QUANTITY MEASUREMENT

S.N. Item Nos. Length Breadth Height Quantity Unit Remark

A CIVIL WORKS
1.0 EARTHWORK
1.1 Site Clearance and layout

Clearing the site by removing the


bushes, trees, concrete pavement and
hard surface whatever at site up to its
root depth including the layout work,
marking the trench, construction of 1 A= 1450.3 1450.3
permanent reference points along
each grid precisely in line and level
and including construction of all
necessary staff and labor facilities.

Total site clearance and layout 1450.3 Sq.ft


1.2 Earthwork in Excavation

Excavation for Structures


Foundation, Earth work in excavation
of foundation of structures, including
construction of shoring and bracing,
removal of stumps and other
deleterious matter and backfilling
with approved Material as per
Drawing and Technical
Specifications., Ordinary soil
Manually, Depth upto 3 m

Foundation 11 5 5 5.75 1581.25


Lower tie beam
Along Grid A-A 1 21.167 1 3.75 79.38
Along Grid B-B 1 21.167 1 3.75 79.38
Along Grid C-C 1 15 1 3.75 56.25
Along Grid 1-1 1 20.583 1 3.75 77.19
Along Grid 2-2 1 20.5 1 3.75 76.88
Along Grid 3-3 1 20.5 1 3.75 76.88
Along Grid 4-4 1 9.917 1 3.75 37.19
Total earthwork in excavation 1740.01 Cu.ft

1.3 Backfiling
Back filling in foundation and
gardening area approved soil
obtained from the excavation at site
and stacked at site or brought from
outside in layer not exceeding 15 cm
thick (compacted thickness)
including transportation of soil,
spreading in required line and level,
sprinkling water, ramming,
compacting with mechanical
rammers) , testing, etc., all complete
as per drawing, specification and
instructions of the Engineer.

(60% of excavation) 1 1044.01 1044.01


Total Back Filling Work 1044.01 Cu.ft

2.0 Brickwork
2.1 Brick soling
Providing and soiling with first class
chimney made brick on flat in
foundation and floor as per drawings,
specification and instruction of the
consultant/Engineer, all complete.

For footing 11 5 5 275


Lower tie beam
Along Grid A-A 1 21.167 0.75 15.88
Along Grid B-B 1 21.167 0.75 15.88
Along Grid C-C 1 15 0.75 11.25
Along Grid 1-1 1 20.583 0.75 15.44
Along Grid 2-2 1 20.5 0.75 15.38
Along Grid 3-3 1 20.5 0.75 15.38
Along Grid 4-4 1 9.917 0.75 7.44

For Floors 1 A= 905.642 905.642


Compound 1 A= 544.658 544.658
Total flat brick soling 1821.95 Sq.ft

2.2 Brick Masonry Works in 1:6 C/S mortar


Providing and laying first class
chimney fired brick one or more
brick thick wall in cement mortar 1:6
(1 cement : 6 coarse sand) in
foundation up to plinth and other
specified places in all heights and
level including the cost of single or
multi stage scaffolding, soaking
bricks, curing, raking joints,
provision for recesses, openings,
toothing etc., all complete as per
drawing, specifications and
instructions of the Engineer.

Below Plinth Beam


Along Grid A-A 1 31.499 0.75 3 70.87
Along Grid B-B 1 31.499 0.75 3 70.87
Along Grid C-C 1 22.666 0.75 3 51.00
Along Grid 1-1 1 27.082 0.75 3 60.93
Along Grid 2-2 1 26.999 0.75 3 60.75
Along Grid 3-3 1 26.999 0.75 3 60.75
Along Grid 4-4 1 13.75 0.75 3 30.94
Total 1:6 B/W 314.42 Cu.ft

Brick Masonry Works in 1:4


2.3
C/S mortar

Providing and laying first class


chimney fired brick one or more
brick thick wall in cement mortar 1:6
(1 cement : 6 coarse sand) in
superstructure in all heights and level
including the cost of single or multi
stage scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc., all
complete as per drawing,
specifications and instructions of the
Engineer.

Ground Floor
Along Grid A-A 1 31.499 0.75 8.25 194.9
Along Grid B-B 1 27.332 0.75 8.25 169.12
Along Grid C-C 1 9.25 0.75 8.25 57.23
Along Grid 1-1 1 27.082 0.75 8.25 167.57
Along Grid 2-2 1 26.999 0.75 8.25 167.06
Along Grid 3-3 1 13.333 0.75 8.25 82.5
Along Grid 4-4 1 13.75 0.75 8.25 85.08
Partition wall 1 24.083 0.417 9 90.38
Other than grid 1 15.5 0.75 9 104.63

First Floor
Along Grid A-A 1 31.499 0.75 8.25 194.9
Along Grid B-B 1 7.083 0.75 8.25 43.83
Along Grid C-C 1 22.666 0.75 8.25 140.25
Along Grid 1-1 1 27.082 0.75 8.25 167.57
Along Grid 2-2 1 4.917 0.417 8.25 16.92
Along Grid 3-3 1 19.083 0.75 8.25 118.08
Along Grid 4-4 1 13.75 0.75 8.25 85.08
Partition wall 1 46.5 0.417 9 174.51
Other than grid 1 10.667 0.75 9 72
Other than grid 1 32.5 0.417 9 121.97

Second Floor
Along Grid A-A 1 30.415 0.75 8.25 188.19
Along Grid B-B 1 30.415 0.417 8.25 104.64
Along Grid C-C 1 22.666 0.75 8.25 140.25
Along Grid 1-1 1 27.082 0.75 8.25 167.57
Along Grid 2-2 1 23.582 0.417 8.25 81.13
Along Grid 3-3 1 26.999 0.75 8.25 167.06
Along Grid 4-4 1 13.75 0.75 8.25 85.08
Other than grid 1 32.5 0.417 9 121.97
Partition wall 1 37.417 0.417 9 140.43
Other than grid 1 10.667 0.75 9 72

