee within the
organization chart.
7.2. All Materials and equipments used in the activities should be approved,
inspected and tested prior to usage.
7.3. Work procedure should follow this method statement and preparatory
technical meeting.
7.4. All activities steps should follow the ITP plan.
Verification Point
S/N Process Step Contractor
Consultant
Construction Q/C
1 Surveying. Hold Hold Surveillance
2 Surface preparation and wire mesh fixing. Hold Hold Surveillance
3 Dash coat. Hold Surveillance Surveillance
4 Guide points and lines and the corner bead fixing. Hold Hold Hold
5 Final coat. Hold Hold Hold
____________________________________________________________________________________
Page 6 of 6 Method Statement for Plastering