Professional Documents
Culture Documents
A CIVIL WORKS
1.0 EARTHWORK
1.1 Site Clearance and layout
1.3 Backfiling
Back filling in foundation and
gardening area approved soil
obtained from the excavation at site
and stacked at site or brought from
outside in layer not exceeding 15 cm
thick (compacted thickness)
including transportation of soil,
spreading in required line and level,
sprinkling water, ramming,
compacting with mechanical
rammers) , testing, etc., all complete
as per drawing, specification and
instructions of the Engineer.
2.0 Brickwork
2.1 Brick soling
Providing and soiling with first class
chimney made brick on flat in
foundation and floor as per drawings,
specification and instruction of the
consultant/Engineer, all complete.
Ground Floor
Along Grid A-A 1 31.499 0.75 8.25 194.9
Along Grid B-B 1 27.332 0.75 8.25 169.12
Along Grid C-C 1 9.25 0.75 8.25 57.23
Along Grid 1-1 1 27.082 0.75 8.25 167.57
Along Grid 2-2 1 26.999 0.75 8.25 167.06
Along Grid 3-3 1 13.333 0.75 8.25 82.5
Along Grid 4-4 1 13.75 0.75 8.25 85.08
Partition wall 1 24.083 0.417 9 90.38
Other than grid 1 15.5 0.75 9 104.63
First Floor
Along Grid A-A 1 31.499 0.75 8.25 194.9
Along Grid B-B 1 7.083 0.75 8.25 43.83
Along Grid C-C 1 22.666 0.75 8.25 140.25
Along Grid 1-1 1 27.082 0.75 8.25 167.57
Along Grid 2-2 1 4.917 0.417 8.25 16.92
Along Grid 3-3 1 19.083 0.75 8.25 118.08
Along Grid 4-4 1 13.75 0.75 8.25 85.08
Partition wall 1 46.5 0.417 9 174.51
Other than grid 1 10.667 0.75 9 72
Other than grid 1 32.5 0.417 9 121.97
Second Floor
Along Grid A-A 1 30.415 0.75 8.25 188.19
Along Grid B-B 1 30.415 0.417 8.25 104.64
Along Grid C-C 1 22.666 0.75 8.25 140.25
Along Grid 1-1 1 27.082 0.75 8.25 167.57
Along Grid 2-2 1 23.582 0.417 8.25 81.13
Along Grid 3-3 1 26.999 0.75 8.25 167.06
Along Grid 4-4 1 13.75 0.75 8.25 85.08
Other than grid 1 32.5 0.417 9 121.97
Partition wall 1 37.417 0.417 9 140.43
Other than grid 1 10.667 0.75 9 72
Deduction
Window(W1) -1 10 0.75 6 -45
Window(W2) -3 6 0.75 4.5 -60.75
Window(W3) -1 6 0.75 3.5 -15.75
Window(W4) -3 4.5 0.75 4 -40.5
Window(W5) -3 4 0.75 10 -90
Window(W6) -1 4.5 0.75 2.5 -8.44
Main Door(MD) -1 4 0.75 8 -24
Door (D1) -8 3 0.417 7 -70.06
Door (D2) -6 2.5 0.417 7 -43.79
Sliding door window -2 10 0.75 7 -105
Ventilation(V1) -5 3 0.75 3 -33.75
Ventilation(V2) -1 3 0.75 2 -4.5
Shutter SH1 -1 12.5 0.75 9 -84.38
Shutter SH2 -1 12.083 0.75 9 -81.56
Shutter SH3 -1 6 0.75 9 -40.5
Total 1:4 B/W 3112.290959 Cu.ft
3.0 PCC/RCC work
3.1 PCC work
3.3 Column
Column upto Plinth beam
Column 14"x14" 11 1.167 1.167 3.5 52.43
Ground Floor
Column 14"x14" 11 1.167 1.167 9.417 141.07
First Floor
Column 14"x14" 11 1.167 1.167 9.417 141.07
Second Floor
Column 14"x14" 11 1.167 1.167 9.417 141.07
Third Floor
Column 14"x14" 4 1.167 1.167 9.417 51.30
Top Floor
Column 14"x14" 4 1.167 1.167 3 16.34
Total RCC for column 543.30 Cu.ft
3.4 Beam
Lower tie beam
Along Grid A-A 1 29.165 0.75 0.75 16.41
Along Grid B-B 1 28.332 0.75 0.75 15.94
Along Grid C-C 1 22.666 0.75 0.75 12.75
Along Grid 1-1 1 27.082 0.75 0.75 15.23