Third Floor beam


Along Grid A-A 1 13.917 0.75 8.25 86.11
Along Grid B-B 1 13.917 0.417 8.25 47.88
Along Grid 1-1 1 13.75 0.75 8.25 85.08
Along Grid 2-2 1 13.75 0.417 8.25 47.30
Other than grid 1 10.667 0.75 9 72

Deduction
Window(W1) -1 10 0.75 6 -45
Window(W2) -3 6 0.75 4.5 -60.75
Window(W3) -1 6 0.75 3.5 -15.75
Window(W4) -3 4.5 0.75 4 -40.5
Window(W5) -3 4 0.75 10 -90
Window(W6) -1 4.5 0.75 2.5 -8.44
Main Door(MD) -1 4 0.75 8 -24
Door (D1) -8 3 0.417 7 -70.06
Door (D2) -6 2.5 0.417 7 -43.79
Sliding door window -2 10 0.75 7 -105
Ventilation(V1) -5 3 0.75 3 -33.75
Ventilation(V2) -1 3 0.75 2 -4.5
Shutter SH1 -1 12.5 0.75 9 -84.38
Shutter SH2 -1 12.083 0.75 9 -81.56
Shutter SH3 -1 6 0.75 9 -40.5
Total 1:4 B/W 3112.290959 Cu.ft
3.0 PCC/RCC work
3.1 PCC work

Providing and laying machine


mixed Plain Cement Concrete of
nominal mix 1:3:6 (1 cement : 2
sand : 4 coarse aggregate ) for
leveling course in foundations
and under floor of building, etc.
in all level with broken stone
aggregate of size not more than
25 mm of approved quality
including formwork wherever
necessary, dewatering, batching,
mixing, transporting, placing,
compacting, curing, including all
lead and lift, etc. all complete as
per drawings, specifications and
the instructions of the Engineer.

Foundation 11 5 5.00 0.333 91.58


Total M10(1:3:6) PCC 91.58 Cu.ft

Providing and laying machine


mixed Plain Cement Concrete of
nominal mix 1:2:4 (1 cement : 2
sand : 4 coarse aggregate ) for
leveling course in foundations
and under floor of building, etc.
in all level with broken stone
aggregate of size not more than
25 mm of approved quality
including formwork wherever
necessary, dewatering, batching,
mixing, transporting, placing,
compacting, curing, including all
lead and lift, etc. all complete as
per drawings, specifications and
the instructions of the Engineer.

Rooms 1 A= 905.642 0.333 301.58


Compound 1 A= 506.83 0.333 168.77
Total M15(1:2:4) PCC 301.58 Cu.ft

3.2 PCC for RCC work


Providing and laying in position
machine mixed and machine vibrated
cement concrete of mix 1:1.5:3 (1
cement:1.5 sand: 3 coarse
aggreagate) M20 grade for
reinforced cement concrete work
using approved cement with 20 mm
graded machine crushed stone
aggregate of approved quality in
various locations and heights
including transportation of concrete
to site of placing, compaction,
finished to required line and level,
protection and curing, etc. all
complete as per drawings,
specifications and the instructions of
the Engineer, but excluding the cost
of centering, shuttering, and
reinforcement, but including the cost
of 2.5% Rheobuild SP-1 admixture
or equivalent by Weight of Cement
all complete as per drawings,
specifications and instructions of the
Engineer.

Foundation 11 5 5 1.5 412.5


Total RCC for footing 412.5 Cu.ft

3.3 Column
Column upto Plinth beam
Column 14"x14" 11 1.167 1.167 3.5 52.43
Ground Floor
Column 14"x14" 11 1.167 1.167 9.417 141.07
First Floor
Column 14"x14" 11 1.167 1.167 9.417 141.07
Second Floor
Column 14"x14" 11 1.167 1.167 9.417 141.07
Third Floor
Column 14"x14" 4 1.167 1.167 9.417 51.30
Top Floor
Column 14"x14" 4 1.167 1.167 3 16.34
Total RCC for column 543.30 Cu.ft

3.4 Beam
Lower tie beam
Along Grid A-A 1 29.165 0.75 0.75 16.41
Along Grid B-B 1 28.332 0.75 0.75 15.94
Along Grid C-C 1 22.666 0.75 0.75 12.75
Along Grid 1-1 1 27.082 0.75 0.75 15.23
Along Grid 2-2 1 26.999 0.75 0.75 15.19
Along Grid 3-3 1 26.999 0.75 0.75 15.19
Along Grid 4-4 1 13.75 0.75 0.75 7.73

Plinth beam
Along Grid A-A 1 29.165 0.75 0.75 16.41
Along Grid B-B 1 28.332 0.75 0.75 15.94
Along Grid C-C 1 22.666 0.75 0.75 12.75
Along Grid 1-1 1 27.082 0.75 0.75 15.23
Along Grid 2-2 1 26.999 0.75 0.75 15.19
Along Grid 3-3 1 26.999 0.75 0.75 15.19
Along Grid 4-4 1 13.75 0.75 0.75 7.73

Ground Floor beam


Along Grid A-A 1 29.165 0.75 0.75 16.41
Along Grid B-B 1 28.332 0.75 0.75 15.94
Along Grid C-C 1 22.666 0.75 0.75 12.75
Along Grid 1-1 1 27.082 0.75 0.75 15.23
Along Grid 2-2 1 26.999 0.75 0.75 15.19
Along Grid 3-3 1 26.999 0.75 0.75 15.19
Along Grid 4-4 1 13.75 0.75 0.75 7.73

First Floor beam


Along Grid A-A 1 29.165 0.75 0.75 16.41
Along Grid B-B 1 28.332 0.75 0.75 15.94
Along Grid C-C 1 22.666 0.75 0.75 12.75
Along Grid 1-1 1 27.082 0.75 0.75 15.23
Along Grid 2-2 1 26.999 0.75 0.75 15.19
Along Grid 3-3 1 26.999 0.75 0.75 15.19
Along Grid 4-4 1 13.75 0.75 0.75 7.73