Along Grid 2-2 1 26.999 0.75 0.75 15.19
Along Grid 3-3 1 26.999 0.75 0.75 15.19
Along Grid 4-4 1 13.75 0.75 0.75 7.73
Plinth beam
Along Grid A-A 1 29.165 0.75 0.75 16.41
Along Grid B-B 1 28.332 0.75 0.75 15.94
Along Grid C-C 1 22.666 0.75 0.75 12.75
Along Grid 1-1 1 27.082 0.75 0.75 15.23
Along Grid 2-2 1 26.999 0.75 0.75 15.19
Along Grid 3-3 1 26.999 0.75 0.75 15.19
Along Grid 4-4 1 13.75 0.75 0.75 7.73
Second Floor
Entire block slab 1 A= 1007.47 0.417 420.11
Deduction
Staircase -1 A= 88.268 0.417 -36.81
Void -1 A= 25 0.417 -10.42
Third Floor
Entire block slab 1 A= 1012.84 0.417 422.35
Deduction
Void -1 A= 25 0.417 -10.42
Staircase -1 A= 88.268 0.417 -36.81
Top Floor
Entire block slab 1 A= 254.59 0.417 106.16
Total RCC for Slab 1161.01 Cu.ft
Staircase
Ground Floor
Steps 16 4.083 0.833 0.750 40.81
First Floor
Steps 16 4.083 0.833 0.750 40.81
Second Floor
Steps 16 4.083 0.833 0.750 40.81
3.6 Band
Sill band
Ground Floor
Along Grid A-A 1 31.499 0.75 0.25 5.91
Along Grid B-B 1 27.332 0.75 0.25 5.12
Along Grid C-C 1 9.25 0.75 0.25 1.73
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 26.999 0.75 0.25 5.06
Along Grid 3-3 1 13.333 0.75 0.25 2.5
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Partition wall 1 24.083 0.417 0.25 2.51
Other than grid 1 15.5 0.75 0.25 2.91
First Floor
Along Grid A-A 1 31.499 0.75 0.25 5.91
Along Grid B-B 1 7.083 0.75 0.25 1.33
Along Grid C-C 1 22.666 0.75 0.25 4.25
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 4.917 0.417 0.25 0.51
Along Grid 3-3 1 19.083 0.75 0.25 3.58
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Partition wall 1 46.5 0.417 0.25 4.85
Other than grid 1 10.667 0.75 0.25 2
Other than grid 1 32.5 0.417 0.25 3.39
Second Floor
Along Grid A-A 1 30.415 0.75 0.25 5.7
Along Grid B-B 1 30.415 0.417 0.25 3.17
Along Grid C-C 1 22.666 0.75 0.25 4.25
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 23.582 0.417 0.25 2.46
Along Grid 3-3 1 26.999 0.75 0.25 5.06
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Other than grid 1 32.5 0.75 0.25 6.09
Partition wall 1 37.417 0.417 0.25 3.9
Other than grid 1 10.667 0.417 0.25 1.11
Third Floor
Along Grid A-A 1 13.917 0.75 0.25 2.61
Along Grid B-B 1 13.917 0.417 0.25 1.45
Along Grid 1-1 1 13.75 0.75 0.25 2.58
Along Grid 2-2 1 13.75 0.417 0.25 1.43
Other than grid 1 10.667 0.75 0.25 2
Top Floor
Along Grid A-A 1 13.917 0.75 0.25 2.61
Along Grid B-B 1 13.917 0.417 0.25 1.45
Along Grid 1-1 1 13.75 0.75 0.25 2.58
Along Grid 2-2 1 13.75 0.417 0.25 1.43
Deduction
Window(W5) -3 4 0.75 0.25 -2.25
Main Door(MD) -1 4 0.75 0.25 -0.75
Door (D1) -8 3 0.417 0.25 -2.5
Door (D2) -6 2.5 0.417 0.25 -1.56
Sliding door window -2 10 0.75 0.25 -3.75
Shutter SH1 -1 12.5 0.75 0.25 -2.34
Shutter SH2 -1 12.083 0.75 0.25 -2.27
Shutter SH3 -1 6 0.75 0.25 -1.13
Total RCC for sill band 107.87 Cu.ft
Lintel band
Ground Floor
Along Grid A-A 1 31.499 0.75 0.25 5.91
Along Grid B-B 1 27.332 0.75 0.25 5.12
Along Grid C-C 1 9.25 0.75 0.25 1.73
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 26.999 0.75 0.25 5.06
Along Grid 3-3 1 13.333 0.75 0.25 2.5
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Partition wall 1 24.083 0.417 0.25 2.51
Other than grid 1 15.5 0.75 0.25 2.91
First Floor
Along Grid A-A 1 31.499 0.75 0.25 5.91
Along Grid B-B 1 7.083 0.75 0.25 1.33
Along Grid C-C 1 22.666 0.75 0.25 4.25
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 4.917 0.417 0.25 0.51
Along Grid 3-3 1 19.083 0.75 0.25 3.58
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Partition wall 1 46.5 0.417 0.25 4.85
Other than grid 1 10.667 0.75 0.25 2
Other than grid 1 32.5 0.417 0.25 3.39
Second Floor
Along Grid A-A 1 30.415 0.75 0.25 5.7
Along Grid B-B 1 30.415 0.417 0.25 3.17
Along Grid C-C 1 22.666 0.75 0.25 4.25
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 23.582 0.417 0.25 2.46
Along Grid 3-3 1 26.999 0.75 0.25 5.06
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Other than grid 1 32.5 0.417 0.25 3.39
Partition wall 1 37.417 0.417 0.25 3.9
Other than grid 1 10.667 0.75 0.25 2
Third Floor
Along Grid A-A 1 13.917 0.75 0.25 2.61
Along Grid B-B 1 13.917 0.417 0.25 1.45
Along Grid 1-1 1 13.75 0.75 0.25 2.58
Along Grid 2-2 1 13.75 0.417 0.25 1.43
Other than grid 1 10.667 0.75 0.25 2
Total RCC for lintel band 92.60 Cu.ft
4.0 Formwork
4.1 Column
Column upto Plinth beam
Column 14"x14" 11 4.668 3.75 192.55
Ground Floor
Column 14"x14" 11 4.668 9.417 483.54
First Floor
Column 14"x14" 11 4.668 9.417 483.54
Second Floor
Column 14"x14" 11 4.668 9.417 483.54
Third Floor
Column 14"x14" 4 4.668 9.417 175.83
Top Floor
Column 14"x14" 4 4.668 3 56.02
Total formwork for column 1875.04 Sq.ft
4.3 Beam
Lower tie beam
Along Grid A-A 1 29.165 1.5 43.75
Along Grid B-B 1 28.332 1.5 42.50
Along Grid C-C 1 22.666 1.5 34.00
Along Grid 1-1 1 27.082 1.5 40.62
Along Grid 2-2 1 26.999 1.5 40.50
Along Grid 3-3 1 26.999 1.5 40.50
Along Grid 4-4 1 13.75 1.5 20.63
Plinth beam
Along Grid A-A 1 29.165 1.5 43.75
Along Grid B-B 1 28.332 1.5 42.50
Along Grid C-C 1 22.666 1.5 34.00
Along Grid 1-1 1 27.082 1.5 40.62
Along Grid 2-2 1 26.999 1.5 40.50
Along Grid 3-3 1 26.999 1.5 40.50
Along Grid 4-4 1 13.75 1.5 20.63
4.4 Slab
First Floor
Entire block slab 1 A= 1007.47 1007.47
Sides 1 131.667 0.417 54.91
Deduction
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34
Second Floor
Entire block slab 1 A= 1007.47 1007.47
Sides 1 131.667 0.417 54.91
Deduction
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34
Third Floor
Entire block slab 1 A= 1012.84 1012.84
Sides 1 138.583 0.417 57.79
Deduction
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78
Top Floor
Entire block slab 1 A= 254.59 254.59
Sides 1 63.833 0.417 26.62
Total formwork for slab 3209.13 Sq.ft
4.5 Staircase
Ground Floor
Steps 16 4.083 0.833 54.42
Landing 1 4.083 8.083 33.00
Sides 1 17.334 0.75 13.00
First Floor
Steps 16 4.083 0.833 54.42
Landing 1 4.083 8.083 33.00
Sides 1 17.334 0.75 13.00
Second Floor
Steps 16 4.083 0.833 54.42
Landing 1 4.083 8.083 33.00
Sides 1 17.334 0.75 13.00
Total formwork for stair 301.26 Sq.ft
4.6 Band
Sill band
Ground Floor