Second Floor beam


Along Grid A-A 1 29.165 0.75 0.75 16.41
Along Grid B-B 1 28.332 0.75 0.75 15.94
Along Grid C-C 1 22.666 0.75 0.75 12.75
Along Grid 1-1 1 27.082 0.75 0.75 15.23
Along Grid 2-2 1 26.999 0.75 0.75 15.19
Along Grid 3-3 1 26.999 0.75 0.75 15.19
Along Grid 4-4 1 13.75 0.75 0.75 7.73

Third Floor beam


Along Grid A-A 1 13.917 0.75 0.75 7.83
Along Grid B-B 1 13.917 0.75 0.75 7.83
Along Grid 1-1 1 13.75 0.75 0.75 7.73
Along Grid 2-2 1 13.75 0.75 0.75 7.73

Total RCC for Beam 523.29 Cu.ft


3.5 Slab
First Floor
Entire block slab 1 A= 1007.47 0.417 420.11
Deduction
Staircase -1 A= 88.268 -88.27
Void -1 A= 25 -25.00

Second Floor
Entire block slab 1 A= 1007.47 0.417 420.11
Deduction
Staircase -1 A= 88.268 0.417 -36.81
Void -1 A= 25 0.417 -10.42

Third Floor
Entire block slab 1 A= 1012.84 0.417 422.35
Deduction
Void -1 A= 25 0.417 -10.42
Staircase -1 A= 88.268 0.417 -36.81

Top Floor
Entire block slab 1 A= 254.59 0.417 106.16
Total RCC for Slab 1161.01 Cu.ft

Staircase
Ground Floor
Steps 16 4.083 0.833 0.750 40.81

Landing 1 4.083 8.333 0.417 14.19

First Floor
Steps 16 4.083 0.833 0.750 40.81

Landing 1 4.083 8.333 0.417 14.19

Second Floor
Steps 16 4.083 0.833 0.750 40.81

Landing 1 4.083 8.333 0.417 14.19

Total RCC for Staircase 165.00 Cu.ft

3.6 Band
Sill band
Ground Floor
Along Grid A-A 1 31.499 0.75 0.25 5.91
Along Grid B-B 1 27.332 0.75 0.25 5.12
Along Grid C-C 1 9.25 0.75 0.25 1.73
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 26.999 0.75 0.25 5.06
Along Grid 3-3 1 13.333 0.75 0.25 2.5
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Partition wall 1 24.083 0.417 0.25 2.51
Other than grid 1 15.5 0.75 0.25 2.91

First Floor
Along Grid A-A 1 31.499 0.75 0.25 5.91
Along Grid B-B 1 7.083 0.75 0.25 1.33
Along Grid C-C 1 22.666 0.75 0.25 4.25
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 4.917 0.417 0.25 0.51
Along Grid 3-3 1 19.083 0.75 0.25 3.58
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Partition wall 1 46.5 0.417 0.25 4.85
Other than grid 1 10.667 0.75 0.25 2
Other than grid 1 32.5 0.417 0.25 3.39

Second Floor
Along Grid A-A 1 30.415 0.75 0.25 5.7
Along Grid B-B 1 30.415 0.417 0.25 3.17
Along Grid C-C 1 22.666 0.75 0.25 4.25
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 23.582 0.417 0.25 2.46
Along Grid 3-3 1 26.999 0.75 0.25 5.06
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Other than grid 1 32.5 0.75 0.25 6.09
Partition wall 1 37.417 0.417 0.25 3.9
Other than grid 1 10.667 0.417 0.25 1.11

Third Floor
Along Grid A-A 1 13.917 0.75 0.25 2.61
Along Grid B-B 1 13.917 0.417 0.25 1.45
Along Grid 1-1 1 13.75 0.75 0.25 2.58
Along Grid 2-2 1 13.75 0.417 0.25 1.43
Other than grid 1 10.667 0.75 0.25 2

Top Floor
Along Grid A-A 1 13.917 0.75 0.25 2.61
Along Grid B-B 1 13.917 0.417 0.25 1.45
Along Grid 1-1 1 13.75 0.75 0.25 2.58
Along Grid 2-2 1 13.75 0.417 0.25 1.43

Deduction
Window(W5) -3 4 0.75 0.25 -2.25
Main Door(MD) -1 4 0.75 0.25 -0.75
Door (D1) -8 3 0.417 0.25 -2.5
Door (D2) -6 2.5 0.417 0.25 -1.56
Sliding door window -2 10 0.75 0.25 -3.75
Shutter SH1 -1 12.5 0.75 0.25 -2.34
Shutter SH2 -1 12.083 0.75 0.25 -2.27
Shutter SH3 -1 6 0.75 0.25 -1.13
Total RCC for sill band 107.87 Cu.ft

Lintel band
Ground Floor
Along Grid A-A 1 31.499 0.75 0.25 5.91
Along Grid B-B 1 27.332 0.75 0.25 5.12
Along Grid C-C 1 9.25 0.75 0.25 1.73
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 26.999 0.75 0.25 5.06
Along Grid 3-3 1 13.333 0.75 0.25 2.5
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Partition wall 1 24.083 0.417 0.25 2.51
Other than grid 1 15.5 0.75 0.25 2.91

First Floor
Along Grid A-A 1 31.499 0.75 0.25 5.91
Along Grid B-B 1 7.083 0.75 0.25 1.33
Along Grid C-C 1 22.666 0.75 0.25 4.25
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 4.917 0.417 0.25 0.51
Along Grid 3-3 1 19.083 0.75 0.25 3.58
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Partition wall 1 46.5 0.417 0.25 4.85
Other than grid 1 10.667 0.75 0.25 2
Other than grid 1 32.5 0.417 0.25 3.39

Second Floor
Along Grid A-A 1 30.415 0.75 0.25 5.7
Along Grid B-B 1 30.415 0.417 0.25 3.17
Along Grid C-C 1 22.666 0.75 0.25 4.25
Along Grid 1-1 1 27.082 0.75 0.25 5.08
Along Grid 2-2 1 23.582 0.417 0.25 2.46
Along Grid 3-3 1 26.999 0.75 0.25 5.06
Along Grid 4-4 1 13.75 0.75 0.25 2.58
Other than grid 1 32.5 0.417 0.25 3.39
Partition wall 1 37.417 0.417 0.25 3.9
Other than grid 1 10.667 0.75 0.25 2

Third Floor
Along Grid A-A 1 13.917 0.75 0.25 2.61
Along Grid B-B 1 13.917 0.417 0.25 1.45
Along Grid 1-1 1 13.75 0.75 0.25 2.58
Along Grid 2-2 1 13.75 0.417 0.25 1.43
Other than grid 1 10.667 0.75 0.25 2
Total RCC for lintel band 92.60 Cu.ft

4.0 Formwork
4.1 Column
Column upto Plinth beam
Column 14"x14" 11 4.668 3.75 192.55
Ground Floor
Column 14"x14" 11 4.668 9.417 483.54
First Floor
Column 14"x14" 11 4.668 9.417 483.54
Second Floor
Column 14"x14" 11 4.668 9.417 483.54
Third Floor
Column 14"x14" 4 4.668 9.417 175.83
Top Floor
Column 14"x14" 4 4.668 3 56.02
Total formwork for column 1875.04 Sq.ft

4.2 Footing 11 20 1.5 330.00


Total formwork for footing 330.00 Sq.ft

4.3 Beam
Lower tie beam
Along Grid A-A 1 29.165 1.5 43.75
Along Grid B-B 1 28.332 1.5 42.50
Along Grid C-C 1 22.666 1.5 34.00
Along Grid 1-1 1 27.082 1.5 40.62
Along Grid 2-2 1 26.999 1.5 40.50
Along Grid 3-3 1 26.999 1.5 40.50
Along Grid 4-4 1 13.75 1.5 20.63

Plinth beam
Along Grid A-A 1 29.165 1.5 43.75
Along Grid B-B 1 28.332 1.5 42.50
Along Grid C-C 1 22.666 1.5 34.00
Along Grid 1-1 1 27.082 1.5 40.62
Along Grid 2-2 1 26.999 1.5 40.50
Along Grid 3-3 1 26.999 1.5 40.50
Along Grid 4-4 1 13.75 1.5 20.63

First Floor beam


Along Grid A-A 1 29.165 1.5 43.75
Along Grid B-B 1 28.332 1.5 42.50
Along Grid C-C 1 22.666 1.5 34.00
Along Grid 1-1 1 27.082 1.5 40.62
Along Grid 2-2 1 26.999 1.5 40.50
Along Grid 3-3 1 26.999 1.5 40.50
Along Grid 4-4 1 13.75 1.5 20.63

Second Floor beam


Along Grid A-A 1 29.165 1.5 43.75
Along Grid B-B 1 28.332 1.5 42.50
Along Grid C-C 1 22.666 1.5 34.00
Along Grid 1-1 1 27.082 1.5 40.62
Along Grid 2-2 1 26.999 1.5 40.50
Along Grid 3-3 1 26.999 1.5 40.50
Along Grid 4-4 1 13.75 1.5 20.63

Third Floor beam


Along Grid A-A 1 13.917 1.5 20.88
Along Grid B-B 1 13.917 1.5 20.88
Along Grid 1-1 1 13.75 1.5 20.63
Along Grid 2-2 1 13.75 1.5 20.63
Total formwork for beam 1049.96 Sq.ft

4.4 Slab
First Floor
Entire block slab 1 A= 1007.47 1007.47
Sides 1 131.667 0.417 54.91
Deduction
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34

Second Floor
Entire block slab 1 A= 1007.47 1007.47
Sides 1 131.667 0.417 54.91

Deduction
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34

Third Floor
Entire block slab 1 A= 1012.84 1012.84
Sides 1 138.583 0.417 57.79
Deduction
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78

Top Floor
Entire block slab 1 A= 254.59 254.59
Sides 1 63.833 0.417 26.62
Total formwork for slab 3209.13 Sq.ft

4.5 Staircase
Ground Floor
Steps 16 4.083 0.833 54.42
Landing 1 4.083 8.083 33.00
Sides 1 17.334 0.75 13.00

First Floor
Steps 16 4.083 0.833 54.42
Landing 1 4.083 8.083 33.00
Sides 1 17.334 0.75 13.00

Second Floor
Steps 16 4.083 0.833 54.42
Landing 1 4.083 8.083 33.00
Sides 1 17.334 0.75 13.00
Total formwork for stair 301.26 Sq.ft
4.6 Band
Sill band
Ground Floor
Along Grid A-A 1 31.499 0.5 15.75
Along Grid B-B 1 27.332 0.5 13.67
Along Grid C-C 1 9.25 0.5 4.63
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 26.999 0.5 13.50
Along Grid 3-3 1 13.333 0.5 6.67
Along Grid 4-4 1 13.75 0.5 6.88
Partition wall 1 24.083 0.5 12.04
Other than grid 1 15.5 0.5 7.75

First Floor
Along Grid A-A 1 31.499 0.5 15.75
Along Grid B-B 1 7.083 0.5 3.54
Along Grid C-C 1 22.666 0.5 11.33
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 4.917 0.5 2.46
Along Grid 3-3 1 19.083 0.5 9.54
Along Grid 4-4 1 13.75 0.5 6.88
Partition wall 1 46.5 0.5 23.25
Other than grid 1 10.667 0.5 5.33
Other than grid 1 32.5 0.5 16.25

Second Floor
Along Grid A-A 1 30.415 0.5 15.21
Along Grid B-B 1 30.415 0.5 15.21
Along Grid C-C 1 22.666 0.5 11.33
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 23.582 0.5 11.79
Along Grid 3-3 1 26.999 0.5 13.50
Along Grid 4-4 1 13.75 0.5 6.88
Other than grid 1 32.5 0.5 16.25
Partition wall 1 37.417 0.5 18.71
Other than grid 1 10.667 0.5 5.33