Along Grid A-A 1 31.499 0.5 15.75
Along Grid B-B 1 27.332 0.5 13.67
Along Grid C-C 1 9.25 0.5 4.63
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 26.999 0.5 13.50
Along Grid 3-3 1 13.333 0.5 6.67
Along Grid 4-4 1 13.75 0.5 6.88
Partition wall 1 24.083 0.5 12.04
Other than grid 1 15.5 0.5 7.75
First Floor
Along Grid A-A 1 31.499 0.5 15.75
Along Grid B-B 1 7.083 0.5 3.54
Along Grid C-C 1 22.666 0.5 11.33
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 4.917 0.5 2.46
Along Grid 3-3 1 19.083 0.5 9.54
Along Grid 4-4 1 13.75 0.5 6.88
Partition wall 1 46.5 0.5 23.25
Other than grid 1 10.667 0.5 5.33
Other than grid 1 32.5 0.5 16.25
Second Floor
Along Grid A-A 1 30.415 0.5 15.21
Along Grid B-B 1 30.415 0.5 15.21
Along Grid C-C 1 22.666 0.5 11.33
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 23.582 0.5 11.79
Along Grid 3-3 1 26.999 0.5 13.50
Along Grid 4-4 1 13.75 0.5 6.88
Other than grid 1 32.5 0.5 16.25
Partition wall 1 37.417 0.5 18.71
Other than grid 1 10.667 0.5 5.33
Third Floor
Along Grid A-A 1 13.917 0.5 6.96
Along Grid B-B 1 13.917 0.5 6.96
Along Grid 1-1 1 13.75 0.5 6.88
Along Grid 2-2 1 13.75 0.5 6.88
Other than grid 1 10.667 0.5 5.33
Third Floor
Along Grid A-A 1 13.917 0.5 6.96
Along Grid B-B 1 13.917 0.5 6.96
Along Grid 1-1 1 13.75 0.5 6.88
Along Grid 2-2 1 13.75 0.5 6.88
Deduction
Window(W5) -3 4 0.5 -6.00
Main Door(MD) -1 4 0.5 -2.00
Door (D1) -8 3 0.5 -12.00
Door (D2) -6 2.5 0.5 -7.50
Sliding door window -2 10 0.5 -10.00
Shutter SH1 -1 12.5 0.5 -6.25
Shutter SH2 -1 12.083 0.5 -6.04
Shutter SH3 -1 6 0.5 -3.00
Total formwork for lintel band 337.92 Sq.ft
Lintel band
Ground Floor
Along Grid A-A 1 31.499 0.5 15.75
Along Grid B-B 1 27.332 0.5 13.67
Along Grid C-C 1 9.25 0.5 4.63
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 26.999 0.5 13.50
Along Grid 3-3 1 13.333 0.5 6.67
Along Grid 4-4 1 13.75 0.5 6.88
Partition wall 1 24.083 0.5 12.04
Other than grid 1 15.5 0.5 7.75
First Floor
Along Grid A-A 1 31.499 0.5 15.75
Along Grid B-B 1 7.083 0.5 3.54
Along Grid C-C 1 22.666 0.5 11.33
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 4.917 0.5 2.46
Along Grid 3-3 1 19.083 0.5 9.54
Along Grid 4-4 1 13.75 0.5 6.88
Partition wall 1 46.5 0.5 23.25
Other than grid 1 10.667 0.5 5.33
Other than grid 1 32.5 0.5 16.25
Second Floor
Along Grid A-A 1 30.415 0.5 15.21
Along Grid B-B 1 30.415 0.5 15.21
Along Grid C-C 1 22.666 0.5 11.33
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 23.582 0.5 11.79
Along Grid 3-3 1 26.999 0.5 13.50
Along Grid 4-4 1 13.75 0.5 6.88
Other than grid 1 32.5 0.5 16.25
Partition wall 1 37.417 0.5 18.71
Other than grid 1 10.667 0.5 5.33
Third Floor
Along Grid A-A 1 13.917 0.5 6.96
Along Grid B-B 1 13.917 0.5 6.96
Along Grid 1-1 1 13.75 0.5 6.88
Along Grid 2-2 1 13.75 0.5 6.88
Other than grid 1 10.667 0.5 5.33
Total formwork for lintel band 363.03 Sq.ft
5.0 Reinforcement
Providing, assembling and
placing highstrength (TMT)
deformed bars, Fe - 415grade
(confirming to IS: 1786 - 1985)
for RCC work, including cost of
binding wiresfor all floors.