Third Floor
Along Grid A-A 1 13.917 0.5 6.96
Along Grid B-B 1 13.917 0.5 6.96
Along Grid 1-1 1 13.75 0.5 6.88
Along Grid 2-2 1 13.75 0.5 6.88
Other than grid 1 10.667 0.5 5.33

Third Floor
Along Grid A-A 1 13.917 0.5 6.96
Along Grid B-B 1 13.917 0.5 6.96
Along Grid 1-1 1 13.75 0.5 6.88
Along Grid 2-2 1 13.75 0.5 6.88

Deduction
Window(W5) -3 4 0.5 -6.00
Main Door(MD) -1 4 0.5 -2.00
Door (D1) -8 3 0.5 -12.00
Door (D2) -6 2.5 0.5 -7.50
Sliding door window -2 10 0.5 -10.00
Shutter SH1 -1 12.5 0.5 -6.25
Shutter SH2 -1 12.083 0.5 -6.04
Shutter SH3 -1 6 0.5 -3.00
Total formwork for lintel band 337.92 Sq.ft

Lintel band
Ground Floor
Along Grid A-A 1 31.499 0.5 15.75
Along Grid B-B 1 27.332 0.5 13.67
Along Grid C-C 1 9.25 0.5 4.63
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 26.999 0.5 13.50
Along Grid 3-3 1 13.333 0.5 6.67
Along Grid 4-4 1 13.75 0.5 6.88
Partition wall 1 24.083 0.5 12.04
Other than grid 1 15.5 0.5 7.75

First Floor
Along Grid A-A 1 31.499 0.5 15.75
Along Grid B-B 1 7.083 0.5 3.54
Along Grid C-C 1 22.666 0.5 11.33
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 4.917 0.5 2.46
Along Grid 3-3 1 19.083 0.5 9.54
Along Grid 4-4 1 13.75 0.5 6.88
Partition wall 1 46.5 0.5 23.25
Other than grid 1 10.667 0.5 5.33
Other than grid 1 32.5 0.5 16.25

Second Floor
Along Grid A-A 1 30.415 0.5 15.21
Along Grid B-B 1 30.415 0.5 15.21
Along Grid C-C 1 22.666 0.5 11.33
Along Grid 1-1 1 27.082 0.5 13.54
Along Grid 2-2 1 23.582 0.5 11.79
Along Grid 3-3 1 26.999 0.5 13.50
Along Grid 4-4 1 13.75 0.5 6.88
Other than grid 1 32.5 0.5 16.25
Partition wall 1 37.417 0.5 18.71
Other than grid 1 10.667 0.5 5.33

Third Floor
Along Grid A-A 1 13.917 0.5 6.96
Along Grid B-B 1 13.917 0.5 6.96
Along Grid 1-1 1 13.75 0.5 6.88
Along Grid 2-2 1 13.75 0.5 6.88
Other than grid 1 10.667 0.5 5.33
Total formwork for lintel band 363.03 Sq.ft

5.0 Reinforcement
Providing, assembling and
placing highstrength (TMT)
deformed bars, Fe - 415grade
(confirming to IS: 1786 - 1985)
for RCC work, including cost of
binding wiresfor all floors.
Column(3.5%) 1 543.30 9318.98
Beam(2.5%) 1 523.29 6411.33
Slab,Staircase,Bands,Footing(2.2
1 1938.99 21380.69
5%)
Total Reinforcement 37111.00 lb
16848.39 kg

6.0 Flooring and Finishing Work


50mm thick P.C.C IN (1:2:4) with
6.1 cement punning (1:1) for flooring
work
Ground Foor
Shutter 1 1 A= 182.88 182.88
Bedroom 1 A= 115.58 115.58
Shutter 2 1 A= 173.2 173.20
C.Toilet 1 A= 23.66 23.66
Car Parking and Entrancee Area 1 A= 191.97 191.97
Staircase area 1 A= 31.99 31.99

First Foor
Living Hall, Dining & Kitchen 1 A= 438.94 438.94
Master Bedroom 1 A= 158.69 158.69
Attached Toilet 1 A= 30.48 30.48
C.Toilet 1 A= 35.833 35.83
Closet 1 A= 41.57 41.57
Balcony 1 A= 29.807 29.81
Balcony 1 A= 36.324 36.32

Second Foor
Bedroom 1 1 A= 145.51 145.51
Bedroom 2 2 A= 133.96 133.96
Bedroom 3 2 A= 113.34 113.34
A.Toilet 1 1 A= 29.59 29.59
A.Toilet 2 1 A= 29.85 29.85
A.Toilet 3 1 A= 25.83 25.83
Passage 1 A= 86.69 86.69
Terrace 1 A= 142.34 142.34

Third Floor
Terrace 1 A= 565.47 565.47
Staircase passage 1 A= 33.6 33.60

Top Floor
Terrace 1 A= 233.75 233.75
Total PCC with punning 3030.85 Sq.ft

6.2 Providing and laying glazed


porcelein tile on the floor
Ground Floor
Shutter 1 1 A= 182.88 182.88
Bedroom 1 A= 115.58 115.58
Shutter 2 1 A= 173.2 173.20
C.Toilet 1 A= 23.66 23.66
Car Parking and Entrancee Area 1 A= 191.97 191.97
Staircase area 1 A= 31.99 31.99

First Foor
Attached Toilet 1 A= 30.48 30.48
C.Toilet 1 A= 35.833 35.83
Living Hall, Dining & Kitchen 1 A= 438.94 438.94
Master Bedroom 1 A= 158.69 158.69
Closet 1 A= 41.57 41.57
Balcony 1 A= 29.807 29.81
Balcony 1 A= 36.324 36.32

Second Foor
Bedroom 1 1 A= 145.51 145.51
Bedroom 2 1 A= 133.96 133.96
Bedroom 3 1 A= 113.34 113.34
A.Toilet 1 1 A= 29.59 29.59
A.Toilet 2 1 A= 29.85 29.85
A.Toilet 3 1 A= 25.83 25.83
Passage 1 A= 86.69 86.69
Terrace 1 A= 142.34 142.34