Column(3.5%) 1 543.30 9318.98
Beam(2.5%) 1 523.29 6411.33
Slab,Staircase,Bands,Footing(2.2
1 1938.99 21380.69
5%)
Total Reinforcement 37111.00 lb
16848.39 kg
First Foor
Living Hall, Dining & Kitchen 1 A= 438.94 438.94
Master Bedroom 1 A= 158.69 158.69
Attached Toilet 1 A= 30.48 30.48
C.Toilet 1 A= 35.833 35.83
Closet 1 A= 41.57 41.57
Balcony 1 A= 29.807 29.81
Balcony 1 A= 36.324 36.32
Second Foor
Bedroom 1 1 A= 145.51 145.51
Bedroom 2 2 A= 133.96 133.96
Bedroom 3 2 A= 113.34 113.34
A.Toilet 1 1 A= 29.59 29.59
A.Toilet 2 1 A= 29.85 29.85
A.Toilet 3 1 A= 25.83 25.83
Passage 1 A= 86.69 86.69
Terrace 1 A= 142.34 142.34
Third Floor
Terrace 1 A= 565.47 565.47
Staircase passage 1 A= 33.6 33.60
Top Floor
Terrace 1 A= 233.75 233.75
Total PCC with punning 3030.85 Sq.ft
First Foor
Attached Toilet 1 A= 30.48 30.48
C.Toilet 1 A= 35.833 35.83
Living Hall, Dining & Kitchen 1 A= 438.94 438.94
Master Bedroom 1 A= 158.69 158.69
Closet 1 A= 41.57 41.57
Balcony 1 A= 29.807 29.81
Balcony 1 A= 36.324 36.32
Second Foor
Bedroom 1 1 A= 145.51 145.51
Bedroom 2 1 A= 133.96 133.96
Bedroom 3 1 A= 113.34 113.34
A.Toilet 1 1 A= 29.59 29.59
A.Toilet 2 1 A= 29.85 29.85
A.Toilet 3 1 A= 25.83 25.83
Passage 1 A= 86.69 86.69
Terrace 1 A= 142.34 142.34
Third Floor
Terrace 1 A= 565.47 565.47
Staircase passage 1 A= 33.6 33.60
Top Floor
Terrace 1 A= 233.75 233.75
Total non-Glazed Tile Work 3032.85 Sq.ft
First Foor
Attached Toilet 1 22 6 132.00
C.Toilet 1 24 6 144.00
Second Foor
A.Toilet 1 1 24.25 6 145.50
A.Toilet 2 1 24.25 6 145.50
A.Toilet 3 1 20 6 120.00
Total Glazed Tile Work 806.50 Sq.ft
First Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02
Second Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02
Total marble for stair 393.87 Sq.ft
Second Floor
Entire block slab 1 A= 1007.47 1007.47
Sides 1 131.667 0.417 54.91
Deduction
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34
Third Floor
Entire block slab 1 A= 1012.84 1012.84
Sides 1 138.583 0.417 57.79
Deduction
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78
Top Floor
Entire block slab 1 A= 254.59 254.59
Sides 1 63.833 0.417 26.62
Total 1:3 plaster on ceiling 3209.13 Sq.ft
First Floor
Along Grid A-A 1 31.499 8.25 259.867
Along Grid B-B 2 31.499 8.25 519.734
Along Grid C-C 1 22.666 8.25 186.995
Along Grid 1-1 1 27.082 8.25 223.427
Along Grid 2-2 2 26.999 8.25 445.484
Along Grid 3-3 2 26.999 8.25 445.484
Along Grid 4-4 1 13.75 8.25 113.438
Partition wall 2 23.916 8.25 394.614
Second Floor
Along Grid A-A 1 31.499 8.25 259.867
Along Grid B-B 2 31.499 8.25 519.734
Along Grid C-C 1 22.666 8.25 186.995
Along Grid 1-1 1 27.082 8.25 223.427
Along Grid 2-2 2 26.999 8.25 445.484
Along Grid 3-3 2 26.999 8.25 445.484
Along Grid 4-4 1 13.75 8.25 113.438
Other than grid 1 13.417 8.25 110.69
Partition wall 2 12.583 8.25 207.62
Third Floor
Along Grid A-A 1 13.916 8.25 114.807
Along Grid B-B 1 13.916 8.25 114.807
Along Grid 1-1 1 13.75 8.25 113.438
Along Grid 2-2 1 13.75 8.25 113.438
Top Floor
Along Grid A-A 1 13.916 3 41.748
Along Grid B-B 1 13.916 3 41.748
Along Grid 1-1 1 13.75 3 41.25
Along Grid 2-2 1 13.75 3 41.25