Third Floor
Terrace 1 A= 565.47 565.47
Staircase passage 1 A= 33.6 33.60

Top Floor
Terrace 1 A= 233.75 233.75
Total non-Glazed Tile Work 3032.85 Sq.ft

6.3 Providing and laying glazed


porcelein tile on the wall
Ground Floor
C.Toilet 1 19.917 6 119.50

First Foor
Attached Toilet 1 22 6 132.00
C.Toilet 1 24 6 144.00

Second Foor
A.Toilet 1 1 24.25 6 145.50
A.Toilet 2 1 24.25 6 145.50
A.Toilet 3 1 20 6 120.00
Total Glazed Tile Work 806.50 Sq.ft

6.4 Providing and laying marble on


the stair
Staircase
Ground Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02

First Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02

Second Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02
Total marble for stair 393.87 Sq.ft

6.5 Providing and laying granite on


the kitchen
Kitchen counter 1 A= 42.64 42.64 Sq.ft

7.0 Plastering & Punning Works


12.5mm thick cement plaster in
7.1
(1:3) in ceiling, beams stc
First Floor
Entire block slab 1 A= 1007.47 1007.47
Sides 1 131.667 0.417 54.91
Deduction
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34

Second Floor
Entire block slab 1 A= 1007.47 1007.47
Sides 1 131.667 0.417 54.91

Deduction
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34

Third Floor
Entire block slab 1 A= 1012.84 1012.84
Sides 1 138.583 0.417 57.79
Deduction
Void -1 A= 25 -25.00
Sides 1 20 0.417 8.34
Staircase -1 A= 88.268 -88.27
Sides 1 37.833 0.417 15.78

Top Floor
Entire block slab 1 A= 254.59 254.59
Sides 1 63.833 0.417 26.62
Total 1:3 plaster on ceiling 3209.13 Sq.ft

20mm thick cement plaster in


7.2
(1:4) in Internal Wall etc
Ground Floor
Along Grid A-A 1 36.167 8.25 298.378
Along Grid B-B 2 36.167 8.25 596.756
Along Grid C-C 1 12.417 8.25 102.44
Along Grid 1-1 1 30.583 8.25 252.31
Partition wall 2 18.667 8.25 308.006

First Floor
Along Grid A-A 1 31.499 8.25 259.867
Along Grid B-B 2 31.499 8.25 519.734
Along Grid C-C 1 22.666 8.25 186.995
Along Grid 1-1 1 27.082 8.25 223.427
Along Grid 2-2 2 26.999 8.25 445.484
Along Grid 3-3 2 26.999 8.25 445.484
Along Grid 4-4 1 13.75 8.25 113.438
Partition wall 2 23.916 8.25 394.614

Second Floor
Along Grid A-A 1 31.499 8.25 259.867
Along Grid B-B 2 31.499 8.25 519.734
Along Grid C-C 1 22.666 8.25 186.995
Along Grid 1-1 1 27.082 8.25 223.427
Along Grid 2-2 2 26.999 8.25 445.484
Along Grid 3-3 2 26.999 8.25 445.484
Along Grid 4-4 1 13.75 8.25 113.438
Other than grid 1 13.417 8.25 110.69
Partition wall 2 12.583 8.25 207.62

Third Floor
Along Grid A-A 1 13.916 8.25 114.807
Along Grid B-B 1 13.916 8.25 114.807
Along Grid 1-1 1 13.75 8.25 113.438
Along Grid 2-2 1 13.75 8.25 113.438

Top Floor
Along Grid A-A 1 13.916 3 41.748
Along Grid B-B 1 13.916 3 41.748
Along Grid 1-1 1 13.75 3 41.25
Along Grid 2-2 1 13.75 3 41.25

Deduction
Window(W1) -1 10 6 -60
Window(W2) -3 6 4.5 -81
Window(W3) -1 6 3.5 -21
Window(W4) -3 4 4.5 -54
Window(W5) -3 4 10 -120
Window(W6) -1 2.5 4.5 -11.25
Main Door(MD) -1 4 7.5 -30
Door (D1) -12 3 6.5 -234
Door (D2) -12 2.5 7 -210
Shutter SH1 -1 12.5 9 -112.5
Shutter SH2 -1 12.083 9 -108.747
Shutter SH3 -1 6 9 -54
Ventilation(V1) -5 3 3 -45
Ventilation(V2) -1 3 2 -6
Total 1:4 internal wall plaster 6134.66 Sq.ft

20mm thick cement plaster in


7.3
(1:4) in external Wall etc
Ground Floor
Along Grid A-A 1 36.167 8.25 298.37775
Along Grid C-C 1 12.417 8.25 102.44025
Along Grid 1-1 1 30.583 8.25 252.30975
Other than grid 1 36.667 8.25 302.50275

First Floor
Along Grid A-A 1 36.167 8.25 298.37775
Along Grid B-B 1 14.417 8.25 118.94025
Along Grid C-C 1 12.417 8.25 102.44025
Along Grid 1-1 1 30.583 8.25 252.30975
Along Grid 3-3 1 30.583 8.25 252.30975
Along Grid 4-4 1 16 8.25 132

Second Floor
Along Grid A-A 1 36.167 8.25 298.37775
Along Grid C-C 1 12.417 8.25 102.44025
Along Grid 1-1 1 30.583 8.25 252.30975
Along Grid 3-3 1 30.583 8.25 252.30975
Other than grid 1 13.417 8.25 110.69025

Third Floor
Along Grid A-A 1 13.916 8.25 114.807
Along Grid B-B 1 13.916 8.25 114.807
Along Grid 1-1 1 13.25 8.25 109.3125
Along Grid 2-2 1 13.25 8.25 109.3125

Top Floor
Along Grid A-A 1 13.916 3 41.748
Along Grid B-B 1 13.916 3 41.748
Along Grid 1-1 1 13.25 3 39.75
Along Grid 2-2 1 13.25 3 39.75