Deduction
Window(W1) -1 10 6 -60
Window(W2) -3 6 4.5 -81
Window(W3) -1 6 3.5 -21
Window(W4) -3 4 4.5 -54
Window(W5) -3 4 10 -120
Window(W6) -1 2.5 4.5 -11.25
Main Door(MD) -1 4 7.5 -30
Door (D1) -12 3 6.5 -234
Door (D2) -12 2.5 7 -210
Shutter SH1 -1 12.5 9 -112.5
Shutter SH2 -1 12.083 9 -108.747
Shutter SH3 -1 6 9 -54
Ventilation(V1) -5 3 3 -45
Ventilation(V2) -1 3 2 -6
Total 1:4 internal wall plaster 6134.66 Sq.ft
First Floor
Along Grid A-A 1 36.167 8.25 298.37775
Along Grid B-B 1 14.417 8.25 118.94025
Along Grid C-C 1 12.417 8.25 102.44025
Along Grid 1-1 1 30.583 8.25 252.30975
Along Grid 3-3 1 30.583 8.25 252.30975
Along Grid 4-4 1 16 8.25 132
Second Floor
Along Grid A-A 1 36.167 8.25 298.37775
Along Grid C-C 1 12.417 8.25 102.44025
Along Grid 1-1 1 30.583 8.25 252.30975
Along Grid 3-3 1 30.583 8.25 252.30975
Other than grid 1 13.417 8.25 110.69025
Third Floor
Along Grid A-A 1 13.916 8.25 114.807
Along Grid B-B 1 13.916 8.25 114.807
Along Grid 1-1 1 13.25 8.25 109.3125
Along Grid 2-2 1 13.25 8.25 109.3125
Top Floor
Along Grid A-A 1 13.916 3 41.748
Along Grid B-B 1 13.916 3 41.748
Along Grid 1-1 1 13.25 3 39.75
Along Grid 2-2 1 13.25 3 39.75
Deduction
Window(W1) -1 10 6 -60
Window(W2) -3 6 4.5 -81
Window(W3) -1 6 3.5 -21
Window(W4) -3 4 4.5 -54
Window(W5) -3 4 10 -120
Window(W6) -1 2.5 4.5 -11.25
Main Door(MD) -1 4 8 -32
Door (D1) -3 3 7 -63.00
Door (D2) -2 2.5 7 -35.00
Sliding door window -2 10 7 -140.00
Shutter SH1 -1 12.5 9 -112.5
Shutter SH2 -1 12.083 9 -108.747
Shutter SH3 -1 6 9 -54
Ventilation(V1) -5 3 3 -45
Ventilation(V2) -1 3 2 -6
Total 1:4 external wall plaster 2795.87 Sq.ft
First Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02
Second Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02
Total 1:4 stair plaster 393.87 Sq.ft
8.0 Door
Door Frame
Main Door (MD) 1 20 0.333 0.25 1.67
Door (D1) 10 17 0.333 0.25 14.15
Door (D2) 7 16.5 0.333 0.25 9.62
Total salwood frame 25.43 Cu.ft
10.0 Railing
50 mm dia stainless steel handrail
in 2m distance
Staircase 2 Running feet= 24 48
Terrace 1 Running feet= 131 131
Terrace 1 Running feet= 34.834 34.834
Total stainless steel railing 213.834 R.ft
Railing glass (Toughen glass) 1 Running feet= 0 0 R.ft
A CIVIL WORKS
1.0 EARTHWORK
1.1 Site Clearance and layout
1.3 Backfiling
2.0 Brickwork
2.1 Brick soling
Providing and soiling with first class chimney
made brick on flat in foundation and floor as per
Sq.ft 1821.95 105.00 191304.75
drawings, specification and instruction of the
consultant/Engineer, all complete.
4.0 Formwork
4.1 Column Sq.ft 1875.04 130.00 243754.88
5.0 Reinforcement
Providing, assembling and placing highstrength
(TMT) deformed bars, Fe - 500grade (confirming
kg 16848.39 115.00 1937565.36
to IS: 1786 - 1985) for RCC work, including cost
of binding wires for all floors.
7.4 20mm thick cement sand plaster(1:4) on stair Sq.ft 393.87 55.00 21662.66
8.0 Railing
(50 mm dia stainless steel handrail) R.ft 213.834 1000.00 213834.00
Railing glass (Toughen glass) R.ft 0 350.61 0.00
Contigences ( E )
i. Physical (5% of D) 586771.65
Subtotal ( F ) 12322204.71