Deduction
Window(W1) -1 10 6 -60
Window(W2) -3 6 4.5 -81
Window(W3) -1 6 3.5 -21
Window(W4) -3 4 4.5 -54
Window(W5) -3 4 10 -120
Window(W6) -1 2.5 4.5 -11.25
Main Door(MD) -1 4 8 -32
Door (D1) -3 3 7 -63.00
Door (D2) -2 2.5 7 -35.00
Sliding door window -2 10 7 -140.00
Shutter SH1 -1 12.5 9 -112.5
Shutter SH2 -1 12.083 9 -108.747
Shutter SH3 -1 6 9 -54
Ventilation(V1) -5 3 3 -45
Ventilation(V2) -1 3 2 -6
Total 1:4 external wall plaster 2795.87 Sq.ft

20mm thick cement sand plaster


7.4
(1:4) on stair
Ground Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02

First Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02

Second Floor
Tread 16 4.083 0.833 54.42
Riser 18 4.083 0.583 42.85
Landing 1 4.083 8.333 34.02
Total 1:4 stair plaster 393.87 Sq.ft

8.0 Door
Door Frame
Main Door (MD) 1 20 0.333 0.25 1.67
Door (D1) 10 17 0.333 0.25 14.15
Door (D2) 7 16.5 0.333 0.25 9.62
Total salwood frame 25.43 Cu.ft

Solid Door Flush door shuttle


Main Door (MD) 1 4 8 32.00
Door (D1) 10 3 7 210.00
Door (D2) 7 2.5 7 122.50
Total solid core flush door shuttle 364.50 Sq.ft

9.0 UPVC Door and Window


Window(W1) 1 10 6 60 Sq.ft
Window(W2) 3 6 4.5 81 Sq.ft
Window(W3) 1 6 3.5 21 Sq.ft
Window(W4) 3 4.5 4 54 Sq.ft
Window(W5) 3 10 4 120 Sq.ft
Window(W6) 1 4.5 2.5 11.25 Sq.ft
Sliding door window 2 10 7 140.00 Sq.ft

10.0 Railing
50 mm dia stainless steel handrail
in 2m distance
Staircase 2 Running feet= 24 48
Terrace 1 Running feet= 131 131
Terrace 1 Running feet= 34.834 34.834
Total stainless steel railing 213.834 R.ft
Railing glass (Toughen glass) 1 Running feet= 0 0 R.ft

11.0 Colouring/Painting Works


Interior Emulsion Works (Two
11.1 coat plastic emulsion paint with
primer)
Total internal wall Paint As per inner plaster work 6134.66
Total ceiling Paint As per ceiling plaster work 3209.13
Total plastic emulsion paint 9343.79383 Sq.ft

Two coat Weathercoat paint with


11.2
one coat primer
Total external wall paint As per exterior plaster work 2795.87
Total weather coat paint 2795.874 Sq.ft

Supply and Applying 3 coats of


11.3 Chapra polish after rendering the
surface on flush door shutter
work all complete as per
specification and instruction
Main Door (MD) 1 4 8 32.00
Door (D1) 10 3 7 210.00
Door (D2) 7 2.5 7 122.50
Total coats of chapra polish 364.50 Sq.ft
Two coats of ready made Enamel
11.4 paints of approved colour over
one coats of primer painting over
properly sanded wooden surface
all
Door Frame
Main Door (MD) 1 20 0.833 16.66
Door (D1) 10 17 0.833 141.61
Door (D2) 7 16.5 0.833 96.21
Total Enamel paint 254.48 Sq.ft

12.0 Manual Rolling Shutter


Shutter SH1 1 12.5 9 112.5
Shutter SH2 1 12.083 9 108.747
Shutter SH3 1 6 9 54
Total Shutter 275.247 Sq.ft
Rate Analysis

S.N. Description Unit Quantity Rate per unit Amount

A CIVIL WORKS
1.0 EARTHWORK
1.1 Site Clearance and layout

Clearing the site by removing the bushes, trees,


concrete pavement and hard surface whatever at
site up to its root depth including the layout work,
marking the trench, construction of permanent Sq.ft 1450.3 2.75 3988.33
reference points along each grid precisely in line
and level and including construction of all
necessary staff and labor facilities.

1.2 Earthwork in Excavation

Excavation for Structures Foundation, Earth work


in excavation of foundation of structures,
including construction of shoring and bracing,
removal of stumps and other deleterious matter Cu.ft 1740.01 25.25 43935.25
and backfilling with approved Material as per
Drawing and Technical Specifications., Ordinary
soil Manually, Depth upto 3 m

1.3 Backfiling

Back filling in foundation and gardening area


approved soil obtained from the excavation at site
and stacked at site or brought from outside in
layer not exceeding 15 cm thick (compacted
thickness) including transportation of soil,
Cu.ft 1044.01 25.00 26100.25
spreading in required line and level, sprinkling
water, ramming, compacting with mechanical
rammers) , testing, etc., all complete as per
drawing, specification and instructions of the
Engineer.

2.0 Brickwork
2.1 Brick soling
Providing and soiling with first class chimney
made brick on flat in foundation and floor as per
Sq.ft 1821.95 105.00 191304.75
drawings, specification and instruction of the
consultant/Engineer, all complete.

2.2 Brick Masonry Works in 1:6 C/S mortar


Providing and laying first class chimney fired
brick one or more brick thick wall in cement
mortar 1:6 (1 cement : 6 coarse sand) in
foundation up to plinth and other specified places
in all heights and level including the cost of single Cu.ft 314.42 600.00 188652.00
or multi stage scaffolding, soaking bricks, curing,
raking joints, provision for recesses, openings,
toothing etc., all complete as per drawing,
specifications and instructions of the Engineer.

2.3 Brick Masonry Works in 1:4 C/S mortar

Providing and laying first class chimney fired


brick one or more brick thick wall in cement
mortar 1:6 (1 cement : 6 coarse sand) in
superstructure in all heights and level including
the cost of single or multi stage scaffolding, Cu.ft 3112.2909592 620.00 1929620.39
soaking bricks, curing, raking joints, provision for
recesses, openings, toothing etc., all complete as
per drawing, specifications and instructions of the
Engineer.

3.0 PCC/RCC work


3.1 PCC work

Providing and laying machine mixed Plain


Cement Concrete of nominal mix 1:3:6 (1
cement : 2 sand : 4 coarse aggregate ) for leveling
course in foundations and under floor of building,
etc. in all level with broken stone aggregate of
size not more than 25 mm of approved quality Cu.ft 91.58 450.00 41211.00
including formwork wherever necessary,
dewatering, batching, mixing, transporting,
placing, compacting, curing, including all lead
and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.

Providing and laying machine mixed Plain


Cement Concrete of nominal mix 1:2:4 (1
cement : 2 sand : 4 coarse aggregate ) for leveling
course in foundations and under floor of building,
etc. in all level with broken stone aggregate of
size not more than 25 mm of approved quality Cu.ft 301.58 470.00 141742.03
including formwork wherever necessary,
dewatering, batching, mixing, transporting,
placing, compacting, curing, including all lead
and lift, etc. all complete as per drawings,
specifications and the instructions of the Engineer.

3.2 PCC for RCC work


Providing and laying in position machine mixed
and machine vibrated cement concrete of mix
1:1.5:3 (1 cement:1.5 sand: 3 coarse aggreagate)
M20 grade for reinforced cement concrete work
using approved cement with 20 mm graded
machine crushed stone aggregate of approved
quality in various locations and heights including
transportation of concrete to site of placing,
compaction, finished to required line and level,
protection and curing, etc. all complete as per
drawings, specifications and the instructions of
the Engineer, but excluding the cost of centering,
shuttering, and reinforcement, but including the
cost of 2.5% Rheobuild SP-1 admixture or
equivalent by Weight of Cement all complete as
per drawings, specifications and instructions of
the Engineer.

Footing Cu.ft 412.5 600.00 247500.00

Column Cu.ft 543.30 600.00 325978.21

Beam Cu.ft 523.29 600.00 313975.91

Slab Cu.ft 1161.01 600.00 696608.87

Staircase Cu.ft 165.00 600.00 99002.75

Sill Band Cu.ft 107.87 600.00 64724.22

Lintel Band Cu.ft 92.60 600.00 55560.00

4.0 Formwork
4.1 Column Sq.ft 1875.04 130.00 243754.88

4.2 Beam Sq.ft 1049.96 130.00 136494.54

4.3 Footing Sq.ft 330.00 55.00 18150.00

4.4 Slab Sq.ft 3209.13 120.00 385095.94

4.5 Staircase Sq.ft 143.23 120.00 17187.10

4.5 Sill Band Sq.ft -6.04 35.00 -211.47

4.6 Lintel Band Sq.ft 363.03 35.00 12706.21

5.0 Reinforcement
Providing, assembling and placing highstrength
(TMT) deformed bars, Fe - 500grade (confirming
kg 16848.39 115.00 1937565.36
to IS: 1786 - 1985) for RCC work, including cost
of binding wires for all floors.

6.0 Flooring and Finishing Work


38mm thick P.C.C IN (1:2:4) with cement
6.1 Sq.ft 3030.85 80.00 242468.32
punning (1:1) for flooring work
Providing and laying Wall Tile as per approved
6.2 Sq.ft 806.50 295.00 237918.09
standard of manufactured country
Providing and laying floor Tile as per approved
6.3 Sq.ft 3032.85 295.00 894691.93
standard of manufactured country
Providing and laying stair marble as per approved
6.4 Sq.ft 393.87 350.00 137853.31
standard of manufactured country
Providing and laying granite as per approved
6.5 Sq.ft 42.64 350.00 14924.00
standard of manufactured country

7.0 Plastering & Punning Works


12.5mm thick cement plaster in (1:3) in ceiling,
7.1 Sq.ft 3209.13 45.00 144410.98
beams stc

20 mm thick cement plaster in (1:4) in Internal


7.2 Sq.ft 6134.66 50.00 306733.05
Wall etc

20mm thick cement plaster in (1:4) in external


7.3 Sq.ft 2795.87 50.00 139793.70
Wall etc

7.4 20mm thick cement sand plaster(1:4) on stair Sq.ft 393.87 55.00 21662.66

8.0 Railing
(50 mm dia stainless steel handrail) R.ft 213.834 1000.00 213834.00
Railing glass (Toughen glass) R.ft 0 350.61 0.00

9.0 Doors and Windows


Total salwood frame Cu.ft 37.70 6622.58 249676.17
Total solid core flush door shutter Sq.ft 322.00 650.56 209479.55

10.0 UPVC window


Window(W1) Sq.ft 60.00 900.00 54000.00
Window(W2) Sq.ft 81.00 900.00 72900.00
Window(W3) Sq.ft 21.00 900.00 18900.00
Window(W4) Sq.ft 54.00 900.00 48600.00
Window(W5) Sq.ft 120.00 900.00 108000.00
Window(W6) Sq.ft 11.25 900.00 10125.00
Sliding door window Sq.ft 140.00 900.00 126000.00

11.0 Colouring/Painting Works


Total plastic emulsion paint Sq.ft 5033.83 40.00 201353.20
Total weather coat paint Sq.ft 2095.35 40.00 83814.00
Total coats of chapra polish Sq.ft 322.00 30.00 9660.00
Total Enamel paint Sq.ft 37.70 30.00 1131.02

12.0 Manual Rolling Shutter Sq.ft 275.25 320.00 88079.04


TOTAL 10668575.5068
SUMMARY

Total Cost ( A ) 10668575.51

Sanitary Cost (5% of total cost) ( B ) 533428.78

Electrical Cost (5% of total cost) ( C ) 533428.78

( D ) = ( A )+( B )+( C ) 11735433.06

Contigences ( E )
i. Physical (5% of D) 586771.65

Subtotal ( F ) 12322204.71

VAT ( 13% of F ) ( G ) 1601886.61

Total ( F+G ) 13924091.32